Thank You for your kind reply, what i equipment i shall use. I am planning to use a compressor and a re-heater (Heater) to provide dehumidified air. Will it work?
Thanks For The Previous suggestions,
I am struggling to find a feasible way of getting dry air (Dehumidified) for performing Dry Lay-Up for Stainless Steel Piping.
Dry Lay-Up is performed in-order to attain the hydro-tested pipes free of remnant water and moisture.
Can anyone please help me...
Thank U Mr.bimr,
Actually this for an Aramco Project, the service is for cooling water. This is a pipe replacement project, the previously installed pipes been badly affected with MIC. I have gone through the SAES A-007 already, the problem here is the pipes are loop formed and hence there is...
CURRENTLY I AM WORKING IN A STAINLESS STEEL PIPING PROJECT FOR THE COOLING WATER SERVICE, I WANT TO KNOW THE METHOD THROUGH WHICH DRY LAY-UP SHALL BE PERFORMED AFTER HYDRO-TEST.
EXPECTING VALID SUGGESTIONS