ASCE Curves for Engineering Design Fees
ASCE Curves for Engineering Design Fees
(OP)
Good afternoon, does anyone have a copy of ASCE's current Curves A and B for Estimating Engineering Design Fees as a % of Construction Costs that they can share?
RE: ASCE Curves for Engineering Design Fees
According to this webpage, ASCE MOP 45 no longer includes "fee curves": https://standards.globalspec.com/std/1551027/ASCE%.... Thus, there are no "current" fee curves.
Further internet sleuthing indicates a serious problem with using the curves, namely that the curves are outdated and lead to fees that are too low. For example: https://ascelibrary.org/doi/10.1061/%28ASCE%290742... and https://www.enr.com/articles/13149-stagnant-percen...
The last time I had a client suggest using the ASCE curves was about 1985. So, I say, good riddance.
Fred
============
"Is it the only lesson of history that mankind is unteachable?"
--Winston S. Churchill
RE: ASCE Curves for Engineering Design Fees
RE: ASCE Curves for Engineering Design Fees
The tank design fee (no bidding or construction services included at this point) worked out to about 3.5% of construction, while the pumping station fee worked out to about 11% of construction. The water district's chief engineer gave me a really hard time over this because he thought both fees should be right at the "magic 6%" that everyone touted back then. This was the first and only time he did this to me. All the other times, he was pretty easy to work with.
I first explained that I can design a water tank pretty cheaply because tanks are simple (thus easy to design from a civil perspective), contain lots of steel (thus relatively expensive to construct), and the structural design is delegated to the tank fabricator's engineer. I also mentioned that the fees for the previous half-dozen tanks I had designed for him were all in the ballpark of 3%-4% of construction. I further explained that pumping station design is expensive because it's far more complicated: the pumps are relatively cheap compared to engineering required to select the correct pumps (i.e. water modeling and browsing paper catalogs) and multiple disciplines were involved, including architectural, electrical, and structural. He still didn't buy it.
Then, I explained that with the 3.5%/11% fees I had come up with, the total cost to the water district would be less than if both fees were 6%. This he bought.
Fortunately, I had prepared both explanations before meeting with him.
I have run across a few other people in government who only remember the "magic 6%" and forget that the curves are actually curves and that the 6% is for a limited scope of work (i.e. design) for a relatively simple project of a specific size and that it doesn't include things like preliminary studies, surveying, geotech, etc. In today's world, we now have storm water plans to prepare, more extensive environmental documentation, and bunch of other stuff that the curves did not address. Even simple projects are complicated now, which means that any type of published fee curve would hurt us more than help us.
I have worked mostly on the public works and industrial sides of civil engineering, so I have generally been able to get the fees I need to do the work right. With good documentation, such as a detailed work breakdown structure with hours assigned to each task, I rarely get signification push back on fees. I often have to trim a little, but I have never had to trim a lot. I do understand the difficulties in the development market, even though I have done very little there. However, at my last firm we had a group that did only subdivisions. The top couple engineers in this group were almost always able to get reasonable fees from developers. The secret was working mostly for medium to large and well-funded developers that they had "trained".
============
"Is it the only lesson of history that mankind is unteachable?"
--Winston S. Churchill
RE: ASCE Curves for Engineering Design Fees
Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?
-Dik
RE: ASCE Curves for Engineering Design Fees
RE: ASCE Curves for Engineering Design Fees
And it gives a perverse incentive to not use an efficient design. I've had clients question a fee because the bids came in low. Never the other way, though.
We do complicated multi discipline projects. And some PM from the client will say, "Joe's Garage Engineering did this curb and gutter project for 6% of the construction fee, so lets start from there and negotiate down."
Some of our offices, in high priced locales get $8000 a sheet, but we can get by at $4000.
RE: ASCE Curves for Engineering Design Fees
RE: ASCE Curves for Engineering Design Fees
Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?
-Dik
RE: ASCE Curves for Engineering Design Fees
Fortunately for me, every fee estimate I have ever produced over the past 40 years or so has been based on a detailed work breakdown structure and estimated efforts for each and every task I and my team would have to perform, plus subconsultant and other non-labor costs, etc. I have prepared fee estimates ranging from $360 (for 3 hours of my time...I'm not kidding) to nearly $3M. I have been pretty successful over the years (1) getting a reasonable fee and (2) performing the work at or under budget. Not always, but most of the time. I have had a harder time meeting schedules due to nearly always having a >100% workload (and sometimes >>100%), but that's a whole 'nuther topic.
============
"Is it the only lesson of history that mankind is unteachable?"
--Winston S. Churchill
RE: ASCE Curves for Engineering Design Fees