Creosote
Creosote
(OP)
We are executing a project requiring the replacement of stop logs at the water intakes. What is a suitable replacement(= to or greater than) creosote lumber? Creosote was specified in the engineering but has a 4 mo. turnaround which is not feasible for our schedule.
RE: Creosote
For other options, see AWPA Standard U1.
FWIW, I would go with 1.25 lb/ft3 or UC-5C.
www.SlideRuleEra.net
RE: Creosote
https://nj.gov/health/eoh/rtkweb/documents/fs/0517...