Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
(OP)
I wanted your folks opinion on something. I was reading ASIRI (2012), I came across this subject. In Mexico, after the Spanish Conquest, the Spaniards build large structures, unfortunately, the soil beneath was Volcanic Saturated Clays and Compressible. Water Pumping from Deeper Layers was resulting in Settlements of several metres (as per the document, I guess failure at that point). The solution implemented was "Overlapping Piles". The already old piles had Additional Piles Installed in between, which reached down to suitable stratum (unlike the old piles which terminated early). My question is, How did they install these Piles? The structure is already present on Top, did they make holes in the Slab or Something? Has anyone here come across installation of Additional Piles AFTER the structure was built?
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
They would have had to install piles through the slab if the piles were to extend beneath the entire footprint.
Or maybe they supported the perimeter on piles and didnt need to go beneath the slab. Installed them from the exterior.
There are many buildings which have had piles installed after the building was built. I have been involved in one such project a few months back.
You are changing a building which was meant to be ground bearing to now being supported on piles. The previous slab was not designed to perform in this way and the main issue is connecting the piles back to the slab. Often you need to install an additional reinforced slab above the old slab.
In the instance above the piles appear to be acting more like rigid inclusions than actual piles that transfer load to deeper stratum. This is because there is no connection between pile A and B.
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
Fortunately, if you had to install piles inside an existing building today there's a chance you can use low clearance drill rigs to install them instead of digging by hand.
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
There of course is some load transfer but the design intent is also to benefit from the increased composite stiffness of the ground as a whole. This is something that piles dont do.
There is also no structural connection to the slab. If this was a new building placed on RI, there would be a load transfer platform (gravel raft essentially) to spread the load "evenly" onto the RI.
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
RE: Installation of Piles AFTER Structure Built / Overlapping Piles Configuration
@MotorCity The Piles, Both A and B, are within the Zone of Influence of the Structure, lets say 2B for a width of 10m, so being present within 20m (within the layers), they will naturally resist oncoming loads (of any kind vertical, lateral, etc. it's nature. Also, the denser medium always contributes more (concentration) than the less denser medium, ie. Concrete>Sand. when Concrete fails, more load goes to the sand, etc.
@MTNClimber The story is centered around people creating Rigid Inclusions without realizing they created Rigid Inclusions. In terms of element, they are exactly like piles but much smaller and they are NOT connected to the Base Plate of the structure. They have a layer called the "Load Transfer Platform" between them and the structure. It serves 2 purpose, 1) transfer the load between the soil and the RI's (unlike Piles which traditionally are meant to carry all the load) and 2) Absorb the Arching Effect from the Resistance of Rigid Inclusions. Rigid Inclusions when resisting load have an effect on the soil above them, i.e. imagine arches being formed in the soil above. If the RI are more efficient? The Arches will be more pronounced or larger. If the LTP is too thin, you will have bending in the slab and heave like effect on the surface. Since there distribution of load between the soil and the RI, this is a Soil Improvement Technique and also quite Cost Effective even proving to be cheaper than Stone Columns most of the time.
My confusion was in the story that, the structure was already built with piles extending to -10m let's say. Then they created New Piles from -10m till -20m while the structure was still Standing! In between the old piles and that in a way was fascinating.