INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Reference for chisel and bailor method against the dynamic impact for piling work.

Reference for chisel and bailor method against the dynamic impact for piling work.

Reference for chisel and bailor method against the dynamic impact for piling work.

(OP)
Hello,

I am doing the piling work using chisel and bailor method with rigid gantry platform. The gantry has two pile grid with 7.5m length and 15m width. The gantry has 2 A-frame to do chisel the pile simultaneously (Photo is attached for reference). My client has given the NCR to stop the piling work simultaneously and we have to do the individual pile after the completion of 24hrs and that is causing us time loss for my project. I Need to get justification towards the quality of boring do not get hampered due to Chisel and bailor method as against piling rig.

I have the reference for pile boring using rotary rig from FHWA for Drilled shafts (Construction procedure and LRFD design methods)
The manual FHWA for Drilled shafts (Construction procedure and LRFD design methods) stated that vibration due to driving of piles immediately adjacent to freshly placed pile concrete is not harmful. Also minimum concreting radius establishment not required.
In accordance with FHWA manual no need to wait for 24 hours after concreting work to start drilling of adjacent pile.

I dont have any reference for chisel and bailor method against the dynamic impact. kindly requesting to share any reference to tackle this problem to aviod the time loss?

Attached pile gantry image for ready reference

Vinothkumar S
Geotechnical Engineer

Replies continue below

Recommended for you

RE: Reference for chisel and bailor method against the dynamic impact for piling work.

(OP)
Hi,

I have found these reference for my thread.
Reference are given the attachment.

As we all well known for the spacing of pile for construction which listed below
1.IS 2911-part 2/2010 – for socketing pile minimum spacing 2.5D section 6.6
2.IS 14593 -1998 - for rock socketing pile minimum spacing 2.5D section 6.10
3.BS EN 1536 - The center to center distance for bored piles produced with a time-difference less than 4 h should be at least four times D or W with a minimum of 2 m. Sec 8.2.1.12
4.Geo Publication 1/2006 – Minimum spacing of the pile sec 7.2.

Vinothkumar S
Geotechnical Engineer

RE: Reference for chisel and bailor method against the dynamic impact for piling work.

(OP)
The referencee is taken from the Code of Practice for Foundations 2017 book section 5.4.5 page no 68 is attached for your ready reference.

Vinothkumar S
Geotechnical Engineer

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close