INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Looking for opinions on the best wa

Looking for opinions on the best wa

Looking for opinions on the best wa

(OP)
Looking for opinions on the best way to analyze the following situation:

One-way concrete slab reinforced top & bottom both ways, 6 1/2" thick with 1" Kalman topping (7 1/2" thick total).

Slab supported by WF steel beams @ 6'-8" O.C. with top flange embedded in slab (no shear studs).  Beams frame into WF steel girders spaced @ 20'-0" O.C. with top flange embedded in slab (no shear studs).  Beams & girders frame into steel columns on a 20' by 20' grid.  Slab designed (and confirmed) for 500 psf LL and 100 psf DL.

The problem:  the floor is used as a warehouse area, using heavy-duty storage racks typically used on slabs-on-grade.  Obviously, the storage rack legs create high point loads on the slab.  How can I get accurate results for shear, moment, deflection based on this point loading.  I need to know if the floor is being overloaded.

It seems to me that applying the loads over a 1' strip of slab and analyzing as a 1' wide conc. beam would be way to conservative.  Am I right or wrong?  Any suggestions?

RE: Looking for opinions on the best wa

AASHTO Specsfor Highway bridges cover point loads on concrete slabs.  Also see many concrete texts,e.g.,"Design of Concrete Structures, Nilson & Winter,11th Ed.

Be sure to check slab for punching shear.

Frank hartzell
frank.hartzell@jacobs.com

RE: Looking for opinions on the best wa

To space the point loads by hand, I would agree with Frank and simply use the AASHTO equation:

The concentrated load is spread over a distance E

E = (4 + 0.06 x S)  but not more than 7 feet (or, I would add, the center to center spacing of the posts).

S = span, ft.\

Alternatively, you could use a finite element analysis on the slab, modeling the beams and girders, and get moment contours.

In either case, you should check punching shear through the slab per ACI 11.12.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close