Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by JimmyJunior

  1. JimmyJunior

    Lighting Study

    Thank you folks. I have been doing lighting studies for a long time and I am of the opinion that a study should always be done for a large project interior (data center, air traffic control room, clean room, etc) and exterior project (parking lots, wall washing, etc). As expressed by some of...
  2. JimmyJunior

    Lighting Study

    Some technical folks where I work say that a lighting study is not necessary for new lighting system installations because human perception is subjective. Other say that the study gives you basic information about the lighting levels. I personally use AGI32 for every lighting study I do. It...
  3. JimmyJunior

    Hand Trip Control Vs Touch Screen Control

    Hello: We are in the process of upgrading our relaying system at our main substation. We are replacing all of our Westinghouse/ABB electromechanical relays with SEL relays + a SCADA system. One modification that has caused concern is the replacement of the individual 15kV air circuit breaker...
  4. JimmyJunior

    MV Surge Arrester Application?

    Hello: Short of doing an EMTP study is there any approximate method of determining the placement of surge arresters along a medium voltage aerial feeder?
  5. JimmyJunior

    Parallel Emergency Loads

    rbulsara: Initially, the 3000AF had a 1200AT plug to comply with NEC and protect the 1200A Al Feeder. This feeder services a dedicated load of HVAC equipment (smoke mode control exhaust fans, elevators, central station lighting). A 3000A busduct was installed and will feed a separate dedicate...
  6. JimmyJunior

    Parallel Emergency Loads

    Please consider the following: 1. Existing E/G system is a random access, parallel, three E/G switchgear. 2. A 3000AF drawout power breaker on E/G switchgear is presently serving a 480Vac, 1200A load using 4/phase 600MCM Al conductors. The linear distance is approx. 1000ft. 3. A new 3000A, 3...
  7. JimmyJunior

    "PE's In Federal Government" Revisited

    Last year (May, 07) I brought to the attention of this fine forum the fact that I was the only electrical PE in the federal agency branch where I work. The situation is still the same. I asked our legal department about the ethical issues involved and I am still waiting for an answer. I did get...
  8. JimmyJunior

    VFDs Application

    Hello: Can VFDs work with regular motors? What parameters should we observe? At my agency opinions are divided on this issue: VFD rated versus non-VFD rated motors. Thanks, Jimmy Junior
  9. JimmyJunior

    New FirePumps

    Recently our engineering group purchased and started installling 4 firepump assemblies in our utilities plant. Each of these assemblies consists of a firepump controller, a pump and a 250HP motor. The decision to replace the older firepumps was made because the older pumps were installed in...
  10. JimmyJunior

    TVSS Protection

    Hi: I have a question about application engineering in the context of interior double-ended substations. To wit, is it warranted to install TVSS protection on the secondary sides of double-ended substations between the transformer secondaries and the main secondary breakers (480Y V or 208Y...
  11. JimmyJunior

    Daisy Chain vs Feeder Bus

    Our principal administrative building is a 4 story office building served by six substations. These consist of 28 year old Westinghouse 12.47kV/480Y/120V and 12.47kV/208Y/120V double-ended substations. All of the transformers except for 3 are Westinghouse originals. All of the substations are...
  12. JimmyJunior

    Belated Transformer Differential Protection

    At our federal agency we have at our Main Substation two 69/12.470kV, 15/20MVA, transformers feeding two walkin breaker lineups. Each lineup is fed from one transformer and the two lineups are connected by a NO tie ACB. Presently the transformers are protected by S&C Fuses. Soon S&C...
  13. JimmyJunior

    Power Systems Analysis - Basis for Design and Maintenance

    Hello: I have been involved with Power System Analysis since 1976, before the advent of the PC. Back then we used main frames to perform short circuit calculations. Where I work I am the only electrical engineer (and only EE with a PE) that has this kind of expertise and experience. My...
  14. JimmyJunior

    Domestic Water Pump Torque Curves

    Hello: I am an electrical engineer trying to convince the folks in my group that when replacing a 1940s vintage 50hp pump motor with a modern energy efficient replacement, a lot more has to be done than just supplying the nameplate data. I think that proper engineering practice would dictate...
  15. JimmyJunior

    PE's In Federal Government

    Hello: I work for a Federal Agency as a Senior Electrical Engineer and have been a PE for 27 years. Our engineering department is multi-disciplined. All of our Branch Managers are PEs also. There are presently several electrical engineers working here, but I am the only PE. Our Agency does...

Part and Inventory Search