TankDude
Structural
- Mar 19, 2006
- 71
I can't find anything in API650 or 653 that discusses required offset between shell vert welds and bottom plate lap welds. Specifically, regarding a bottom replacement. I have always tried to use 12" when designing and detailing new construction, and this was just a rule-of-thumb that someone told me years ago. Does anyone know of any requirements by API, and if not what sort of "best practice" might you employ? Thanks.