Once did a comprehensive commissioning test of a data center that included a 300kW UPS. In order to test out everything, UPS, HVAC, etc. the contractor had to go purchase a pallet load (200) of 1.5kW heaters. All plugged in and all on high. 300kW of heat being dumped into the room. HVAC...