Resourcegroups and resources
Resourcegroups and resources
(OP)
I want to add resources in my projectplanning in this way:
1 Tasks are assigned to specified groups of engineers for example: primairy Engineers
2 In this way I want to keep an overview of the totaal capacity for this group.
3. In later stadium the tasks are assigned to 1 person(name) so I can see the individual workload
4. But when I do that I lose workload of the group and I want both (workload for the group and the individual)
How do I do that? I tried with adding both Group and name, but that doubles the workload of the task!
Please help, kind regards
Tony
1 Tasks are assigned to specified groups of engineers for example: primairy Engineers
2 In this way I want to keep an overview of the totaal capacity for this group.
3. In later stadium the tasks are assigned to 1 person(name) so I can see the individual workload
4. But when I do that I lose workload of the group and I want both (workload for the group and the individual)
How do I do that? I tried with adding both Group and name, but that doubles the workload of the task!
Please help, kind regards
Tony
RE: Resourcegroups and resources