Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

æSlotted' Wood Roof Diaphragm

Status
Not open for further replies.

GoBizon

Structural
Nov 7, 2006
12
Original Design, all wood members, 72’ roof span (6:12 slope): 20’ monoslope truss from brg wall to girder truss, 32’ gable truss girder to girder, 20’ monoslope truss from girder to brg wall. Girder truss designs have been verified and total span is 80’. The 72’x80’ area is clear spanned in both directions with the exception of steel columns at girder supports.

Problem: Owner does not want a ‘dry’ sprinkler system.

Arch. Solution: Change insulation of roof trusses to an insulated panel atop the typical roof sheathing. However, the cost is too great for this over the entire roof area. Therefore, replace the 20’ monoslope trusses with TJIs and provide a continuous vent space at the intersection of TJI and roof truss. This creates 3 continuous ‘slots’ in the roof diaphragm: the ridge and one 20’ up the slope at each end. The wind load parallel to the trusses is 255plf at the eave.

Question: The use of continuous ridge venting seems to be a generally accepted practice. Are there any concerns with having the 3 continuous breaks in the roof diaphragm?
 
Replies continue below

Recommended for you

Yes... but not so much at the ridge where the shear is probably zero. How do you plan to transfer the shear across the other two strip openings? Unless you break up the diaphragm by adding vertical shearwall elements below, this transfer will have to be done.

Mike McCann
MMC Engineering
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor