Hi Guys
A design has been carried out for some bolts in a base plate & they were spaced at 90mm when the code says the minimum should be 105mm, this was missed when been checked (wasn't me)and site went ahead and installed the steelwork at the bottom of a shaft.
However the client has now...
Hi I've a plastic/polystrene mould to place in a concrete tank. The volume of the mould is approximately 15m3 and I intend to pour concrete from the bottom of this mould to the top (level with the top). Concrete will be placed evenly all around (total height of approximately 1.3m). When the...
Yea it's a very bumpy car alright!!
By dosing bund I mean concrete chamber this is just the name we have given it on site, apologies. The chemicals are going to be introduced into the water supply at this location and the concrete chamber will be used to contain any spillages. If yoy forget...
Hi Guys
I've been asked for a concrete spec for a dosing bund which will contain calcium hyprochlorite but may contain sodium hyprochlorite in the future. Using BS8500 I'm not sure which design class to go for XC3/4 or perhaps DC4 but then again I may be completely wrong with both of them, i've...
Hi Guys
I've got a lagoon which is approximately 30m in length, into this lagoon flows a 3 x 140mm PE pipes which will contain only a small amount of sludge. Is there anyway I can support these pipes on the surface of the water with say for example 5nr 1m x 1m pontoon or some other bouyancy...
Hi Guys
I was wondering if anybody would be able to tell me where I could find some good reading material and examples on how to analyse sheet pile retaining structures with multiple levels of support i.e. 2 and up!Most of the problems I will be dealing with over the next few weeks will have 3...
Hi guys, I'm using british standards and was wondering when you have a dead load (1.4) live laod (1.6) snow load (1.6) and wind load (1.2) do you calculate all of these seperate or is there a combination factor you use, i.e. do you apply a safety factor of 1.2 to them all and not work them out...
Hi hokie66, by link I mean shape code 51, so what I'm trying to ask is if we use H20 links shape code 51 at 400 centre what are of reinforcement would this provide per meter?!
Could somebody correct me if I'm wrong please, is the reinforcement area of a H20 link = 628mm2 i.e. 2 x 314,
From this I was wondering if a H20 link at 400centres was equal to 785.5mm2 or is it different because it's a link.
when working out the active pressures of a soil at a certain depth is the undrained strength Cu the same thing as c' and Su and can the formula Ka x density x z - (2 x Su x Sqrt(Ka)) be used or is a different formula needed??