  1. Dennis1234

    Setting Planned Finish Date based on Remaining Work

    Thanks for your reply, IRstuff. No, I haven't yet baselined the project yet. Usually I would before work began, but in this case work on part of the project had to begin before I could confirm the plan for other modules. I was actually doing one last resource leveling to set the planned dates...
  2. Dennis1234

    Setting Planned Finish Date based on Remaining Work

    I am trying to use Actual Work and Remaining Work to adjust the planned Finish date of a task in progress (with an Actual Start date) when resource leveling. However, when I level, project seems to set the planned Finish date based on the Remaining Work from the Actual Start date rather than...