Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. sunny7uc

    Installing Wall Pit Next To Footing

    you probably have your solution already. Jet grouting is another way to underpin and provide temporary shoring at the same time.
  2. sunny7uc

    New Piles to be installed under an existing in service Abutment

    Compaction Grouting is probably a solution you are looking for. Pin Piles/Micropiles will be probably more expensive as it will require structural slab/grade beams. Compaction Grouting can be done in phases to keep the traffic open.
  3. sunny7uc

    Liquefaction and Seismic Settlement

    Liquefaction is a concern and should not be taken lightly. liquefaction concerns can be as deep as 55-60 ft. I suggest stone columns or other ground improvement methods that fit your site constraints. You need to densify the soils so the potential of liquefaction is reduced.
  4. sunny7uc

    Wind farm job on 100m fill?

    Loike fattdad said, site characterizxation and appropriate ground improvement method will do fine. You can insllaanchors, helical piers, micropiles, Dynamic Deep Compaction, etc. depending on the soils and loads. check out www.haywardbaker.com for different site improvement methods.
  5. sunny7uc

    Solar Foundation Support

    There is a geotechnical company www.haywardbaker.com, they are a large design-build contractor. they can do dynamic compcation, helical piers, steel piles, or can provide other economical solution depending on site conditions. I had good luck with them as they do have several techniques.
  6. sunny7uc

    RAP and Responsibility

    What if the building settles as RAP was not designed to the right depth or adequate diameter was not constructed. Modulus Test/Plate Load test is meaningless without utilizing basic soil mechanics. I think Engineer of record is liable, even for all design build work...isnt that true?
  7. sunny7uc

    Vibro Stone columns

    I agree with you "dglittle" on the soil mix columns, that they need to be constructed as a "cell" element. I made no commenst about jet groutng, but sure can be used in cells smililar to soil mix columns. Stone columns shall work with simple area replacement ratio because they are not as stiff...
  8. sunny7uc

    CBR on cement-treated soils

    I have done CBR on cement+fly ash+soil mix samples, it can be done.
  9. sunny7uc

    Vibro Stone columns

    You can utilize reinforcement effect of stone columns (proven by Finite Element Analysis), you can come up with a area replacement ratio (11-20%) to reduce liquefaction risk. You may also look at soil mix colums in lieu of stone columns. I will suggest you to call Hayward Baker.
  10. sunny7uc

    Geopiers thread261-64135

    You can put a steel rod in the center or do a soil anchor between columns for uplift. Uplift capacity can be provided with any aggregate-pier system. Check out FAQs at the above refernced website.
  11. sunny7uc

    Interpretation of Vibro-replacement Stone Column data

    I just want to re-emphasize that if the design is for liquefaction mitigation, post construction CPTs and/or SPTs between the columns is warranted. Plate load tests does not tell you anything if you are mitigating liquefaction potential.
  12. sunny7uc

    Interpretation of Vibro-replacement Stone Column data

    I recommend post construction CPTs or SPTs as the best ways to check the quality of ground improvement for liquefaction mitigation. If this is for bearing a plate load test with the engineering judgement of the "geotechnical Engineer" (not the design build contractor) should be adequate. For...
  13. sunny7uc

    Liquefaction Factor of Safety

    Usually a FS of 1.1 is used to my knowledge.
  14. sunny7uc

    Geopiers thread261-64135

    You do not ned to worry abour water table, use some other aggregate pier system like Vibro Piers. It can be installed by dry bottom feed method. Checkout www.vibropiers.com or http://www.haywardbaker.com/services/vibro_piers.htm
  15. sunny7uc

    Impact Piers

    family of aggregate piers (geopiers/vibropiers/impact piers/etc...) are tested by plate load tests, normally a 36" plate load test is used. Please note that a 10 ft long pier will show you the same result as 20 ft long pier because the size of plate is too small. Therefore, make sure that...
  16. sunny7uc

    thread256-53555

    Stone columns/vibro piers/geopiers/rammed aggregate piers has same stiffness. It is a hole filled up with gravel. A simple check - take a 1 cuft of box, take 3/4 inch rock and denisfy it as much as you can - you will find that you cannot densify it much, therefore these all systems create a...

Part and Inventory Search