If you have two points restricting the pipe in the same direction, it can not move .... you need to change the design.
See the basic rules of piping flexibility.
http://currentenergy.blogspot.com/2012/01/piping-stress-analysis.html
I am involved with a new project using european normative EN-13480.
My question is about the right cases combination based on thermal stresses.
Regards.
Hi mechanicalman11, I suggest the link below.
http://currentenergy.blogspot.com/2012/01/piping-stress-analysis.html
All the best!http://currentenergy.blogspot.com/2012/01/piping-stress-analysis.html
I know exist a very long discussion about these, but can somebody explain to me detailedly this?
For example:
Can I temporarily delete the supports in the sus case when I have lift off?
Thanks.
Pablo
Friends, thanks for your answers, the problem is very big now because the client want to use crosses (very crazy) in your project (delayed coker) for cleaning lines.
I find information about SIF in an old paper, and in conclusion is possible to use SIF of normal TEE x 1.5 that they tell me...