INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

FMEA - DFMEA and PFMEA - nobody knows how it works

FMEA - DFMEA and PFMEA - nobody knows how it works

FMEA - DFMEA and PFMEA - nobody knows how it works

(OP)
I’m curious to see others experience with the FMEA process per AIAG, under the broad scope of the APQP process.

I am under the impression that companies say they align with this to be compliant, however it’s has been my experience that the subject is often very misunderstood. What typically ends up happening is engineers will argue and debate and then finally settle on something no one agrees on. I am amazed how few have studied official process per AIAG, or even know about it. Most try to tackle with their own internal logic, which can be a good trait, but not necessarily aligning with the process.

Is this another topic like GD&t, where it is so confusing that it ends up convoluted and being boiled down to an incorrect simplicity, that often just gets pushed under the rug, due to the investment cost (time, money, interest) of learning it properly?

RE: FMEA - DFMEA and PFMEA - nobody knows how it works

One of the problems with FMEA et.al. is that often on one side you have people that have studied the AIAG to death but have never had to apply it so something that they were making, and on the other side you have people that have been making a product for decades and are trying to figure out which data needs to go where.
They are simply speaking different languages.
IF the two sides work together from the start (not just throwing things over the wall at each other) you can actually get it done.
I have worked with aerospace companies that have their own inhouse systems for things like this. Those can be a nightmare.

= = = = = = = = = = = = = = = = = = = =
P.E. Metallurgy, consulting work welcomed

RE: FMEA - DFMEA and PFMEA - nobody knows how it works

In my experience, historically most of these analysis are done by a small group of number crunchers, locked in a closet in the basement and isolated from the project team at large.

The analysis are done because they are a contractual deliverable, not because management has bought in to the potential value they could add.

They are started too late, long after the analysis results could be used as design inputs.

RE: FMEA - DFMEA and PFMEA - nobody knows how it works

I've actually been part of a few good, effective DFMEAs and PFMEAs. Like most processes, it's about as good as the people executing it.

At a minimum, it's important that the effort be led by someone knowledgeable of the FMEA process, and that the team include designers and/or process people directly involved.

Part of FMEA competence is recognizing the difference between "D" and "P". If you're throwing in "what if they make it wrong" into the DFMEA ("D" = "design"), then you're doing it all wrong. Likewise, design should not infiltrate the process side.

The places I did FMEA had clearly documented criteria for scoring. The importance of this can not be overstated.

The fact that doing FMEAs is an epic drag can also not be overstated.

RE: FMEA - DFMEA and PFMEA - nobody knows how it works

We used to dread doing FMEAs until one day they sent over a senior manager who happened to be rather good at FMEAs. He showed us how to use them in a sensible fashion, rather than as a box ticking exercise.

At one company I had a coworker who had worked in aviation, and he practically had a stroke when it was announced that we needed to do an FMEA. He then described how they did it in aerospace. It was almost exactly the opposite of what I'd been shown, basically bottom up instead of top down.

Cheers

Greg Locock


New here? Try reading these, they might help FAQ731-376: Eng-Tips.com Forum Policies http://eng-tips.com/market.cfm?

RE: FMEA - DFMEA and PFMEA - nobody knows how it works

umatrix,

I have never done FMEA.

I have worked with people who were rigidly process driven. A process like FMEA is presented as a set of procedures. You start from step one. You do steps two and three and so on until you reach the fourteenth and final step. You are now done, and you can stop working, and file the report somewhere.

It would be a shame if thinking about the data, studying the results, and making decisions were not written up as part of the procedure!

--
JHG

RE: FMEA - DFMEA and PFMEA - nobody knows how it works

IME DFMEAs are standard engineering process. Identify and rank failure modes then analyze or test accordingly to mitigate those failures. It takes the ambiguity out of all downstream analysis and testing, and clearly documents WHY or why you are NOT making critical design decisions or expensive bits of analysis or testing. Given our legal climate stateside, I would NOT want to release any design not covered 100% by a DFMEA. I wouldn't say completing them is thrilling but team reviews are usually educational when you have good dialogue amongst reviewers and worth mentioning as a training opportunity for junior engineers. The biggest issue I see with DFMEAs is that some companies don't store and iterate them, so engineers are left to waste hours creating from scratch rather than simply tweaking the 30 year old DFMEA that's 95% appropriate.

As to PFMEAs, I usually ask suppliers for them but leave the necessity up to others. At previous mega-corps every supplier completed PFMEAs regardless of part volume. In the small consultancy world now the customer often doesn't care and suppliers try to minimize costs for small customers by skipping the documentation. Ultimately that's their decision for me to document, not mine to make. The DFMEA covers me, the PFMEA covers the customer and supplier.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close