NDT not done before Hydrotest
NDT not done before Hydrotest
(OP)
For some reason, NDT was not done or carried out less than stated in ITP for a given equipment/facility.
However, equipment/facility was successfully hydrotested, and operated for almost 2 years without any incident.
Considering that NDT was not fully completed or not compliant to Code requirement, should NDT be re-visited or be re-done, again?
Please consider the equipment/pressure vessel/piping/facility was successfully hydrotested and operated for almost 2 years now.
Thank you.
However, equipment/facility was successfully hydrotested, and operated for almost 2 years without any incident.
Considering that NDT was not fully completed or not compliant to Code requirement, should NDT be re-visited or be re-done, again?
Please consider the equipment/pressure vessel/piping/facility was successfully hydrotested and operated for almost 2 years now.
Thank you.
RE: NDT not done before Hydrotest
Steve Jones
Corrosion Management Consultant
www.linkedin.com/in/drstevejones
All answers are personal opinions only and are in no way connected with any employer.
RE: NDT not done before Hydrotest
luis
RE: NDT not done before Hydrotest
Hydrotesting is done to mimic the severest condition of operation. NDT in 99.99% of the time, does not in itself certify a facility.
There is no penalty by the Code if any NDT was not done or not done at all, unlike pressure testing which is compulsory and would entail numerous penalties and additional safeguards (“golden weld”) if pressure testing is not carried out.
An owner can choose to reduce to zero the cost on QA/QC by not carrying NDT and go straight to hydrotesting. This of course carries a huge risk of failing the pressure testing, but it is an option available to Owner.
Some may say “Not all defects can be found by hydrotesting” which I completely agree. However, the same can be said about NDT/RT, too. Not all defect can be found via 100% RT. Lack of fusion (at certain planar), lamination, fatigue potential, are not discoverable via RT.
RE: NDT not done before Hydrotest
RE: NDT not done before Hydrotest
If there are defects, consult with the client's inspection team regarding the next scheduled shutdown. Share the NDT reports with them.
Plan the next shutdown / on-stream / external / internal inspection accordingly.
DHURJATI SEN
Kolkata, India
RE: NDT not done before Hydrotest
Make use of the earliest opportunity to complete the NDT requirements. Pray you do not encounter any surprises!
RE: NDT not done before Hydrotest
Steve Jones
Corrosion Management Consultant
www.linkedin.com/in/drstevejones
All answers are personal opinions only and are in no way connected with any employer.
RE: NDT not done before Hydrotest
luis
RE: NDT not done before Hydrotest
No, the owner cannot.
The owner can stipulate NDT in excess of code requirements but they cannot reduce code mandated NDT requirements.
The owner would then "own" a piping system that is non-compliant with the relevant code.
NDT and hydrotesting are done for a reason - predominantly safety.
Hypothetically, you had an incident tomorrow and someone was seriously injured or died and it was discovered you had knowingly operated a plant that didn't comply with the relevant code for 2 years.
The lawyers would be dancing for joy and rubbing their hands together.
And if you didn't know and it was only just discovered it is a very, very poor reflection on the Quality department associated with this facility.
Good luck !
RE: NDT not done before Hydrotest
The point is this: which is more supreme. The NDT or the pressure testing?
Which act(s) actually certify, validate the integrity of a facility: the NDT or the pressure testing?
ASME B31.3 allows "closure weld" procedure for waiving of hydrotest, or more popularly known as "golden weld".
Now reverse that context.
RE: NDT not done before Hydrotest
The things must be done criteriously and complemented, for waiving of a hydrotest, sometimes we have a "golden weld" who is checked with complementar NDT tests such as UT or RX and others. And in your initial post it was not clear that your question was hypothetical again I hope my star would help you to be careful.
luis
RE: NDT not done before Hydrotest
The code requires both to be completed and you have not completed both.
Now, you seem to be " hypothetically" trying to find loopholes to achieve your end result.
There is only one way to resolve this, conduct the required NDT and if no issues you are home safe with a code compliant piping system.
If there are issues you will have to repair or remove welds and that then will require a new hydrotest.
RE: NDT not done before Hydrotest
Best regards - Al
RE: NDT not done before Hydrotest