Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by Dennis1234

  1. Dennis1234

    Setting Planned Finish Date based on Remaining Work

    Thanks for your reply, IRstuff. No, I haven't yet baselined the project yet. Usually I would before work began, but in this case work on part of the project had to begin before I could confirm the plan for other modules. I was actually doing one last resource leveling to set the planned dates...
  2. Dennis1234

    Setting Planned Finish Date based on Remaining Work

    I am trying to use Actual Work and Remaining Work to adjust the planned Finish date of a task in progress (with an Actual Start date) when resource leveling. However, when I level, project seems to set the planned Finish date based on the Remaining Work from the Actual Start date rather than...

Part and Inventory Search