Drained vs. Undrained: Reduce the Load on Clay from Existing Condition
Drained vs. Undrained: Reduce the Load on Clay from Existing Condition
(OP)
Example soil profile:
0-15' Sand
15-20' NC Clay
20'+ Sand
You excavate to 10'. Replace with material that weighs 1/2 of much as the excavated material.
Can you assume the clay layer will behave as drained? It seems like to me it would partially depend on how much time is between the excavation and the replacement?
0-15' Sand
15-20' NC Clay
20'+ Sand
You excavate to 10'. Replace with material that weighs 1/2 of much as the excavated material.
Can you assume the clay layer will behave as drained? It seems like to me it would partially depend on how much time is between the excavation and the replacement?
RE: Drained vs. Undrained: Reduce the Load on Clay from Existing Condition
If you reload you will stop some some if not all the heave.
RE: Drained vs. Undrained: Reduce the Load on Clay from Existing Condition