INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Eccentric loading of a channel

Eccentric loading of a channel

Eccentric loading of a channel

(OP)
A C15x40 channel framed as a beam supports a load from an HSS4x4 tube column. The column load is axial and wind load lateral, parallel to channel length. The tube column is connected to the channel with bolts through the web, with the tube against the outer face (opposite the toes of the channel). The top of the channel is also loaded with equipment, whose loads are of a similar magnitude to the point load from the tube steel post, (but are distributed instead). Does this loading situation warrant any special analysis because the centroid of the post is 2" from the outer face of the channel? The channel is braced by other horizontal steel framing 2' away on one side and 4' away on the other.

I realize that the loads' magnitudes are always a factor, but in this case I'm not seeing the reason for any special concern, as it's pretty common (I think) to connect to a structural channel by bolting to the outside face.

I've analyzed this platform in RISA-3D, and the channel was found to be adequate, but I made no special effort to model this specific connection detail.

Without going into more specifics, does this strike you as a problem?

RE: Eccentric loading of a channel

The shear center of the channel is probably not far from the center of the HSS, so it does not sound like a problem.

RE: Eccentric loading of a channel

Agree with BAretired. Remember, the shear center of a channel is actually on the side of the channel web where your tube is positioned.

DaveAtkins

RE: Eccentric loading of a channel

A C15x40 shear center is 0.767" outside the web. For a 4x4 tube your theoretical eccentricity is 2" - 0.767" = 1.23".

There is inherent stiffness in the tube so it might be surmised that the channel doesn't "feel" the eccentricity and the tube simply sucks up the bending back into itself (i.e. the axial load sort of flows into the outer tube flange against the channel) and this is also due to the fact that the channel may have very little torsional stiffness anyway - but here is a bit of effect that will occur there.

It could be modeled to test how much effect it has.

RE: Eccentric loading of a channel

It would be prudent to laterally brace the channel at the point of contact with the HSS to prevent it from moving sideways. With that precaution, rotation of the channel is prevented by the stiffness of the HSS.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close