Does anyone know the main issues surrounding batching of different types of crude in an onshore pipeline. What additional facilities/ considerations should be made? is it generally feasible in all pipelines. The two types of crude do not differ that much; densities 800 and 850. Are there any...
We are putting together an engineering schedule for pipelines and the requirement for stress analysis came up. What as a minimum would be needed/ or is typically carried out for pipelines and why? Thank You
Does this vary much for gas?
Thanks,
Its a 20" crude line. We know what equipment to use, we're trying to determine the best way to do it! i.e. how would you stage isolation of the old section and tie-in the new section along with removing the fluid from the old and filling the new! trying to do it with the minimum number...
We are looking at options for tieing in a new (>40km)pipe section that will have been laid alongside the existing liquid line. Considering that we have to remove the fluid from the old pipe section as part of the operation are there any thoughts on how line plugging might be carried out for the...