SPT of zero
SPT of zero
(OP)
Hi Interesting - or not, question. If you had a SPT of zero quoted for loose sands at depth (several metres down but in the influence zone), how would you correlate that to a friction angle or allowable bearing pressure ultimately? its a simple pad, nothing serious on it in our case. How would you go about solving that? As we cant even correct the N value for overburden - but it has several metres of soil above it of more reasonable strength.
RE: SPT of zero
We need more information.
RE: SPT of zero
RE: SPT of zero
RE: SPT of zero
Isn’t a really a concern specifically. Pressure applied at ground only around 30kpi. The zero spt is about 5-6m Down. I don’t really have huge concerns on this one I suppose. But it was more of general question when we get these readings. For simple things like this we use simple correlation charts, which typically give an increase in stress for 25mm settlement. Albeit we can accept more. And for things like this we may only have a borehole with spt readings.
RE: SPT of zero
On most sites where I have encountered this condition, the recommendation has been either to surcharge the site and wait for settlement to occur, or to use a deep foundation system or ground improvement. All options come with a cost, that the owner usually does not like.
RE: SPT of zero
Also, MTN is correct, settlement usually governs. If this is a large wide slab then your bearing pressure is likely pretty high. Your bearing pressure which results in 25mm settlement will be your minimum of the 2.
RE: SPT of zero
For others Maybe I needed to be clearer in my question. My question really was assigning parameters from spt tests when we get a reading of zero. Principally in deeper soils. And what approach you to take. They doesn’t involve expensive needless piling or unfeasible ground improvement. Obviously I am not talking about multi-storey buildings here.
RE: SPT of zero
RE: SPT of zero
RE: SPT of zero
RE: SPT of zero
Not judgmental, just sarcastic. We all see too many engineers that don't actually look at the situation in front of them.
RE: SPT of zero
RE: SPT of zero
RE: SPT of zero
RE: SPT of zero
Shear box is one way, triaxial testing is another, the issue with lab methods is you can get a shelby tube of silty fine sand but its not truly undisturbed, so you would most likely reconstitute the sample to the void ratio you measured. A field vane with increased rate of rotation is another way in granular soils.
I work with liquefiable silty sand tailings deposits and the tailings industry is starting to understand, due to all the failures of late, that you can't assign a friction angle to saturated very loose granular material. A comparison for the shear strength of granular materials related to relative density is illustrated in the chart below.
RE: SPT of zero
Two things to consider when working with this type soil:
1) Say a "long" point-bearing piling can support very heavy loads because surrounding soil provides lateral bracing along length of the pile.
Would you consider this pile to be laterally braced for the portion of it's length that passes through a "thick" layer of soil where N = 0?
I would say "no", regardless of that layer's other soil properties.
2) If an underground layer of soil with N=0 was below the water table, it is likely more of an incompressible, viscous pressurized fluid with friction angle essentially zero.
The incompressible pressurization supports TigerGuy's experience that this layer does not cause problems (for reasonable applied loads) except for slow settlement (as increased pressure caused by the applied load reaches equilibrium with soils that contain it).
RE: SPT of zero
RE: SPT of zero
MTN your reference shows for an SPT of 1 in rounded uniform sand, Dunham would give a phi of 23 degress = (12*1)^0.5+20. Do you honestly believe that?
GG1 nailed it, I think the issue really stems from the inadequacy of SPT to determine the strength of very loose material. These materials need CPTs.
RE: SPT of zero
RE: SPT of zero
I don’t think anyone does a great job addressing this, in text or in this forum (no one has specifically given a general rule of thumb), for a reason! It’s hard to nail down an actual value that you can argue is even likely 80% correct. Those formulas are all over the place. All you can is play with the value, see how it effects your analysis, evaluate it’s weight in your design, and make an educated decision.
RE: SPT of zero