Ok,
Shall I put my question this way,
1 I prepaired the case for stability run
( I have 7 generators in my case)
2 saved the case for pssds4
3 From pssds4 entry point I did following;
4 perform base stability run
I choose rotor angle of generators for the channel 1 to 6
(My case has...
Hi
Can anyone tell me step by step guide to dynamic simulation with PSS/E activities for the following case,
1 Tripping of a generator
2 Three phase earth fault at a bus (say 220 kv) what are the critical clearing times that are widely used.
Big thank for your valuable post. Actualy I'm studying bulk power transmission. I'm working in National power system control centre in Sri Lanka. I'll try to find the reference book that you suggested.
Thank you QBplanner. I agree with you. You talk about North America power system. I'm dealing with Sri Lanka power system which is smaller with compare with yours.
I would like to have some idea about auto transformers. Perticularly, input voltage 220 kV, output voltage 33 kV and there is 132 kV tapping as well. This is not a three winding transformer. There are few this type of transformes in our transmision network. A name of a text book or some...
Thank you dpc, I have all the material supplied by Siemens but very large and contains thousands of pages. I'm looking for some few pages for kik start. If you know a text book based on PSS/E, it is fine I can buy it.