Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. sudiptoghosh

    MICOM P923 RELAY

    DPC, Thanks for the reply: The voltage magnitude comes from the same relay and not from other measurement devices Pretty old installation and the chances of blown fuse is absent
  2. sudiptoghosh

    MICOM P923 RELAY

    Alsthom Micom P923 RELAY in our generator relay panel has tripped on undervoltage as seen from fault records.The relay was set to operate at 80 % voltage with a definite time lag of two seconds.Though it is showing that the relay has tripped on undervoltage in fault records , but when we see...
  3. sudiptoghosh

    69 KV GSU for 66 kv system

    Thanks to all. But the MVAR will be supplied by the generator and we operate at Lagging Power factor to supply MVAR to the grid.So if the GSU voltage is 66KV instead of 69KV with an OLTC what is the harm
  4. sudiptoghosh

    69 KV GSU for 66 kv system

    The system voltage is 66 KV and not 69 KV.Then why the GSU Voltage is 69KV instead of 66KV
  5. sudiptoghosh

    69 KV GSU for 66 kv system

    What is the advantage of a GSU transformer of 11KV/69 KV Connected to a 66KV grid.Why 69 KV is used instead of 11kv/66 KV
  6. sudiptoghosh

    TG Set load fluctuations due to grid

    Thanks for your replies.Actually the droop setting is 4 %.The DCS trends are not so fast to show the actual MW during the disturbance.The frequency had actually gone upto 52.5 Hz momentarily , as understood fron the nearby grid substation.(Two local grid substation was disconnected from the...
  7. sudiptoghosh

    TG Set load fluctuations due to grid

    We have a 18 MW generator running in parallel with the utility grid.The max generation is around 14 MW.After 4MW of internal consumption remaining 10 MW is exported to Grid. Today it was noticed that thre was a severe hunding in the TG load ie.. from 10 MW it went down to 2 MW and again picked...
  8. sudiptoghosh

    Adding a second captive power plant

    Kindly find the SLD http://files.engineering.com/getfile.aspx?folder=89b4f8b8-a619-4da0-903b-4d9b45c5a2c3&file=508301-9999-039A-c_(COLOR)_(2).pdf
  9. sudiptoghosh

    Adding a second captive power plant

    inpran, Sorry for the confusion 2) Both the generators have their own independent generator transformers.When both the transformers are in operation ,the two generators are connected to the grid through their respective GT.So it is similiar to two power plants supplying power to a...
  10. sudiptoghosh

    Adding a second captive power plant

    We have a Captive Power plant of 18 MW Capacity.The generation is at 11KV and after catering to our plant requirements the excess power is being sent to the 66 KV grid through a YNd1 66KV/11KV,20 MVA transformer bank.When the CPP is under maintenance or not operational the grid power,stepped...

Part and Inventory Search