Is it wrong for an engineer to be the designated checker of a calculation and stamp the calculation with his seal?
Scenario:
EIT prepares calculation based on design that was directed by the PE. The PE checks the EIT's calculation. The PE then stamps the calculation.
Thanks for the input.
I am adding a new wood chip screen, and need to design the concrete foundation. I have been given the following from the screen vendor. These loads are typical 4 places.
Fvstatic = 25k
Fhstatic = 5k
Fhdynamic = 1k
I would like to do spread footings.
How do I treat the dynamic load? I know I...