Many thanks for the responses. It is really useful to get some feedback this being one of my first threads. It is an industrial or light industrial unit i think. Not sure about crances or other equipment though.
Hi - many thanks for the reply. I was not planning to do any works on the equipment. The query was raised by a building survey and I was just asked to comment on what it was!
Can anyone shed some light on this picture I was asked about and give me some information. It looks like an old battery bank but I have not seen this type of cell before.
Any help appreciated! Many thanks
Can anyone help - I am upgrading a building supply to 1000KVA at 400V and installing new switchgear and a standby generator. The client has a spare generator rated at 1250KVA. The electrical contractor says the size of the main switchgear should be based on the rating of the generator not the...
I need to connect a 400V generator to a main switchboard and I think it would be better to use parallel multicore 4x185mm2 or 6/8x95mm2 XLPE/SWA/LSF armoured cables in underground ducts - but I've had some feedback that this is not a good idea and it is better to use single core cables.
Can...
I'm looking at an automatic transfer sysmtem to swap between two 400V power sources ("normal" mains supply and a standby generator) using 2 interlocked ACB's.
My question is what side of the main ACB device should we put the voltage sensing relays?
I've been told we should not put...
OK, where you've got a dedicated transformer it is common to earth the source neutral at the first point in the LV system where the neutral is terminated - the main LV switchboard.
I agree with previous answer that sizing should be done to ensure the fault withstand current can be stood for...