I have a task in my project that involves three people, a Consultant, a Manager and a Director.
The task lasts for 40 days and requires the following levels of time from each of the above resources; Consultant 20 days, Manager 15 days and Director 5 days.
How should I best represent this in my...
Looking for some MS Project guidance.
I am running a project and have 8 IT consultants (all charged out at the same rate) covering different functional areas of a piece of software.
My question is;
Should I create 8 different resources or one resource with 8 units.
Creating 8 resources is a...