We are currently looking at at an elevator built in 1929-30. Along one side of the elevator, 1200 foot long, is a slip built originally to unload ships via Marine towers ... way to complicated to explain here. Long story short we are currently considering adding 24,500 metric tonnes of storage along this slip in the form of 21' dia x 70 tall cold formed steel hopper bins. The slip and for that matter the whole elevator is founded on timber piles. Its about 10 to 15 feet of fill placed over about 40 feet of clay marl, then 15 feet of clayey silt transforming into 10 feet of silty clay ending up up as 5 feet of silty sand lastly about 3 feet of mixed sand glacial till finally bedrock.
Thoughts on how far they might have driven the piles in 1929?
The only info on the piles is they were supplied locally which likely would have meant white and red pine, hemlock perhaps, maybe even red oak? ....
No info on sequence, concerned about negative skin friction.
Perelim on analysis yields axial loads in the 25 ton per pile nieghbourhood, so is close, condition aside. Thoughts?
Thoughts on how far they might have driven the piles in 1929?
The only info on the piles is they were supplied locally which likely would have meant white and red pine, hemlock perhaps, maybe even red oak? ....
No info on sequence, concerned about negative skin friction.
Perelim on analysis yields axial loads in the 25 ton per pile nieghbourhood, so is close, condition aside. Thoughts?