I have a small question.
I have a main project and sub projects with tasks for each sub project. For each sub project , the duration for that particular project is wrong for some reason. It shows for example: Nov 30 3:30 PM Dec 4 2:30 AM as 10.38 days.
We are a 24hr operation . To accomodate...