Miami Pedestrian Bridge, Part XIV
Miami Pedestrian Bridge, Part XIV
(OP)
A continuation of our discussion of this failure. Best to read the other threads first to avoid rehashing things already discussed.
Part I
thread815-436595: Miami Pedestrian Bridge, Part I
Part II
thread815-436699: Miami Pedestrian Bridge, Part II
Part III
thread815-436802: Miami Pedestrian Bridge, Part III
Part IV
thread815-436924: Miami Pedestrian Bridge, Part IV
Part V
thread815-437029: Miami Pedestrian Bridge, Part V
Part VI
thread815-438451: Miami Pedestrian Bridge, Part VI
Part VII
thread815-438966: Miami Pedestrian Bridge, Part VII
Part VIII
thread815-440072: Miami Pedestrian Bridge, Part VIII
Part IX
thread815-451175: Miami Pedestrian Bridge, Part IX
Part X
thread815-454618: Miami Pedestrian Bridge, Part X
Part XI
thread815-454998: Miami Pedestrian Bridge, Part XI
Part XII
thread815-455746: Miami Pedestrian Bridge, Part XII
Part XIII
thread815-457935: Miami Pedestrian Bridge, Part XIII
Part I
thread815-436595: Miami Pedestrian Bridge, Part I
Part II
thread815-436699: Miami Pedestrian Bridge, Part II
Part III
thread815-436802: Miami Pedestrian Bridge, Part III
Part IV
thread815-436924: Miami Pedestrian Bridge, Part IV
Part V
thread815-437029: Miami Pedestrian Bridge, Part V
Part VI
thread815-438451: Miami Pedestrian Bridge, Part VI
Part VII
thread815-438966: Miami Pedestrian Bridge, Part VII
Part VIII
thread815-440072: Miami Pedestrian Bridge, Part VIII
Part IX
thread815-451175: Miami Pedestrian Bridge, Part IX
Part X
thread815-454618: Miami Pedestrian Bridge, Part X
Part XI
thread815-454998: Miami Pedestrian Bridge, Part XI
Part XII
thread815-455746: Miami Pedestrian Bridge, Part XII
Part XIII
thread815-457935: Miami Pedestrian Bridge, Part XIII
RE: Miami Pedestrian Bridge, Part XIV
The top chord and diagonals shrinks/creeps as well. So you have to look at the relative movement/shortening. Also, there is no significant restraint from the joints or top chord. If the bottom chord shrinks relative to the rest of the truss, it will just camber up. The creep and shrinkage does not create a significant shearing force at the end joints.
You can call it a truss or frame (although by far, the stiff load path is the truss). It doesn't mater. You don't have restraint from the top chord to act as enough of a strong back to create significant shears. Even if you had a full web, a girder just typically cambers with PT in the bottom flange and this structure has less internal restraint than a girder.
Even with a vierendeel, the truss will still cambers. The verticals may get high bending curvature if the chords are much stiffer in bending than the verticals and you get differential creep/shrinkage. But in our case, the diagonals are very stiff since they take load axially and the camber is only resisted by bending in the chords which are much less stiff than the truss configuration.
In a true truss, there are zero shear forces due to PT. This structure is much closer to a true truss than a vierendeel.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The flexural strength and stiffness of members are no way near enough to resist the shrinkage to that degree.
What do you imagine is resisting the shrinkage force in the deck, sufficient to rupture the node?
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The stiffness of the diagonals is not relevant. Take them as being absolutely rigid. No mater how rigid they are, they will only bow the top chord (and truss). It is the flexibility of the chords relative to the truss that maters if differential shortening is going to cause shear stress at the joint.
There are many things that Figg did or didn't do that really surprises everyone. So I can't say that they did look at the long term response. I can say that any competent design team would look at both the short and long term behaviour which would include the creep, shinkage, and temperature changes.
The long term response is particularly important in this structure due to the tube stays. If the long term response wants to cambers up, there is big trouble with additional shear at the joints and compression on the diagonals. That is because unlike the truss chords bending stiffness, the stays are really stiff and even with a little camber, will produce large forces. They would produce enough force to keep the truss flat (or in the initial position). This is when the PT can actually stress the joints.
If I find the time, I can model it to get a more affirmative answer. I may approximate the section shapes just to get a feel for the long term response. Once those stays and back span are on, then the analysis gets to be more complex. Without the stays, it is not so bad to analyze by hand (at least with the simply supported case and only the gravity loads).
RE: Miami Pedestrian Bridge, Part XIV
There's been a bunch of comments and theory about the backspan/tower helping support the 11/12 node. I posted way back that the main span needed to support itself without anything else helping for any chance of the whole structure working long term and I still believe that. From the report and structure build info, it's been made clear errors were made so this wasn't the case, but then that was rather obvious by just looking at the pictures of the cracks.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
From Bridge Factors Attachment 70 FIU Superstructure Longitudinal
FIGG LARSA Calc Pg 5, pdf file page 13
Concrete Truss_diagonal Rectangle 1.7500 2.0000
Concrete Truss_diagonal 2 Rectangle 1.7500 3.5000
End Truss Diag 2 is 3.5X21" - do not know where that is used
RE: Miami Pedestrian Bridge, Part XIV
Yes it will help. Thank you.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
If we consider a rectangular solid beam placed horizontally and simply supported with no end restraints, and loaded with a uniform load , we expect it to deflect downward.
It does so because there is compressive stress in the top and therefore the top shortens, and there is tensile stress in the bottom, and therefore the bottom lengthens. Simultaneously a horizontal shear is induced in the web - Vh=1.5V/A.
Does it not seem logical that anything that would create that same curvature in the beam would cause the same internal stress?
What is less obvious is how a vertical load manages to create a horizontal stress in the rectangular beam. Would not a horizontal load like PT forces seem more direct and more obviously create horizontal stresses?
If we think of a pack of paper for the printer, and we want to prevent the sheets from sticking together we flex the sheets to cause them to slip on each other. That slip would represent the horizontal shear from the curvature. If we prestress the sheets on the tight curve side just enough to shorten them and maintain alignment with the sheets above, that shear is negated. But don't we have to transfer some of that PT force to the sheet just below the top sheet and to all the sheets from there to the PT force?
If the object were a truss and not a beam, if it were 18 feet deep and 174 feet long, and if prestress forces in the deck were sufficient to cause maybe an inch of camber in the truss, would it not have lifted off its interior falsework and be spanning 174 feet, and therefore the axial load in diagonal 11 have been the same as when setting on the pylon? Would the load in member 11 been negated if loads were placed on top of the truss to force it to stay straight? Or would the load in 11 be increased?
This brings to question the issue of concrete strength at the time of tensioning and the E value at that time.
I think the drawings allowed tensioning at 6000 psi.
RE: Miami Pedestrian Bridge, Part XIV
The forces in the diagonals due to the initial PT of the deck are 14Kips and 7Kips respectively for #2 and #11. That will go down with creep and shrinkage. Keep in mind that this is only looking at the initial PT of the bottom deck in isolation. I am getting a DL compression in #2 of 1800Kips and 1280 Kips in #11. IN the north end, I get a vertical shear of 110 Kips in the bottom deck, 58 Kips in the canopy and 12 Kips for the weight of #12. So the net vertical component to the diagonal is (938Kips-100-58-12)=770 Kips
The camber up is 0.92" (this excludes the DL which is obviously in the opposite direction.
The initial dead load deflection is 1.3".
The south end reaction is slightly higher than the north end reaction.
The initial deck PT contributed 0.5% to the interface shear at the north end.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Thanks. Does your model give an estimation of longitudinal shortening due to drying shrinkage and applied PT?
RE: Miami Pedestrian Bridge, Part XIV
That value is for only PT D1L and D1R? So there are five more sets of strands to be tensioned?
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
The upward camber is short term with all the PT in the deck (no other PT applied yet). I am trying to set the initial temperatures for the PT strands. The temperature will be kept the same through out the analysis. Shrinkage is models as a negative temperature on the concrete. How much high strength concrete shrinks in a Florida environment is a good question. I usually use 0.0003 strain but 0.0002 may be more appropriate. 5/8" 100 feet is about 0.0005 which is realistic but maybe on the high side (once you include thermal changes it may be more realistic).
The model is 2D and stick elements for simplicity. Even at that is takes a while to put in all the PT, determine temperatures etc.
Hokie,
Right now, I have only included the initial PT (full bottom deck) and the initial concrete modulus. I will include for shrinkage and creep later. I will rerun the model with a lower E for concrete to account for creep. The temperature on the concrete will be negative to account for shrinkage. I am getting there but it is a lot of work and I still have to my regular work.
The concrete shortens with the application of the PT.
RE: Miami Pedestrian Bridge, Part XIV
I am back on the computer. The total shortening of the bottom deck from the initial bottom deck PT is 0.56" but that is taken up mostly by camber of the truss.
I made a slight error. The DL deflection is closer to 1.5" rather than 1.3".
I work more on this later. I have to go back to work.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
No worries, it is just Canadian money.
I am a Stuct. Eng., so I have to get CPDs hours done anyways.
RE: Miami Pedestrian Bridge, Part XIV
Hi Earth314159. I am not sure what you are suggesting here and am curious to understand the function. Are you suggesting that in a true truss there are no shear forces to be found if post tensioning (PT) is provided? I'm not sure if PT will remove shear forces from a truss.
Thanks for your thoughts on this.
RE: Miami Pedestrian Bridge, Part XIV
No, that is not what I am suggesting. There is still shear in the structure due to gravity loads. The PT in a "true" determinant truss does not add to any of the member forces (including shear). It only adds minimally to the horizontal shear at #11 and #2 in this truss which is not determinant.
The compression in the concrete created by the tension in the PT is equal and opposite with a net zero member force.
PT in a true truss can camber or otherwise deflect the truss but the net members forces will be zero if you look at that PT case in isolation. You use the laws of superposition to add back in the other cases.
RE: Miami Pedestrian Bridge, Part XIV
FIGG Bridge Engineers, Inc Party Submission Findings Conclusions Recommendations, and Attachments 628567
and I noted some differences between the way FIGG presents the WJE analysis and the WJE report itself.
I have two questions that are bothering me.
One: If the truss was not supposed to crack when the shoring was removed, why didn't this raise questions about how it was constructed?
Two: Pate headed down to FIU to calm people down. Would it have turned out different if he had made an effort to understand what they were upset about?
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
One - Some concrete cracking is normal and not of structural significance. I do not have the dimensions of "acceptable cracking" at my fingertips - I recall FDOT (I think - from NTSB meeting) sets 1/2" deep and either 0.002 or 0.006 inch width. That is for normal structures and there was nothing special about this one, right? (Hint - it was a truss).
I also recall an NTSB comment that on the morning of March 15 the cracking was 40 times an acceptable limit.
Two - I don't think the EOR made an engineering call on March 15.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
https://www.miamiherald.com/opinion/op-ed/article2...
RE: Miami Pedestrian Bridge, Part XIV
https://www.enr.com/articles/48016-what-florida-br...-
P.S. What is going on with the widespread misuse of the word 'sheer'?
https://www.eng-tips.com/search.cfm?pid=0&page...
RE: Miami Pedestrian Bridge, Part XIV
https://www.enr.com/articles/48016-what-florida-br...
Unfortunately, the ENR article ends seemingly incomplete and it incorrectly states the bridge design would use cables attached to the pylon instead of faux stay pipes.
https://www.miamiherald.com/opinion/op-ed/article2...
This opinion from a member of the NTSB is pretty straight-forward in stating the design error was clear yet the group think behavior overrode any dissenting response/concern.
What I still have not seen addressed officially is the issue that has been broached by many posts in this forum, regardless of all the talk/calculations on the applicability of shear capacity at the critical nodes - based on joint preparation and such, shouldn't the main span have been designed to be a fully safe and functional self-supportinhg span, not reliant on the future addition of the small back span to 'capture the 11/12 node'? Is this a common design/construction scheme - build one section of a multi-span structure with knowledge that it is reliant on another yet to be constructed section? Shouldn't individual sections stand alone unless they share beams? My naivete shows . . .
RE: Miami Pedestrian Bridge, Part XIV
Or maybe " the sheer magnitude of the consequences of the shear failure before your eyes"?
That sheer looks like a problem to me. :)
RE: Miami Pedestrian Bridge, Part XIV
It certainly should have had the capacity to support itself and any construction loads, as well as withstood the rigors of transport, without failure and with some room to spare. And I believe this was the intent.
The concept of every piece having its final capacity at time of erection is not efficient and not required in many stages. An example is a precast girder which can support formwork for a yet to be placed concrete slab. The slab can be considered to be composite when completed and provide far more support in the final structure but the girder acting alone only needs to have the capacity to support (safely) the construction activities and the wet concrete and forming. Once cured, the intended strength is developed. If the designer does not screw up.
Not at all. You are right on point. There are calculations by the design firm that address shear in node 1/2. but I have found no calcs for node 11/12. It appears node 11/12 was not properly addressed in the design.
But I have to wonder about the long term service of the improperly treated joints. If FDOT wants them chipped and cleaned for good sealing and to prevent deterioration, these joints would not be protected as intended by FDOT. They will be wet when it rains - they are effectively in the gutter. And deterioration of reinforcing will not be visible. Perhaps this is what Berger saw when they requested guidance for treatment of the joints.
RE: Miami Pedestrian Bridge, Part XIV
Source: Comment to this article> https://www.enr.com/articles/48005-ntsbs-fiu-bridg...
Can someone please elaborate on this comment? I suspect point of comment is diminished if the bar tension changes were staggered at 50 kips. Are two balanced bars outside kern area effectively inside area? Was 50 kips small enough a limit for concentric loading? What complication is caused by positioning of dead end anchors? Did the bars in fact cause excessive tension in 11 cross-section?
RE: Miami Pedestrian Bridge, Part XIV
I understand that Figg had multiple models and that some predicted greater shear forces across the 11-12 joint, but they only used the "simple-span" model and the "fixed-pylon" model which predicted lower forces. It is unexplained why they did this, but I could see them thinking that these 'should' be the worst case and thus not really checking/looking into it (or just missed it). Either way the model at the time of the collapse would have been the simple span model. I also understand that they had a solids model (Lusus) and a beam element model (Larsa). They said that these correlated fairly well. My question is - why was shear demand in these models so different (lower) than the FHWA's check and even the Figg 'hand-checks' that were part of the 3/15/18 slide presentation.
Regarding the 3/15/18 presentation. It appears that Figg checks the shear strength at this node and finds that it has adequate strength. What was wrong with this hand check?
Also I didn't realize that two of the designers were on vacation immediately following the bridge move. Including the lead project engineer. Not sure that things would have been different, but interesting to note.
EIT
www.HowToEngineer.com
RE: Miami Pedestrian Bridge, Part XIV
There we learn that about 11% of the deck PT was first applied ( D1) and about 24% of the canopy PT was stressed ( C2) when the PT rods in member 2 and member 11 were to be stressed. There is no specification as to sequencing the tensioning between the rods.
From calcs now underway by Earth 314159 we find that full PT in the deck will cause about 1 inch camber and dead load about 1.5 inches deflection so member 11 may have been under some load but likely much less than when spanning 174 feet or when on the falsework with full PT in the deck. Stressing one rod to max before stressing the other will induce a moment but whether that causes tension depends on the total load in the member at the time. PT acting at the kern could cause sero tension in an otherwise unstressed column, and PT outside the kern can cause tension. Axial loads at that time could overcome the tension stress and the section remain in compression across its full area. Only the numbers know.
Perhaps the analysis by Earth314159 can provide some numbers to work with here. We need the compressive load in member 11 while on its falsework and with PT tendons D1 and C2 only stressed to answer this question.
Without a computer analysis I would consider that the PT force in the deck was about 960 kips and in the canopy was about 880 kips. While those forces are somewhat close to the same value the compressive
forceSTRESS in the canopy is much greater because of its relative size being much smaller. So the effect of the early PT would be a downward camber or a lifting of the ends. That could induce tension in members 2 and 11, making it more likely that cracking did occur from stressing one PT rod located outside the kern.Or that PT sequence may have caused some initial cracking at nodes 1/2 and 11/12.
RE: Miami Pedestrian Bridge, Part XIV
When I was going through MCM's Contracts & Purchase Orders it became obvious that MCM was really only performing as the Construction Project Management firm and the actual Contractors, were all Subs. MCM was ranked 276, down from 245 in the 2015 ENR 400. So they were a big dog in construction but I was starting to get the feeling they didn't really have the chops to be doing this level of Heavy Civil Construction. It was one of the first things I looked at, when FIU made the Bid/Submittal packages available for public viewing. Link I knew MCM had people on staff that were Florida Licensed Professional Engineers, but where were they on this project? Was MCM a "General Engineering Contractor" on paper only? FDOT also doesn't give the CEI firm any engineering authority over design.
The FIU Request for Qualifications - Request for Proposals, pg 51 lists the requirements for the Design-Build Firm’s Project Manager. Link. Specifically, The Project Manager assigned by the Design-Build Firm must be proficient with the English language, and shall possess a Registered Professional Engineer License in the State of Florida and three (3) years of specific experience in construction management on limited access facilities or have a minimum of five (5) years of specific work experience providing construction management in limited access highway facilities.
Here is the organizational chart MCM submitted with the proposal on September 30, 2015.
The Design-Build Manager for MCM was one, Joe Martin, P.E. (LinkedIn: Link) The chart wasn't worth the paper it was printed on. Joe Martin, P.E. left MCM in October 2015 for Odebrecht. His role seems to have remained unfilled and the FIU Bridge Project put under the management of Rodrigo Isaza (LinkedIn: Link). You can see MCM's descriptions of Mr. Martin & Mr. Isaza starting on pg. 25, of their submittal. Link
It is entirely possible that Rodrigo Isaza met the minimum of five 5)years of specific work experience providing construction management in limited access highway facilities but there was a clear lack of critical understanding & thinking related to the execution of the work.
Using a 19th century nautical comparison. MCM was a big dog and as such, when they sailed into port, they anchored and waited their turn, to unload and load but when they weighed anchor and headed out to sea; they were just dog legging, direct reckoning sailors, who made the error of thinking they could blue water sail without a Celestial Navigator.
RE: Miami Pedestrian Bridge, Part XIV
This project was a reality check for all.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
https://jalopnik.com/florida-pedestrian-bridge-col...
old field guy
RE: Miami Pedestrian Bridge, Part XIV
Unfortunately, this article is poorly written. For just two examples (there are others):
-- "The report went on to say that Berger knew he should have checked the math...." Louis Berger, in this case, is a company, not an individual.
-- "In other words, the contractors did crappy math." The article hits this theme quite a few times. But, it was the engineer working for the contractor who did crappy math, not the contractor.
Fred
==========
"Is it the only lesson of history that mankind is unteachable?"
--Winston S. Churchill
RE: Miami Pedestrian Bridge, Part XIV
The comments by the 'public' if you will provide an insight to what a jury might think/say/decide.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
https://miami.cbslocal.com/wp-content/uploads/site...
RE: Miami Pedestrian Bridge, Part XIV
As an aside, who ultimately determines if the EOR loses their PE due to the miscalculations and apparent disregard for public safety? I assume it'd fall to the professional departments of the various states he's licensed in?
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
There is a hand calculation in the FIGG design calcs that addresses node 1/2 using a "punch thru" set of shear planes thru the deck and out the end. I do not see a similar calc for node 11/12.
The slide presentation calc of the shear in node 11/12 was a similar calculation to that at node 1/2 in the design calc. That calc and a subsequent calc presented to NTSB included contributions from any reinforcing which could be identified in the region, not being limited to reinforcing intended to resist shear friction.
The FIGG calcs were made using a coeff of friction of 1.0, while the actual joints had received no roughening and a correct coeff of friction would be 0.6, reducing the contribution of all components by 40%. The NTSB concluded the joint prep was not a factor - it would have failed anyway.
As I recall now, that slide presentation did not address the presence of two 4" dia pvc sleeves vertical thru the deck and together at both sides of member 12. Nor did it consider the extensive cracking of diaphragm 2, which it assessed as having cracked from the vertical component of members 11 and 12. The horizontal thrust was greater than the vertical component and the joint had slipped maybe 1/2 inch when the slide presentation was made. Tests from WJE show that maximum resistance of a shear friction joint is developed at a slip of 0.020 to 0.025 inches - long before the EOR saw the actual conditions on the morning of March 15. It was downhill from there.
You may have answered your own question. It appears that almost no attention was given to tne need for node 11/12 and member 11 to "stand alone" during Stage 2 erection and until the entire double span structure was completed.
When complete, member 12 was to be "wrapped" and integrated into a concrete pylon 5 feet by 6 feet in dimension cast with the north span. And the north span was a shortened mirror image of the main span, so member 14 of the north span counters part of the horizontal force in member 11 in the final structure. The mental image of the huge pylon seems to have created a confidence in this area that overshadowed the importance of capacity at Stage 2.
And - can anyone confirm the actual reinforcing in member 11? The drawings leave some question of whether member 11 should have been considered a member "without PT rods" and therefore should have had 10 - #7 bars, or whether member 11 was a member with "with PT rods" and therefore was to have only 8 - #7 bars - in which case the amount of reinforcing does not meet the minimum requirement for a structural member. In either case, I see a visibly evident lack of appropriate reinforcing in the web members.
Thank you.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
That's what makes this more a failure of imagination than of calculation.
I agree that Figg seems to have concentrated too much on the final structural configuration, but I'm still on the fence about how much it mattered. There is no evidence that there was to be any substantial connection between the decks of the main span and back span of the finished bridge. So I think that while the completed span could not have failed in the same way as the Stage 2 span, there would still have been plenty of room for failure. Given time, the horizontal component of the force in 11 could still have separated the 11/12 node from the main span deck. But instead of kicking that node off the deck to the north, it would have shoved the entire main span to the south until it used up all the available travel in the expansion joints. Depending on the detail design of how the main span was to be anchored to the pier and at the southern abutment, it might or might not have collapsed fully, but it certainly would have made a scary mess.
RE: Miami Pedestrian Bridge, Part XIV
The south expansion joint is 1-1/2 inch wide so that is the point where the south stairs would begin resisting forces. Whether that would have kept it on its supports is a guess at this time. NTSB Member Homedy discussed the stairs as providing forces to keep it on its supports. The staff responded that there was an abutment at the south end. Hmmmm....
Member 11 was so badly damaged and under reinforced it could then have been the weak link.
Imagine this - the force in member 11 is 1.61 times the truss reaction at the pylon. For the reaction to equal the force value in member 11 would require a span length of about 240 feet (deducting any increase in the end span reactions of the canopy and deck ). This is where the imagination comes in -
Can you imagine an engineer supporting one end of a 240 foot long structure just like this on a 24 foot long column of the dimensions 21" X 24" and reinforced with 8 - #7 bars?
Can anyone?
Would cracking and splitting in that column like that seen in member 11 have caused any concern among the people at the meeting of March 15?
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
Just as an example, when during the meeting on March 10, 2018, the day of the collapse, FIU ask BPAs opinion of FIGG's analysis, they deferred to their in-house superiors (Jake Perez and Luis M. Vargas) and requested time to give a response. One wonders why Jake Perez and Luis M. Vargas, were not, already involved and at the meeting. Luis M. Vargas' CV on his BPA Profile certainly establishes him as an engineer familiar in dealing with concrete failure. If BPA had brought the full measure of talent that they had claimed would be supplied to the project, when conditions in the field degraded, perhaps tragedy could have been averted.
I also think the NTSB spared FIGG the coup de grâce. The NTSB puts little emphasis on the cracking that was photographed between 3:16pm & 3:18pm on March 10, 2018, 2-1/2 hrs after the transports were removed and 1 hour before the PT rods were detensioned. There was already a visible crack in member 12, longitudinal cracking in #11 and the spalling on the deck at the edge of the diaphragm was great enough to have been accompanied by cracking on the north face of the diaphragm. The bridge was most likely already damaged beyond repair. There was only one opportunity, to attempt to repair the concrete and that was while it was still on the SuperShores in the casting yard.
Emails between Figg & MCM regarding when the detensioning took place and if the photos taken between 3:16pm & 3:18pm, were before detensioning, establish that FIGG knew the new cracking had begun before detensioning.
When Louis Berger's, Dr. Shama, first modeled the complete bridge, he did so with the PT bars in #2 & #11 fully tensioned. He found the compressive forces in #2 & #11 far too high. FIGG assured Dr. Shama that #2 & #11 would be detensioned immediately after the bridge was set. It may be that the FIGG employee that Dr. Shama worked with, was one of the FIGG staff on vacation at the time of the collapse and Dr. Shama's concerns not known to others at FIGG. It seems, detensioning possibly slowed the the failure of #11 by reducing the compressive force in #11 and the decision to retension precipitated the collapse.
RE: Miami Pedestrian Bridge, Part XIV
I would disagree that there was ever any opportunity at all to "repair" the concrete. The design itself lacked any shear steel within the concrete for connecting strut #11 to the deck. The only "repair" that could have been done would have been to introduce a massive steel tie sufficient to "capture the node" at #11/#12 and tie it back to the previous node on the deck. There was not one possible modification to the concrete that could have had any preventive effect capable of avoiding collapse.
RE: Miami Pedestrian Bridge, Part XIV
https://www.ccbiznews.com/news/corpus-christi-harb...
What I find is rather confusing. The "design" has been suspended but I found other links that seem to indicate the bridge is half-built. One article mentioned the contractor was the same one as the FSU bridge, but it's not. This article indicates Figg is designer of the new Harbor Bridge, but that's not mentioned anywhere else that I find.
RE: Miami Pedestrian Bridge, Part XIV
https://www.caller.com/story/news/2018/03/19/engin...
https://ftp.dot.state.tx.us/pub/txdot-info/spd/cda...
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Please check post for typo. Third paragraph, should be March 10, not 15.
RE: Miami Pedestrian Bridge, Part XIV
When a girder fails, usually the entire girder is replaced as a repair. Since this bridge was designed as a single girder, the only practical form of repair is total replacement. Since the whole idea of the single girder was to lower cost, it should therefore not have been a huge burden to scrap it in the casting yard. This bridge was treated like a red-headed stepchild.
RE: Miami Pedestrian Bridge, Part XIV
That brings us back to the beginning - and the question of "Who decided to abandon the whole project?"
The collapse would have at least aroused the attention of the design team. With 30 days of study, the problems could have been identified and corrections made in the detailing while 90% of the forming would have been reused or at least reconstructed to known dimensions. Start building the back span immediately and concurrently with the casting of the replacement to the main span. Add 6 months to finish date - that would seem better than what we have now - nothing.
Or better yet design it using steel - much lighter so foundations are adequate - the size has already been approved, the location determined - just need a concentrated effort to redesign and save a project.
Had there not been loss of life this project might have been resurrected. Those taking action and closing the street would have been heroes.
If only the street had been closed immediately at the end of the March 15 meeting.
As we know now, there would not have been time to shore it and save it, and that fact would have pointed out the wisdom of closing the streets, thereby certifying the heroes.
Was there a knee jerk reaction that led to the decision to abandon this 'red headed step child'?
Professional reputations would have been stained, and the costs would have been significant, but there would have been a completed project.
I have always wondered why the back span was not constructed concurrently with the casting of the main span. I do not see anything significant that would have prohibited that.
RE: Miami Pedestrian Bridge, Part XIV
They would also have suspended the retensioning of the PT bars in 11, since putting up a crew would have been unsafe. If the PT bars had NOT been retensioned it is possible that the bridge could have held until the shoring was in place. It really depends on how quickly they could support the node in question.
What I’ve long found ironic is exactly what jrs_87 said: this was the red headed stepchild project! That exact phrase has been running through my head since the week after the collapse.
After going through everything in the docket, watching the October 22nd meeting twice and reading the final report, I can only conclude that for all that this was a special, novel project for FIU, to FIGG and MCM it was just a little pedestrian bridge. It did not get the attention it needed from the design or construction firms.
While MCM was ultimately in charge of the build site, they abdicated their oversight to the mighty FIGG EOR rather than listening to what the bridge itself was saying. Frankly, with the rush to retension the PT rods they proceeded even though the Coranado group PT inspector was not present- which should never have been allowed to happen. There was no one in the March 15th meeting who had the courage to stand up to the FIGG EOR and call BS on the plan.
This project was too small to garner FIGGs real attention. Clearly the EOR was very busy with more important projects. I am still rather stunned that the reason the peer review was abbreviated was because FIGG dropped the ball by planning to use their internal offices for the review rather than a seperate firm. Then they had to rush to get the design rubber stamped in time. I find it telling that even FIGG can not explain how they used their models to extract the original calculations for capacity and demand on the nodes. That’s how little this project meant to them, until it blew up in their faces.
RE: Miami Pedestrian Bridge, Part XIV
FortyYearsExperience (Structural) While I agree that there was never a point at which a repair could be 'effective', I can't help but mark the point in time, when an examination of the cracking should have taken place and was summarily dismissed by FIGG. I did contemplate the futility of the suggestion of a repair. Figg was given opinions/concerns regarding the node/s by FDOT-Tom Andres, BPA-(Cold Joint) & Louis Berger (Compressive Forces in PT tensioned #11), so when a problem developed in the casting yard, it should have been the wake up call.
Kestrel42 (Bioengineer) How does one shore the bridge? You cannot send workers under the bridge. Do you bring the transporters back? There were cracks in the #1/#2 node as well. The cantilever resisting PT action cannot be restored.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Impact-echo, ultrasonic impulse-echo.
Impact-Echo is a nondestructive test method for evaluating concrete and masonry structures. The test utilizes stress waves (sound) that is normally generated through striking concrete by an impactor (Impact), and recording the reflections and refraction from internal flaws and other boundaries (Echo).
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
I'm speaking out of ignorance, as I'm not familiar with the process for concrete. But it's hard to imagine the procedure being that much more unwieldy than ultrasonic weld testing, which is completed regularly for major bridge structures under construction.
----
just call me Lo.
RE: Miami Pedestrian Bridge, Part XIV
IC
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Sometimes it takes a moment to consider this from a higher level and in two sentences I think you've captured the essence here about what went wrong.
The cult of the FIGG EOR also looms large in this disaster and hopefully in the future it will embolden some of the others in the next meeting to step up to the plate and demand action (or inaction) despite what "the mighty EOR" says.
I think (hope) state highways departments will already be preaching the safety first philosophy more than they already did.
To go through that amount of data must have taken you days so congratulations for that assessment.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Perhaps a link to where we should go? Then maybe a return link?
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
(...just the facts mam)
RE: Miami Pedestrian Bridge, Part XIV
All that has happened is that someone posted in Part XIII (or 13 in most peoples language) and shouldn't have been. Hence the post above by Denial just put part XIV back as the top listing.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
I haven't checked in a long time but I read a few of the latest posts.
Cracks usually go straight through a member. In the NTSB board meeting, they mentioned a standard that considers cracks to be an issue if they are more than 0.5" deep. 99.9% of cracks are more than 0.5" deep. So I don't know where that standard originated from but it makes no sense. The width of the crack is more critical. Also the consistency (does the width vary and how), shape, location of the crack are all more important than the depth. You can usually determine what is happening by an external review of the crack. Even in research, you usually don't look at the internal shape (probably too difficult). You can in theory use ground penetrating radar (GPR) to determine the internal shape. We used to use x-rays for locating rebar and PT (We use GPR now) but I don't ever recall seeing an x-ray and being able to identify the shape of a crack (I am not saying it can't be done) but likely at least as difficult to identifying bone fracture shapes on x-ray (not that easy).
RE: Miami Pedestrian Bridge, Part XIV
When we see full-section cracking, with crack width such that you can insert your fingers, then we are looking at a whole different situation.
http://julianh72.blogspot.com
RE: Miami Pedestrian Bridge, Part XIV
And to comment on your last sentence, particularly cracking of that magnitude in an area having designed (??) and purposeful reinforcing. Put simply, if the designer put reinforcing there for a purpose and it cracks that badly, it is time to consider the total consequences of a failure.
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
Seems that Figg now brings with them a skeptical reputation.
FIU Collapse Report Spurs Texas Bridge Design Review
The Texas Dept. of Transportation has suspended design work on Corpus Christi’s Harbor Bridge pending a safety review of plans prepared by FIGG Bridge Group, one of the firms faulted by the National Transportation Safety Board for last year’s deadly pedestrian bridge collapse at Florida International University. Although construction of the $803-million cable-stayed structure’s initial phase remains unaffected, the review, expected to take at least 30 days, could further delay a project already behind on its original 2021 completion schedule. Tests of elements already in place have revealed no issues.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
http://panthernow.com/2019/10/31/decisions-to-proc...
RE: Miami Pedestrian Bridge, Part XIV
FIU Hosts 2019 International Accelerated Bridge Construction Conference
They will not be discussing last year's deadly bridge collapse the NTSB ...
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Plus also I suspect that the student accommodation that was going in on the other side of the road in anticipation of the bridge is now all complete and full.
So they have a huge issue with them crossing the road anyway possibly killing more kids than the bridge collapse did inside 5 years if there isn't a bridge.
RE: Miami Pedestrian Bridge, Part XIV
The use of the back span to "capture the node".
I think that this was just some after the fact bafflegab to cover their assets.
If it had been a design intent that the back span would provide needed support to the main span, then why was the back span not completed and in place before the main span was placed.
If the back span was seriously intended to provide needed support to the main span, then in addition to the other shortcomings we can add an inappropriate construction schedule and another failure of oversight.
The point is probably moot as the span was badly damaged even before it was placed.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
The pylon was going to use the two spans as part of its formwork so it could not be in place until the two spans were in place. Perhaps the audience for that comment was meant not to notice.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
This is close to an admission of liability for the failure. They provided multiple longitudinal post-tension cables, but they did not connect those cables to the 1.5 million pound load heading north in diagonal strut #11. The 1.5 million pound load moved northward because it was not restrained by any other force. (Newton, First Law of Motion, discovered 332 years ago; see, "Principia Mathematica Philosophiae Naturalis" pub. Cambridge University, 1686)
RE: Miami Pedestrian Bridge, Part XIV
Heck, it probably doesn't even work anymore, it has been so long. We have computers today and they take care of all that stuff so we don't have to worry about it.
Wiley's First Law of Computers: Garbage Out is directly proportional to Garbage In.
RE: Miami Pedestrian Bridge, Part XIV
"because it was not restrained by any other force"
It was restrained, but just not enough.
I do agree though with sentiment - all they really needed to do was connect those cables via strong enough end beam to resist the end force.
I just hope that the results of this investigation prove to be a key learning point in bridge / concrete truss design for decades to come.
However I don't think there will be too many designs similar for a long time due to this collapse. There was no redundancy and the design and execution was flawed.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I would respectfully submit that the oft repeated assertion of "no redundancy" misses the mark.
The subject bridge lacked any functional connection between strut #11 and the multiple longitudinal post-tension cables in the deck. If the absence of such connection were to be repeated in two trusses running parallel to each other, such a bridge would have "redundancy" but would certainly also collapse. The problem was not a lack of redundancy. It was a lack of a critical connecting element. No matter how many times you repeat that error, you are not going to fix the bridge. And yet, if that connection had been provided only once, the bridge would have stood for 100 years without possessing any "redundancy".
If the term "no redundancy" is defined to mean "lacks a critical element" -- well then we have an argument about the meaning of language, and not about civil engineering.
RE: Miami Pedestrian Bridge, Part XIV
Newton's Laws of Motion were actually replaced in 1915 by Einstein's relativity theories (1905 & 1915) but they're still "good enough" for everyday engineering.
Was doing some reading about Scientic Laws and came across these nuggets:
So the definition of a scientific law kinda sounds a lot like a traffic law: just because a 35MPH speed limit means "up to 40MPH is OK" in your city doesn't mean it will be the same in all cities.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
You'd pretty much have to wouldn't you?
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
That is such completely unmitigated horseshit, one wonders whether anybody would trust WJE if they said the sky was blue.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
I recall the Sunday show that exposed all the bad things - and a lot of them really got me steamed up.
When they got to the point of criticizing JEEP because they could be turned over by an idiot driver I quit watching. They lost all credibility with me. Then I learned they rigged the Chevy PU gas tank explosion.
In court they say "one lie, all lies" or something to that effect.
Thanks, and Happy New Year to all.
What do we hear from the EOR these days? Looking for a job or hiring an agent to sell his book?
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
NTSB report was pretty damming of FIGG amongst others, but they hide behind their defence of "if the joint was made properly" which seems not able to stand p to serous scrutiny.
So any more hearings?
Court cases?
Anything new?
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
Note: Original headline reads "
Developers remove engineer from main span of New Harbor Bridge Project, firm will continue work ..."
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
I hope this project isn't almost a trillion dollars...
RE: Miami Pedestrian Bridge, Part XIV
Dik
RE: Miami Pedestrian Bridge, Part XIV
Dik
RE: Miami Pedestrian Bridge, Part XIV
Link
RE: Miami Pedestrian Bridge, Part XIV
https://event.on24.com/eventRegistration/EventLobb...
If my bridge relied on an apprentice mason scouring a few square feet of concrete in an extremely tight area to remain aloft, I think I would be standing over his shoulder with a trowel in hand whilst doing so..........
IC
RE: Miami Pedestrian Bridge, Part XIV
Why yes, they are:
"FIGG also detailed that it had hired forensic structural engineering experts Wiss, Janney, Elstner Associates to conduct an investigation, which revealed that the construction joints at the failure point were not roughened in alignment with Florida standards. (Roughening would have also contributed to the strength of the connection.)"
https://www.paintsquare.com/news/?fuseaction=view&...
RE: Miami Pedestrian Bridge, Part XIV
This bridge was fatally flawed in design and construction.
To try and blame a non roughened joint doesn't work for me. I haven't read all the back words here but I'm pretty sure the NTSB refuted that suggestion. Sure it didn't help, but this bridge would have fallen down even with a roughened construction joint.
I also can't see how anyone can say something like this "would not have occurred" when there were a number of failure modes, lack of strength and re-inforcement and probable damage whilst it was moved and placed on its supports
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Wasn't there significant design errors made by FIGG? Where did admitting your wrong and accepting at least partial responsibility go?
RE: Miami Pedestrian Bridge, Part XIV
Notice how the event summary says "had the construction joint been roughened as required" and does not say the specifications or drawings required roughening. Codes require it to be roughened and the engineer is suppose to communicate those requirements in the specifications and drawings. Someone was suppose to tell the contractor that the joint had to be roughened and even in that case, it was still under designed. Regardless, it did not meet the minimum level of strength to protect the life and safety of the public. The response to the cracks was unacceptable and for any competent experienced structural engineer that works with concrete, it boarders on criminal negligence.
The roughening issue is a moot point and is irrelevant to the question of responsibility.
RE: Miami Pedestrian Bridge, Part XIV
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
The bridge is not pinin'! It's passed on! This bridge is no more! It has ceased to be! It's expired and gone to meet it's maker! It's a stiff! Bereft of life, It rests in peace! If you hadn't set it on the pier It'd be pushing up the daisies! It's metabolic processes are now 'istory! It's off the twig! It's kicked the bucket, It's shuffled off it's mortal coil, run down the curtain and joined the bleedin' choir invisible!! THIS IS AN EX-bridge!!
Note: FDOT is going to build a pedestrian bridge in it's place, hopefully made of steel, with no faux supports...
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
However I agree the above that that statement is a bit rich. That is like saying had we not placed that last piece of straw on the camel then its back would not have broken.
RE: Miami Pedestrian Bridge, Part XIV
"hey, that last piece of straw must have weighed so much more than the previous pieces of straw..."
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
May 12 - U.S. Department of Transportation, Office of Inspector General - FHWA Report No. ST2020035
RE: Miami Pedestrian Bridge, Part XIV
Florida Department of Transportation to build replacement for collapsed university bridge
Feds Uncover Missed Opportunity to Catch Fiu Bridge Design Errors
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I pity the designer and contractor on the next bridge. There will be more inspectors than workers, with inspectors inspecting the other inspectors.
RE: Miami Pedestrian Bridge, Part XIV
What I don't understand is how FIGG ignored that the bridge was telling everyone there was major problems. How did FIGG come to the conclusion that adding more compression to the joint was going to help matters?
I can't come to the conclusion that FIGG is not at least partially liable here.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Finding no specific requirements for the truss joints, the engineering firm overseeing construction requested specific direction in this matter.
FIGG responded by instructing the joint to be prepared to meet FDOT requirements. But FDOT as I read it a year ago gives NO specific direction beyond removal of loose materials and cleaning the joint and FDOT does not specify an amplitude of roughness, normally specified at ¼ inch.
Then, after failure, WJE prepared and tested joints which were prepared to intentional roughness of ¼ inch amplitude and used that as a “woulda – shoulda” joint, implying that their preparations and testing proved the likely results had the FIGG requirement been followed.
But there is a large gap in this logic – somehow they made the jump from FDOT requirements of "clean" to an intentionally roughened amplitude of ¼ inch.
A bit of a “bait and switch” maneuver, it would seem.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
His lips were moving.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
So I am in agreement with you - this joint preparation could not have saved it. The handling of the joint preparation and the double talk attempting to obscure a lack of specificity in the instructions to the job and the subsequent laboratory testing show an attempt to deflect the focus.
Sadly, the EOR did not make an engineering call on March 15.
That would be most prudent at that jucture.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
I think the usefullness of this forum is there are other experienced professionals who can voice our opinions.
Like Vance Wiley (Structural) pointed out the Member 11/12 has already been separated from the deck so the adhesion at the construction joint is minor if not trivial comparing with the loss of effective concrete at the critical section displaced by the 4 No. of vertical 4" I.D. pipe sleeves, various cable ducts and one large horizontal 8" I.D. embedded drain pipe. These embedded items are the real killer because not only they (1) robbed the section of precious bonding concrete they also (2) obstructed placement of reinforcing bars so desparately needed, (3) created weakness points and paths (stress concentrations) due to their presence and (4) provided sources of defective construction due to the difficulties of compacting concrete in small, tight and confined spaces.
In the update to the preliminary BTSB report on May 23, 2018 NTSB's Fig 1 and 2 show, below the the construction joint, the deck had already developed diagonal shear cracks, typically about 45 degree, in a pattern exactly predicted by FDOT Engineer Tom Andres on Mar 2016 when he first review the preliminary design. The crack on one side was 4" deep shown from the insertion of a tape and appeaed at least 20mm wide. Above the construction joint NTSB showed by Fig 3 Member 11 had a crack 7" deep against by the insertion of a tape. The extensive cracking of Fig 1, 2 and 3 were taken prior to the collapse and also based on them Figg declared the FIU bridge safe! NTSB and most of us were critical of such claim as it shows Figg did not even know the bridge had gone and continued to fiddle with the postensioning rod until the bridge broke up.
The key evidence prior to the collpase shows bridge had suffered fatal and structural damage below and above the construction joint and any suggestion that the adhesion of old deck concret could have hold the bottom of Member 11/12 without separation/failure cannot come from an experienced or qualified reinforced concrete designer. Any engineer experienced in reinforced concrete can confirm it is normal for such a constrcution joint to have minor cracks just by shrinkage in many existing serviceable structures.
RE: Miami Pedestrian Bridge, Part XIV
I would also note that the WJE modeling did not include the conduits for the post tensioning rods, etc. It also modeled the deck as effectively infinite depth, when in fact the deck failed. They seem to have set out to prove that the un-roughened cold joint was to blame, and saw what they were looking for.
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I haven't followed WJE modelling recently but I know the accuracy of every mathematical model depends on the assumptions used. Rubbish in rubbish out.
I post the follow sketch to higlight some of the important considerations
I have shown three section of the deck in A, B and C. C and A were highly stressed laterally by the transverse tendons whereas Member 11/12 was unstressed in the same direction. Thus the interface is prone to crack when there is a major change in stresses in the components. These members were initially held tight together by the PT rods in 11. According to OSHA report 11 has no structural crack at the CJ prior to the bridge removal from the casting yard.
The CJ was seen open up (or cracked) after the bridge had been installed at its final position and the PT rod stress was removed. At this point 11 would have its highest compression load (less only the live load) and it could only hold its position if its joint with the deck did not break.
It can be said with certainty in any court of law that the joint in question had already failed structurally prior to the collpase and re-tightening of the PT rods. The following sketch shows the effects from the embedded items.
Prior to the collapse we know the CJ had cracked or the interface shifted horizontally. The failed components show the failure plane could include the horizontal CJ indicated by the orange dotted line, a vertical plane between the deck and the bottom of Member 12 (show in red dotted line) and two horizontal plane , in green dotted line on either face of 12) along the embedded 8" drain pipe's centreline. In transverse direction possibly two more vertical planes, on either face of 12, shown as B1 were contributing shear resistance against failure.
OSHA has called it a blow-out failure when the bridge collpased.
The shear resistance of concrete and the shear resistance of rebar across the above dotted line interfaces or plane are the main forces to hold the bridge together. Some enhanced shear resistance from the clamping action may be at play but not much in this failing mode.
The design has a modest but not generous amount of shear steel across the CJ interface. At the deck interface with the front of 12 reinforcement is lacking because of the two PT rod anchors there plus the semi-circular cutout for the drainage pipe had left little room for passing the reinforcement through. The two sides bonding of 12 with the deck, Area maked B1, have been curtailed severely vertically by the 4x4" vertical sleeves and horizontally cut off by the presence of 8" drian pipe.
I have not gone through every steel bar to compute the capacity of this joint but it is a lot weaker than any drawing could reveal if the full set of embedded itmes were not included in the examonation.
Only looking at how little room availabe for inserting rebar so that it can have adequate development lengths, on both sides, then one realises how hopeless is the situation. If WJR could not find how this joint fails then its modeller has not enough practical knowledge of reinforced concrete in the field. If any rebar cannot be anchored adequately in both directions across an interface then that rebar should be written off structurally (for not able to realise its full material stress). In the OSHA report one can find a rich set of examples showing exposed bars with intact hooks and clean lengths which indicate the failures were by bonding and not shear.
RE: Miami Pedestrian Bridge, Part XIV
Back of envelope, to hold 1.5 million pounds in place requires 25 square inches of steel. (before we get onto factors of safety etc.)
NOWHERE in these drawings can we find 25 square inches of steel, let alone that amount being configured to restrain the horizontal force in strut # 11.
And, as saikee119 points out, the small amounts of steel which are visible are too short to provide any development of tension force. Effectively, there is ZERO square inches for meeting the requirement of 25 square inches of tension steel.
So, the FIGG argument is that 1.5 million pounds could have been held in place by cleaning the cold joint better.
HAHAHAHAHAH
RE: Miami Pedestrian Bridge, Part XIV
For Member 11/12 To initiate a failure by pushing out from the deck the concrete has to break along the line of least resistance. Most of the resistance is the shear capacity of the concrete and the rebar from shearing and tensile strengths. Tension is concrete is normally a write-off in RC design unless postensioning is involved.
There are many combinations but the failed bridge has helped us to establish the mode of the blow-out. I have stopped to count the steel bars as the drawings are quite poor in revealing the information. May be the latest drawings with a complete set of bar bending schedule would help.
What is certain many bars if adequately anchored would have to fail by shearing off the circular section or snapped off by tension but not many of those are visible. If the rebar could not hold the node together as a rigid joint then the theoretical models would have little value. The primary failure wasn't in the structural calculations but in the detailing of the rebar because the node was not made rigid enough to perform its structural duty.
NTSB criticised the design for the load and capacity calculation errors. This is equivalent to say the capacity of the node should have been downgraded due to the imperfection of rebar installation (caused by PT rod anchorages, limited concrete dimensions, large amount of embedded pipe sleeves and drain pipe at critical locations creating stress concentrations and load path interruptions).
The 4 vertical sleeves were in good condition after the bridge broke away. Could the plastic stronger than the reinforced concrete? These sleeves formed a weak spot for Member 11/12 to leave the deck "cleanly".
All the reinforcement across the CJ had sheared off properly although only a few cross sections could be seen or made out from Fig 63.
Looking at the above OSHA drawings, showing a massive amount of rebar unable to be gripped soundly by the concrete, it is a waste of time to go the extreme length to prove the concrete adhersion at the CJ if constrcuted perfectly could have made a difference.
Any engineer investigating the 11/12 connection with the deck needs to appreciate the installation of 4 No. of 4" vertical plastic pipe sleeves and one 8" PVC drain pipe have severely compromised the integrity of the rebar in the vicinity by depriving the full development of the concrete bond with the steel bars. In another word there is no use in having sufficient rebar development lengths when there isn't sufficient concrete surrounding the steel bar!
RE: Miami Pedestrian Bridge, Part XIV
I'm not sure the thought of bringing criminal charges has been dropped yet.
Brad Waybright
It's all okay as long as it's okay.
RE: Miami Pedestrian Bridge, Part XIV
A construction joint with concrete poured at different times, resulting unavoidably slightly different shrinkages and creeps, is always a plane of weakness no matter how perfect the construction.
The Fig 63 by OSHA I posted last time in fact shows the performance of the CJ rather well. To any experienced RC professional the construction result looks normal, acceptable, average, no particular bad or good. The shear surafce is quite rough, irregular and deep at places because a significant amount first stage concret had been forcibly removed substantiating a significant amount of successful integration, bond or adhesion with the second stage concrete.
There were altogether 10 vertical bars (2x4x7S01, 2x6S07, see drawing B61) plus 50% of the axial rebar from Member 11 (2x4x7S11+2x7S03, see drawing B40) and one PT rod sheared off cleanly at this CJ.
The failure of the connection is actually due to what happens the beyond the CJ to the rear end of Member 12 where the majority of the rebar from Member 12 was exposed and had no bonding concrete. With the exception of a few small diameter bars severed, like the 4S01 in the deck from both directions, nearly all the other bars, 1x11S03, 2x3x7S01, 2x9S01,2x9S02, 2x2x8S07 from drawing B47, had the concrete stripped off revealing the bare steel. This is not the result of a good design when half the structural components didn't get stressed, let alone failed.
Pinning the hope in the soundness of the CJ won't hold any water because NTSB has already shown 11/12 has been massively underdesigned. NTSB would have by default assumed the Member 11/12 node constructed soundly without defect in ordedr to carry out the analysis.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
"No PT bars were sheared at the construction joint, at least not until the portion of the deck was cut loose for examination."
That is correct 3DDave. That's because the PT bars were not connected to any other bars. They simply ended in 'space' embedded in concrete. Thus, they moved intact, together with the concrete surrounding them.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Politics. If you shut the road then ABC is a failure. So they gambled they could fix it.
No-one does that voluntarily. Everyone tries to offload as much responsibility as they can. Despite all our "codes of ethics" it's how engineering works when things don't work.
RE: Miami Pedestrian Bridge, Part XIV
So true.
Figg's hired-gun (WJE) report dated Sept 18.2019, page 128 states:
Even though Figg's own EoR (Pate) was on site at the meeting hours before the collapse, whereby instructing the contractor and sub to continue with the stated re-stressing operation, before he traveled back to Tallahassee.
Engineers are becoming too much like f'n lawyers!
RE: Miami Pedestrian Bridge, Part XIV
Node 1/2 has a D/C Ratio of 2.15 while Node 11/12 has a D/C Ratio of 1.62.
Would we not expect the failure to more likely have been at Node 1/2 if the cause was inadequate design capacity?
Did FHWA not consider the capacity loss due to the pipe sleeves when arriving at the D/C of 1.62??
The differences between Node 1/2 and Node 11/12 have been discussed - size of Member 2 vs Member 11, thickness of diaphragm, amount of reinforcing across the CJ, angle of Member 2 vs Member 11. In short, Node 1/2 appears to be much more robust and obviously was not expecting assistance from future construction.
But the finding was that the D/C Ratio of the failed heel joint ( Node 11/12 ) was less than that of the heel joint at the other end of the truss which did not fail.
RE: Miami Pedestrian Bridge, Part XIV
Wasn’t my fault! I’d already left!
RE: Miami Pedestrian Bridge, Part XIV
Don't know about USA, but I've been told by three employers here that the insurer might walk away if you admit any fault without the insurer's prior approval.
RE: Miami Pedestrian Bridge, Part XIV
Although 1/2 was underdesigned by a bigger margin than 11/12 its members have more generous dimensions. All of then are 1'9" thick but 1 and 2 are both 3' wide whereas 11 &and 12 are 2' and 2'-10.5" wide respectively. 1/2 is type 1 and the drawings show no 4" pipe sleeves. This makes structural sense as in a bridge we always fix one end and allow the other end free to expand to avoid any thermal stress from the evironmental changes. Therefore if 11/12 were to be held down there is no need to install holding down bolts and sleeves at 1/2 end.
Having demand/capacity ratio exceeding 1.62 or higher doesn't necessarily cause an immediate failure. The bridge wasn't taking the full load at the time of collapse. Also using say a common load factor for dead load 1.4 and live load 1.6 the bridge at collapse didn't have an extra 40% dead load and the live load was zero so the structure was far from being stretched. NTSB's declaration of demand exceeding capacity is a judgement that the bridge design did not comply with the bridge design code.
As far as I know capacity reduction analysis including embedded items is never done for a footbridge in this catagory as no one would pay for knowing this information. Like many have said it is far easier to pass the problem down the line of the food chain. The designer, if he is experienced and has a conscience would probably add a note in the formwork drawing asking additional trimmer steel bars around the embedded pipe sleeves and leave the technician preparing the rebar drawing to sort out the rest. I use the word conscience because a good experienced engineer knows his bad arrangement, oversight or exclusion could kill and would try to discharge his duty with intregrity, so alerting others of a problem is the minimum one should do. A good rebar detailer, say in UK, will know the problem already and would attempt to distribute the stress around the sleeves with extra bars. After all a few steel bars cost very little but the attention to details is the quality of the engineering. I am not saying a few extra bars is what needs to save this bridge but it would surely force the rebar detailer talk to the engineer to hammer out a solution for an obviously poor arrangement.
That reminds me of FDOT Tomas Andres who marked up countless warnings on FIGG's initial design drawings about the obvious shortcomings. It was FDOT's responsibility to do peer review so he just offered his experience to a safer design.
There cannot be a better way to understand what is a good and bad rebar detailing just by comparing the condition of 1/2 with 11/12 after the collapse.
1/2 didnot suffer any visible structural damage when viewed from the ground. It was just moved.
11/12 on the other hand had 11, 12 and deck totally separated but the separation could be consequential to the joint connection failure.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
I am one of those who stopped reading the thread after a while when no new information came in and picked it up again so I wasn't aware of WJE's work. I wonder if it is me only having a problem to understand WJE's logic.
The cut and paste WJE's defense suggests :-
(1) WJE had accused no one monitored the cracks. This lets FIGG down.
(2) Structural/VSL own drawings mandated restressing operation to stop if existing cracks widen or new cracks observed.
(3) Evidence showed CJ was not roughened. This could cause existing cracks to widened when restressed and Structural/VSL would have several opportunities to observe.
(4) Structural/VSL could stop the operation if existing cracks widened and collapse could have been avoided.
By (1) I assume no one made any record/note of the cracks, no photo and no video. This also means nobody knew if existing cracks had narrowed or widened or any new cracks developed during the restressing. By (3) WJE now tells everybody the CJ was not roughened and the existing cracks could only widen and not close if restressed.
Since there was no crack monitoring, any restress would widen the cracks and the agreement was to halt restress if cracks widen so what was the purpose instructing VSL to restress? Was FIGG intentionally getting VSL into a trap knowing VSL was unlikely to carry out monitoring so it would not know the cracks widening and continue to destroy the bridge?
SInce there was no crack monitoring during restressing so no new crack information was available. WJE's evidence that the CJ wasn't roughened must be the same information that every contractural party had before VSL did the restressing. What was the evidence convinced FIGG/WJE that the CJ was not roughened and a restress would only widen the existing cracks? Why such information wasn't communicated to the contratual parties to stop the restressing?
LionelHutz (Electrical)
Spot on!
RE: Miami Pedestrian Bridge, Part XIV
1. A supervisor was on the deck during the retensioning. Sadly he sustained brain damage during the collapse.
This report shows they did not test the structure of the end of the deck/member-12/diaphragm
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
"No PT bars were sheared at the construction joint, at least not until the portion of the deck was cut loose for examination."
Hi 3DDave. What is the inference that we can draw from this fact?
Many thanks for your helpful input.
RE: Miami Pedestrian Bridge, Part XIV
It's because you left out the qualifier - PT NUT remained in place. Sorry that you mistyped that, and depended on what you believed you had typed instead of what was actually put into words.
The bar did not remain embedded in concrete.
Here's what I think you heard in your head when typing:
"They simply ended in 'space' embedded in concrete. Thus,
theythe embedded ends of the PT bars moved intact, together with the concrete surrounding them."In fact the entire upper bar remained in place and only the one end of the lower bar was embedded in concrete. The tension nut was not ever embedded.
RE: Miami Pedestrian Bridge, Part XIV
Here was the scene at the CJ showing the exposed PT rod and how it rip out from the Member 11, severed the links on it way out while the links cut the protecting plastic conduit of the PT rod. The breaking up of the lower section of Member 11, multiple cuts of the conduit and severance of the shear links were only possible if the lower PT rod was intact and firmly anchored during the collapse. Thus OSHA Fig 63 without the presence of the lower PT rod at the CJ must be the result of the post-colapse cutting by the workmen.
Initially I was intrigued by multiple cuts of the plastic conduit. Only after looking at how the PT rod left Member 11 could I put the two together and realised the cuts were done by the shear links.
RE: Miami Pedestrian Bridge, Part XIV
"No PT bars were sheared at the construction joint, at least not until the portion of the deck was cut loose for examination."
Hi 3DDave. What is the inference that we can draw from this fact?
Many thanks for your helpful input.
RE: Miami Pedestrian Bridge, Part XIV
Yes. Same as car accidents. Your insurer carries your liability, so your mistakes are now theirs to admit to, not yours. That’s the deal.
I think this is part of the general defense -Look at this shonky contractor! Not even monitoring the cracks! No wonder the bridge fell down!
RE: Miami Pedestrian Bridge, Part XIV
Don't believe everything you read.
RE: Miami Pedestrian Bridge, Part XIV
A structural guy working with reinforced concrete may see cracks differently from a mechanical guy.
When an engineer declares structural cracks the remedial work will have to be structural repair able to restore the original structural integrity of the structure, Otherwise the repair is just cosmetic.
Your Fig 42 is the same as OSHA Fig 18 which came from a group of photo Fig. 17 to 20 inclusively from the OSHA report depicting the general condition around the CJ.
When the bridge bottpm was fully supported in the casting yard the application of PT rod stress in Member 11 would shortened the disgonal member slightly as both concrete and rebar have elastic modulus. The cracking in your Fig 42 is a consequence of it. At that condition the bridge structural integrity had not been compromised. That would be my view from a retired engineer who designed, accepted , rejected, modified, strengthened and repaired reinforced concrete structures. Legally say at a court of law the reciver of this bridge at that condition would not be able to reject the work but may be able to demand sealing of the cracks say using epoxy resin injection.
The "structural" cracks I was talking about can be seen in OSHA Fig 32 to 38 inclusively. OSHA Fig 35 is a direct comparison of your Fig 42 but after the bridge had been placed in its final position and the PT rod stresses in 11 removed. As the CJ at that time shown a complete separation and a visible 11/12 bodily displacement of about 1/2" (OSHA Fig 40) relative to the deck. At this point the bridge could be considered damaged structurally and would no longer be servieable. Additionally the 4" crack depth in the deck showed by OSHA Fig. 30 and the 7" crack depth in diagonal 11 in OSHA Fig. 39 confirmed the bridge was beyond repair and must be partially demonlished, re-constructed, modified and strengthened if it were to be serviceable again.
Any engineer who has worked with reinforced concrete for say 20 years would know the bridge was gone just looking at the OSHA photos mentioned above.
RE: Miami Pedestrian Bridge, Part XIV
With the benefit of hindsight and with the mindset of critical analysis to understand the failure, I do not agree that the initial CJ crack represents a shortening of member 11 or for that matter, the slab. The photo was taken after concerns were raised when loud cracking noises were heard as the shoring was removed. Again, with hindsight, the structure was already straining, unexpectedly, under its own weight. Cracks due to shortening would and did occur prior to shoring removal.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The key issue which I can't find is any pictures of what was sticking out of the deck slab before the pour of the no 11 column. But from the picture above at 00.35 3rd June the only thing seemingly holding this joint together is that weedy looking green cage. Mention before has been made that they have no where near the amount of steel you need for the forces on member 11 and in fact it was only the PT rods which were really holding it together. Loosen them as they did and it literally fell apart and couldn't be recovered.
As soon as you got significant movement on that joint surely these bars would have sheared off?
The really criminal part for me was the action of tightening them up without really understanding what was happening / could happen.
This was the real straw which broke the bridge, but it may well have collapsed a bit later anyway.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
All concrete structures crack. It is a fact of life. What matters is how severe and where.
I have been interested in looking out for concrete that has received the best quality control and attention to details. Top of my list are the Charle De Gaulle airport in France and Oslo airport in Norway where bare concrete is part of the architectural features. Yet you can find cracks there. Some have been carefully patched up and some were left unattended but the amount is among the minimum you could find.
I shall explain the crack not structural in Sym P. le (Mechanical) 4 Jun 20 22:36 Fig. 42 which is depicted again below for quick reference. The bridge was still in the casting yard and after PT rod stresses applied.
The same crack changed in nature and severity after the bridge had been installed at its final position and on completion of the release of the PT rod stresses in Member 11.
That crack width was measured suggesting the one side had separated from the other side by approximately 1/2". I ignored the >1" width at the surface as it is the crack's interior that should be of interest to us.
If one looks at the design drawing B47, especially Section AA, one may be able to pick up information why the same crack changed by so much.
If PT rod tensions were applied while the bridge was in the casting yard the Member 11 would be axially compressed. The compression would also squeeze the deck axially because the PT rods anchors wanted to move from left to right. The deck was not taking load at that time.
When the bridge was placed at its final position the deck would be forced to take its design dead load and the member 11 would have one of the highest compressions in the structure. Member 11 could only develop the expected high compression if the deck provided the necessary reaction from which the deck must be stretched to develop tension to partly neutralise the previous compression from the PT rod stresses. By releasing PT rod stresses Member 11 anchores were no longer compressing the deck but wanted to deflected in the direction exactly opposite to what was before.
Thus in the MCM Fig. 42 the Member 11 was compressing the deck inward while in OSHA Fig 35 the Member 11 was stretching the deck outward. It should be obvious that the deck has a much greater scope in resisting Member 11 in compression, by buckling, than by tension of letting Member 11 to depart from the end connection. Thus the same crack in MCM Fig 42 and OSHA Fig 35 are different in nature. I for one would not lose sleep for minor concrete cracks permanently compression zone.
What stopping Member 11 moving outward and way from the end of the structure was its strcutual connection with the deck. Looking at Section AA many structural engineers would drop their jaws because there were no serious restraint availabe to prevent the whole thing from sliding out along top of the 8" drain pipe!
If we look at the rebar provision in drawing B47 there were some hefty 8S01, 8S02, 8S03 and 8S04 (1" diameter) at the rear of the deck but due to the physical obstruction of the 8" drain 8S03 and 8S04 were discontinued at the middle and turned 90 degree to avoid the drain pipe. OSHA Fig 62 shows all 8S01 to 8S04 inclusively intact after the failure but one side of 8S04 seems to have cast in the wrong position. The 8S01 is the lowest horizontal bar in OSHA Fig.62 below, then upward it is 8S02, 8S03 and 8S04. 8S03 was seen embedded between 8S01 and 8S02 on the right side. 8S01 to 8S04 were exposed after the surface layer of the concrete came off with 11/12. My point is had similar size horizonatal rebar were able to place above the 8" drain pipe the chance of a failure could have been significantly reduced.
Design drawing B47 Section AA alone can tell us why and how the bridge failed.
In horizontal direction the only reinforcement to stop 11/12 from sliding out of the deck were just two 4S01 (1/2" diameter). One snapped at the middle and evident in OSHA Fig 63 I post previously. In the vertical direction the designer did provide a modest amout of large diameter rebar but their effectiveness was severely compromised by the presence of the 4 No. of 4" vertical sleeves and the 8" drain which destroyed bondable sections of the reinforcement. In other word even if adequate development lengths had been provided in the vertival steel some sections of the concrete were weakened, too slender and were unable to distribute the full material stress. OSHA Fig 61 to 71 inclusively confirmed none of the vertical reinforcement had failed. They were just stripped off the concrete after failure.
RE: Miami Pedestrian Bridge, Part XIV
I don't need a lecture about cracking. Have seen all too many.
But my opinion stands. The crack while still in the casting yard should have been investigated further, as it showed separation between the flange and web.
The design was fatally flawed, and hopefully will result in concrete trusses never seeing the light of day again.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Hokie, I believe the correct conclusion would be that, "concrete trusses with fatal flaws should never see the light of day again." Concrete trusses have been used endlessly in civil structures, and will continue to be so used.
RE: Miami Pedestrian Bridge, Part XIV
I agree with saikee too that most of us dismiss cracks of that magnitude as “non structural”. I wouldn’t be prepared to condemn an engineer for dismissing initial cracking of that magnitude. We have the benefit of hindsight. They didn’t.
RE: Miami Pedestrian Bridge, Part XIV
There have been a few, but "endlessly" is stretching it. I have never seen one in person, and have more than forty years experience.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
https://en.wikipedia.org/wiki/Yokohama_North_Route
https://commons.wikimedia.org/wiki/Category:Okuma-...
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
With the exception of the picture at the bottom left, which may or may not be a component in an intended bridge, I think the others are steel. But if you can provide some documentation otherwise, I am interested. Early on in these discussion of the Miami footbridge, I did some googling as you have done, and didn't find much. There was one example of a concrete truss bridge in Europe, maybe Germany, and it was very bulky in appearance.
RE: Miami Pedestrian Bridge, Part XIV
A pure concrete truss with decks resting on it may have been much better. It is likely the end re bar would have been tied back into the lower flange with something more than the equivalent of chicken wire or with PT rods running the full length of the truss properly capturing the forces from the lateral member.
It's not the truss per se which was at fault here, but the way the whole bottom deck, top canopy and intermediate asymmetrical struts were put together complete with all sorts of weak points. Member 11 just didn't have enough reinforcement to attach it to the bottom deck and blew out. Poor design.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
A truss needs three things: compression, tension, and joints. Concrete is great in compression, useless in tension so requiring reinforcement, and tedious at best in joint design.
This was not just a truss, it was a truss/frame where the frame action was not addressed, and it had dissimilar chords without a rational way of getting the forces transferred between chords and webs. Differential volume change due to the construction sequence was the initiator of cracking. Altogether, an abject failure in design concept as well as execution. In addition, as a novel concept, it should have been tested. They had ample opportunity while it was still on the ground to load test it, probably using water bladders or sand bags as the test load.
RE: Miami Pedestrian Bridge, Part XIV
My argument has long been that the connection of Member 11 with the deck was rendered irrelevant by the faulty design. Hence, Member 12 became the constraint preventing 11 from moving north. The meager rebar passing from the deck through 12 only serves to tear at the deck adding to the illusion of punch out. The lower PT rod becomes the mechanism of failure but is also the final snag holding the structure together until it tears out of 11. As I've stated previously, the lower PT bar initially held the structure together but once the tension was released, the structure relaxed and snagged. Adding load to the structure only exaggerated the deflection to its demise.
Importantly, the sleeve around the PT rod would limit the relative movement of 11 to the deck to approx. 1/2 inch. Further movement is allowed by the tearing of 11.
We have not seen images of the initial crack at 12 while the structure was still in the yard.
Consider the following diagrams:
Also, the deck sag is greater along the center longitudinal axis than along the deck perimeter as is evidenced by the longitudinal crack along the deck underside in the drain cut-out.
Bridge Factors Photo 71 – View of crack in cut-out for drain pipe under deck on 3/12/18 at 10:20
a.m. (Source: Munilla Construction Management, MCM)
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
To me Member 12 wasn't an impenetrable fortress against the translation shear against Member 11. In fact it was almost like a lump of concrete attached to Member 11 that can be moved bodily with 11. That was the heart of the whole problem. If we temporarily ignore the contribution from the joint then structurally the only resistance of 12 against 11's horizontal shear is by bending its connection at its top with the canopy. Since 12 is about 18' high and the canopy is only 1' thick the rotational resistance at the canopy connection would be small even when there is a large displacement at the bottom of 12.
Your indication of the CJ sheared off along a horizontal plane, part red and part green, in your last sketch is not the path of the least resistance. The OSHA Fig. 58 to 70 inclusively show the shearing path was stepped. There was no concrete left on top of the 8" drain pipe in every one of the OSHA Figures. This substantiated after the CJ the failure plane had changed level to the top of the drain. The NTSB's version of the failure path is depicted by its Fig. 32 which is enclosed below.
In a way it was the combination of the 4 No. of 4" pipe sleeves and one 8" drain pipe that broke the back of the camel. These embedded items apart from disallowing the necessary rebar to be placed, especially in the horizontal direction where it was needed most, they created a weak pocket for 11/12 to slide out once the reinforcement in the A-B-C part of the CJ had sheared off.
In NTSB Fig. 32 the part C-D would be in tension and in design offered zero resistance from concrete. If you scrape the barrel the concrete tensile resistance is around 0.5 to 2 N/mm2 which is insignificant. I believe there were only 4 No. #4 bars, availoable to resist tension, from the deck longitudinal reinforcement which again not much a fight against the huge shearing force from the Member 11.
The last defence against the shearing from diagonal 11 is the shearing capacity along part D-E-F plus the two vertical shearing faces indicated by hatched areas C-D-E-H-C, on each side of Member 12. Unfortunately the end of the deck has 12 No. of end anachors from the longitutinal strand tendons. They prevented any substantial rebar to be inserted into the hatched areas but the drawing B47 did show a couple of #4 bar. Part D-E-F has a decent amount of Vertical reinfrecment available to withstand the horozontal shear but unfortnately none of them failed in shear but by bonding accaording to the OSHA figures.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
In my stick diagram above, I attempted to show relative movements in the nodal region and also proposed an offset displacement of 11. My reasoning for this is that as 12 bows, the base of 11 tips upward, and as the bridge sags, the top of 11 tips downward. My depiction of the movement of the top of 12 and both the canopy and deck deflection is greatly exaggerated. A one inch relative motion between the deck and 11 would not result in the same movement elsewhere in the structure, rather, significantly less.
It seems to me that 11 is ill equipped to support the loads imposed on it both in its intended role and far less in its effective role. There is no question that the base of 11 is being torn apart. I suggest the following image, the significance of which has been overlooked, reveals that the failure of 11 was the "next step" in the collapse. The upper PT Rod has yielded at the failure point in 11 which indicates that its base was still firmly positioned in 12 as 11 sheared. The failure cascaded from that point as 11 pancaked while being guided along the lower PT Rod. Note that the lower PT Rod was free to extend out of the blister cap while the upper PT Rod was not.
Evidence Testing and Results - Adrienne Lamm
(epoxybot (Structural) 18 Mar 18 17:25)
As I reviewed the dash cam video, I noted that prior to 12 descending, the 10/11/canopy node dropped significantly while the deck had also rotated significantly. This suggests that the slab rotated off of the base of 12 and I've previously noted evidence of torsional failure in the diaphragm. The collapse of 11 would have hammered its own base, the 11/12 node and also the lower portion of 12, increasing the likelihood of the rebar being stripped clean.
The Shear Plane Fallacy as I posted only refutes the suggestion that surface treatment or lack thereof played any role in the collapse. Although weaker shear surfaces are identified, I do not find it plausible that the bulk of concrete and rebar in Member 12 was weaker than the distressed Member 11.
You rightfully raised the issue of language. It has me thinking that when the cracks first appeared as the shoring was removed the question that needed to be asked was "Is the structure fit for moving?" and this should have guided the inspection and review at that time. Figg was well aware that the node was critical and that the structure needed to survive a certain amount of jostling. As such, I think that the cracks were structural issues prior to the move.
(edit: removed blank space)
RE: Miami Pedestrian Bridge, Part XIV
i do not see an indication of failure of the upper PT rod in Member 11.
Is there a better image?
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
After failure the rigid PT rod, especially the bottom one, was severely bent so one can say the PT rods might have yielded but the yielding is consequential to and not contributory to the bridge failure.
It may difficult for non-structural engineers to appreciate but if the connection failed the first thing happened to a PT rod would be a total stress relaxation, or zero stress, due to a total loss in the anchorage. If a PT rod later yielded it could only be the bending stress from distorting an initially straight 45mm diameter rod. This is totally different from the unform post-tensions in the brdige design.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
What we should all appreciate is that the 11/12 node detached from the deck. The structure accommodated with various deformations and held (though momentarily) until shortly after load was reapplied to the two PT rods in Member 11. Whereas the design intended this node to be inclusive of the deck, it was not.
The detachment of the 11/12 node resulted in the lower anchorages of the PT rods having competing loyalties to the detriment of Member 11.
If Member 11 failed due to excessive load and offset ends (by deformation), the PT rods would unload their energy into the collapsed member (I believe the rods are stretched about 1.4") and then be vulnerable to deformation as the member crushed further. The different deformations of the upper and lower PT rods are consistent with this failure scenario. In fact, had
Member 12(edit) the upper PT rod not deformed in this manner, it would disprove my theory.If Member 11 pushed through Member 12, the lower PT rod would tear out of the bottom of Member 11 but
Member 12(edit) the upper PT rod would be protected, at least initially.RE: Miami Pedestrian Bridge, Part XIV
Interestingly, your posted image goes more to support my theory than a multitude of alternative perspectives. Your image indicates that the two deformations are in the same plane which is more indicative of a single assault than multiple assaults which might have occurred with the collapsing structure.
RE: Miami Pedestrian Bridge, Part XIV
Is this the area which as supposed to be roughened?
The KISS principle applied to the failure.
Member 12; Negligible contribution to the structural strength.
Member 11; In compression.
The connection between member 11 and the deck; all of the calculations and speculation may be reduced to:
The connection will fail when the force on the connection exceeds X.
Member 11 is in compression and exerts a force of Y on the connection.
The upper PT rod is anchored such that it acts to add to the compressive force on member 11 but does not add to the force on the connection.
The lower PT rod is anchored in the deck.
Call the force on the lower PT rod Z.
Tension in the lower PT rod adds to the force on the connection.
When Y + Z exceeded X, the connection kicked out.
I can see the use of the PT rods to support the cantilevered portion of the span during transit, but once in place the rods were mostly superfluous.
Member 11 was under compression and the PT rods served to increase the compressive force, and in the case of the lower rod to increase the force on the connection.
The tension on the lower PT rod acted to open the crack rather than to close it.
All of the arguments and calculations come down to: When Y plus Z exceeded X, the bridge fell.
And it was done intentionally.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
The technical concept and ideas you are expressing are fundamentally correct. I would just say that it is better to say that the PT increased the concrete compressive stresses in member #11 or increased the shear stresses at the pour joint. I am being picky but the compressive force in the member was not increased due to the PT since the compressive member force is actually the sum of the PT (PT force is negative since it is tension) and the concrete (this is equal to the member force from the frame analysis). It is an important concept to think about the members this way when doing PT design.
Without any external forces, I can tighten a rod in a chunk of concrete and the concrete compressive stresses increase and the PT increases (in tension) but the chunk of concrete takes no more compressive load/force. It's member load or force is still zero. PT is equal and opposite to magnitude of the concrete.
When you think about post tensioned concrete or other residual stresses (tempered glass, wood shrinkage, cooling rolled steel elements etc.) in this way, it makes it less confusing/complicated and that is the only reason that I point it out.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
"Tension in the lower PT rod adds to the force on the connection."
But this is wrong. By definition, the force "on the connection" is a force that is applied BETWEEN #11 and the deck. That means we are looking for a force OUTSIDE #11, that is BETWEEN #11 and the deck. This is the shear force between #11 and the deck. It is commonly agreed that this force was about 1,500 kips (1.5 million pounds.)
Note: tension in the lower PT rod is INSIDE #11. Therefore, it is not outside #11.
The bridge would have failed no matter what the tension in the lower PT rod. i.e. The failure condition of the bridge was independent of the tension force in the lower PT rod. Failure was caused by the fact that there was no tensile steel provided in the deck that could have prevented 1.5 million pounds in #11 from travelling north.
RE: Miami Pedestrian Bridge, Part XIV
It is certain that this is neither designed as a frame, nor is it designed to avoid moment development which clearly caused a variety of cracks that a pure truss could not have.
I mention this as the linked Brady Heywood article calls this a truss; it's form is more of an openwork beam, not much different than if it had been first cast with a solid web that had triangles cut into it, rather than an assemblage of individual parts that normally comprise a frame or a truss. The main difference there is the localized web reinforcement to account for the loss of shear continuity from chopping so much out of the web.
RE: Miami Pedestrian Bridge, Part XIV
If there are examples where a truss member failed under load and the structure didn't collapse it would be interesting to see them, but just two doesn't seem to be enough.
RE: Miami Pedestrian Bridge, Part XIV
The lower PT rod was anchored to the deck below the crack.
After the collapse and the destruction of a lot of concrete, the end of the lower PT rod appears to be still anchored to the deck, despite being ripped almost entirely out of member 11.
The crack is opening in a horizontal direction.
This strongly implies that the concrete had already separated and that the joint was held together by the reinforcement.
Here is the first indication of failure.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
I agree, having trusses on both sides does not make the structure redundant.
RE: Miami Pedestrian Bridge, Part XIV
I'm confused. I thought that because the lower PT rod was anchored to the deck at the bottom, that tension in the rod created compression in the joint, but because the joint was not perpendicular to the PT rod, that a shear force was also applied to the joint? (Since the top of the upper PT rod was not exposed, I assume that it was not Post tensioned.) ((yes I know about assumptions.)
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Here the crack is opening in a horizontal direction.
Yes, it's being measured diagonally but the movement is horizontal.
If the crack was opening diagonally, the horizontal crack to the right would also be opening.
The actual displacement is greater than the measured amount.
Looking at this sketch, the lower PT rod passes through the plane of failure.
The tension in the PT rod may be resolved into horizontal and a vertical components.
The vertical component adds to the friction of the failure plane but does nothing to close a horizontal crack.
The horizontal component of the PT tension acts to open rather than close the crack.
[quote Earth Pi]Without any external forces, I can tighten a rod in a chunk of concrete and the concrete compressive stresses increase and the PT increases (in tension) but the chunk of concrete takes no more compressive load/force. It's member load or force is still zero. PT is equal and opposite to magnitude of the concrete.(/quote)
The point is that one end of the lower PT rod is anchored outside of member 11 and did exert a force such as to cause the collapse.
Your comment is valid for the upper PT rod, but not for the lower PT rod.
The attempt to capture the node and to close the crack with a force in the opposite direction was particularly ill advised.
Talk about dumb and dumber.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
In contrast with the previous answer you received to your question, I have always been of the opinion that the failure to recognize frame action was a primary reason for this failure. In steel trusses, you can sometimes get away with ignoring joint moments, due to the inherent ductility of steel. Not so with concrete, and that is why concrete trusses are exceedingly rare and not at all practical. This was a novel structure, and should have been tested before erection. A load test while it was still in the casting yard would have exposed its flaws.
RE: Miami Pedestrian Bridge, Part XIV
Trusses and frames have been around since before the middle ages. It is well known that both trusses and frames must have shear reinforcement at each node, where the forces in each element change direction. This particular truss/frame had no shear reinforcement in the deck connecting with the northward force in strut #11. Thus, the northward force in #11 kept moving northward. The rest is all hot air.
RE: Miami Pedestrian Bridge, Part XIV
Perhaps you can share with us an example of another structure of this type.
RE: Miami Pedestrian Bridge, Part XIV
"whose vertical members are in tension and whose diagonal members are in compression"
So they took a design that was patented by a millwright over 175 years ago, pimped it up, failed to understand the basic forces and broke it.
I wonder if the drain, sleeves, and conduit were steel instead of plastic if it may have held together long enough for someone to condemn it without anyone dying.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Hokie 66 says "Perhaps you can share with us an example of another structure of this type."
Yes, every single truss/frame on the planet is a structure of a similar type. Every single truss/frame on the planet has got shear reinforcing at EACH NODE - because EACH NODE in a truss/frame necessarily connects a force in compression with a force in tension or an opposing force. This Miami truss/frame has got, effectively, zero shear steel at the node connecting the compression force in #11 with a tension force in the deck (north force in #11 with south force in deck). If you assert that it does have such shear reinforcing, please point out where it is.
RE: Miami Pedestrian Bridge, Part XIV
Howe, Pratt, and Warren are the most common configurations of trusses, and they are all commonly used in steel trusses.
There have been few, very few, examples of concrete trusses, mostly in Europe. I know of one concrete truss footbridge in California, now abandoned.
RE: Miami Pedestrian Bridge, Part XIV
Also FIGG proposes that it would be like an I beam.They seem to have forgotten that in an I beam the flanges are welded to (or rolled with) the web?
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Hokie66, are you suggesting that because this truss is formed in concrete it is exempt from the requirement that EVERY truss/frame requires shear reinforcement at the nodes ?
Strut #11 has a load of 1,500,000 pounds pressing north. Can you identify any structure within the truss/frame that balances that force to prevent strut #11 from travelling north ?
RE: Miami Pedestrian Bridge, Part XIV
To your second point - as I recall, both PT rods were re-tensioned, alternating in 50 kip increments.
Kinda scarySo tragic to think of working on a joint having 1500 kips load which was less than 50 kips away from failing and causing the structure to collapse and then intentionally adding that last 50 kip load. And the damn thing killing so many.(edit - I apologize for being so glib. That was grossly insensitive.)
RE: Miami Pedestrian Bridge, Part XIV
Were I to have designed the joints, there would have been generous weldments to firmly anchor PT forces and distribute bearing and rotational eccentricity forces to significant areas of concrete, with the steel providing shear transfers. And I would offer those weldments at nodes 1/2 and 11/12 for connection to your 25 square inches of tension reinforcing.
Together we could bring over 80 years to a project.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
I have thought about this too. I believe if the embedded items were strong enough to distribute the internal stress like a rebar the bridge could have lasted a lot longer. For that to happen the sleeves and pipes would have to be pretty thick and physically structural elements.
When the embedded sleeves, conduits and pipes are plastic with radically different in elasticity to the concrete and rebar the concrete surrounding them would be forced into higher stress due a reduction of area. The areas around these embedded services had formed hinges once the concrete had been crushed internally allowing the rebar a much higher degree of movements not permitted in a serviceable structure. The crushed concrete around the hinged areas would be loosened resulting the structural bonding of the concrete with rebar confined further high up in the elevation until the remaining available bonded length could no longer sustain the structure. In other word because of the embedded items wereable to nullify a section of the bonded length of the rebar the provided original development length had suddenly become inadequate.
In any design in reinforced concrete the fundamental assumption or requirement is there should be no slip between the concrete and the steel reinforcement and the two must have identical strain. Once this breaks down the design fails.
Like I mentioned previously all the rebar in the CJ were sheared off but all the vertical rebar in 12 were intact. None of them failed structurally. The concrete just couldn't grip the bars.
RE: Miami Pedestrian Bridge, Part XIV
Respectfully I beg to differ. No shear reinforcement is not the same as inadequate shear reinforcement provisions.
With reference to the NTSB Fig 32 posted most recently by Waross 15 Jun 20 23:06 I have established the rebar across the failed interface in the enclose table.
The area CD was in tension so strictly speaking not shear reinforcement but were available to stop the failure.
There were substantial vertical rebar of 2x#11 and 8x#7 across DF. They could have been able to resist the horizontal shear had the bars' development length not compromise by the crushed concrete around the embedded item. In the end these bars failed by bonding.
Apart from the sheared off reinforcement in the CJ (showed in construction drawing B61, B40) nearly all the rebar I quoted in above are visible from the OSHA report. An isometric cut out view prepared by NTSB final report as Fig 17, which I posted on 3 Jun 20 00:35, also shows the extent of the shear reinforcment available.
RE: Miami Pedestrian Bridge, Part XIV
I can agree that, in the case of Node 11/12, the results suggest it may as well not have had any shear reinforcing "at all".
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The north face of rebar 9s01, 9s02 and
9s048s07 can be seen from every OSHA figure depicting the rear of the deck. Their east face can be seen on both south and west sides after 11/12 was blownout as evident in OSHA Fig 60 and 63, most recently posted on 2 Jun 20 01:24 here.I believe these bars, forming a group of 7 on each side of 11/12, were shear reinforcement for the the longitudinal tendon forces applied to the 2'-3.785" thick deck against the rest of the 4'-3.875" deep edge beam. They were never intended to restrain 11/12 from blowing out.
During the course of bridge failure the two sets of 9s01, 9s02 and 8s07 were suddenly called upon to stop 11/12 from moving out. They could have failed by shearing off each steel cross sectional area if sufficient length of the rebar had been embedded above and below the shearing plane. As it happened the shearing plane was at the level of 8" PVC drain pipe and evidently above this level the embedded length of 9s01, 9s02 and 8s07 were insufficient (because a failure plane was never envisaged there) so the concrete broke off instead of steel bars sheared off. Structiurally speaking the force needed to break the concrete bond off from the rebar here was less than that required to shear off the 4 number of #9 and 4 number of #8 steel bars. The bond had also been severely compromised by the close proximity to the 4 No. of the 4" vertical plastic sleeves.
To me there was no anomaly of 9s01, 9s02 and 8s07. They were just bars designed for other purpose inside the connection that the blown-out surface interfering with. Approximately a length of 45 times the diameter of a rebar is needed to be fully embedded in sound concrete to allow the steel stress to be fully developed. By inspection 9s01 and 9s02 do not have 45*1.125 = 50" above the failure surface.
RE: Miami Pedestrian Bridge, Part XIV
This speaks not only to the level of care taken during construction, but also to the attention to detail taken by those who are appointed to review this sorry affair and did not point this out. This is not a figment of my imagination. I am not interested in comparing reality to the theoretical performance expectations of mythical structures.
RE: Miami Pedestrian Bridge, Part XIV
I see curvy black things that weave around the vertical 2by. They look like rebar but are blacker. Also all the blue conduit running side by side seem to leave no room for concrete between them. And whats the smooth black pipe hung with ziptie under the deck floor? I'm mystified.
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Would the 1,500,000 lbs plus the added tension of the PT bars be close to the failure point of # 11 under compression?
Thanks.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
waross, I believe this has been covered with the conclusion being that it is close. But that would be a theoretical limit below which significant confidence could be placed that failure would not occur. In this situation, the design intentions were not met so the additional question is what parameters should guide the calculations.
RE: Miami Pedestrian Bridge, Part XIV
I wouldn't be too harsh on the quality of workmanship here as it wasn't a contributory factor to the collapse.
From the available photo the rebar of 12 were seen in reasonable format and position before the pour. By comparing them with the heavily distorted final positions after the failure can be misleading and even dangerous because we do not have a 3D image showing the exact embedded position of every bar. The important consideration should be had any bar been omitted, changed size or cast wrongly?
Fixing reinforcement is not an exact science. No matter how clever is the designer's concept we still have to rely on mostly emi-skilled labourers to execute the works of fixing the bars and erecting the formwork. The accuracy they use is about an quarter of an inch if we get lucky.
The main failing of this bridge is the designer has not thought of the congestion from the embedded sleeves, ducts and pipes resulting omission of vital reinforcement to link the 11/12 solidly with the deck. The drawings show a symmetrical design, for drawing office economy, but the site work show a few odd bars lapped at slightly different locations asymmetrically for avoiding services is a fact of life in every reinforced concrete structure.
RE: Miami Pedestrian Bridge, Part XIV
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
I think the curvy black things are grout bleed tubes for the PT rods. The smooth black pipe looks like a screed rail to aid pouring the deck.
Is there any redeeming structural value in the Member 11 PT rods by grouting them had the structure been successfully positioned?
Several photos of the work in progress. The top mat of deck rebar has not been installed in the first photo (Photo 8). The final installation of the grout bleed tubes extend upwards in the filet (Photo 15). They probably required a hole to be drilled in the form work (Fig. 30)
RE: Miami Pedestrian Bridge, Part XIV
The relaxed rods would have no structural contribution in a compression member. Actually, as the compressiomn members like M11 "creep" and shorten under long term compressive loads, the rod will push on the closure at the top, and probably should have a void provided to maintain a cap or plug at the top.
RE: Miami Pedestrian Bridge, Part XIV
I try to answer your question as I think you could be barking on the wrong tree by thinking the compressive stress played a significant role in this bridge. Speaking from a civil/structural background I would say a reinforced concrete structure rarely fails in compression.
Above is the Figg's calc submitted to NTSB. Most of it was computer print out but some hand calculations were added as sanity check. The design force in 11 was 1664k.
The design compressive stress in concrete can vary slightly with design codes but the main stream ACI318 prescribes 0.85f'c for 4000psi concrete and reduce 0.05 per 1000psi above 4000psi. Thus the charcateristic compressive stress is 0.75f'c fora specified strength 6000psi (see construction drawing B38). 11 has a dimension of 2'-0" by 1'-9" so the compression capcity from the concrete alone should be at least 0.75x6000x21x24/1000 = 2268k or 1012 ton without even consider the contribution from the compression reinfrcement. Since the bridge weighs 950 ton (construction drawing B37) so compression isn't a problem.
After the collapse NTSB cut 8 cores out of the bridge structure. The three cores from the deck have recorded failure stresses between 8580 to 10770 psi which are comfortably above the specified strength of 6000 psi. It is normal for the site concrete to be higher than the specifed strength. If a contractor supplies a poorer mix design that fails below the specified strength he could be asked to demolish the bridge before it leave the casting yard. Due to the standard deviation in the concrete quality control there is usually a modest safety factor available but never included in the design.
Therefore the concrete compression in 11 will not be a significant contributor to the failed bridge both in theory and practise.
RE: Miami Pedestrian Bridge, Part XIV
Must admit I am not up to date with various design code changes but conduits for post-tension tendons and rods were used to be designed either grouted and ungrouted.
It is possible for long term durability the tendons and rod should be protected against corrosion and it makes sense to have them surrounded and protected by grout.
However there can be occasions where design conditions mandate a change in the tendon or rod tension so leaving the system not grouted is the only way. Over 40 years ago I designed a 2m thick roof experimental hall to house a nuclea fusion JET device. I had to cast the roof in 1m wide beams. Each had to be cast with shear key abutting the other. Each beam was a standard reinforced concrete design in one direction. On completion the other direction was stressed together by PT rods to act as a monolithic slab. This arrangement is for the eventual decomissioning to allow the roof to be demolished in small pieces after it has been soaked with years of radiation. The building is still operational today and I do not think the design codes would or could dictate the grouting arrangement of every post tension tendon or rod.
RE: Miami Pedestrian Bridge, Part XIV
Consider the following as the explanation for the collapse sequence. It's about the split at the bottom of Member 11.
If the lower tab loses its integrity, the upper tab takes the load and kicks out. Member 11 pancakes guided by the lower PT rod. I still contend that the slab rotates the diaphragm off of the bottom of Member 12.
There is a plethora of cracking all throughout the 11/12/diaphragm from a variety of causes but none of those other causes advanced to the extent of collapsing the structure.
RE: Miami Pedestrian Bridge, Part XIV
The heavier one is above the drain and shows some displacement. It seems to follow the trajectory of the upper PT rod and would seem to align with cracking in Member 11.
RE: Miami Pedestrian Bridge, Part XIV
Not sure what the last 15 years have brought, but 20 years ago it was required that PT be grouted in exposed structures and grouting was not required in protected structures, as in a structure with a roof membrane. That seems to make sense. As one architect loved to say "It seemed like a good idea at the time", I guess.
As a bit of history, one practice early in the use of PT in slabs, and from the period of paper wrapped strands to prevent bond and allow post tensioning after the concrete has cured, the system was touted as being waterproof if the compressive stresses were 300 psi or greater. The benefit was parking structures did not need a waterproof membrane, thereby avoiding the associated wear and repair.
Not the best idea - but it did provide a lot of opportunities for repair work. And the paper wrapping served well to maintain moisture in contact with the strands.
RE: Miami Pedestrian Bridge, Part XIV
My interpretation of the spliting at bottom of Member 11 is a lot simpler than yours.
Before the collapse the inner vertical face of the 2'-0" thick diaphram beam was flush with the inner face of the North pier. When the bridge started to fall it kinked at 9/10 with the deck and 10/11 with the canopy. Thus 9/10/deck and 10/11/canopy were two hinges and the bridge was no longer a structure but a mechanism.
The deck was well designed and didn't break into pieces but was virtual intact after the fall, right? So during the drop of 9/10/deck to the ground the deck's underside or more precisely the underside of 12 would have uplifted from the bearings and momentarily leaned against the southern edge of the North pier.
If the deck deformed to a "V" shape then the physical distance between the two extremities of the deck had to be shorten. This is just the property of a triangle that the sum of two sides is bigger than the third side. We now know at the Southern end the 1/2 of the bridge was resting on the Southern pier after the failure so if there were longitudinal shortening a relatively small amount would have taken place there. At the North end due to the "V" geometry and the underside of 12 was leaning against the edge of the pier there had to be a sliding action at the pier edge as a result from any reduction in the bridge's overall length. In fact the shortening was at least 2'-0" in order to enable the deck plus the diaphram beam to clear off the Northen pier.
Rather unfortunately Member 12 is 10.5" wider than the width of the diaphram beam so at the precise moment when the diaphram was able to clear the pier and commenced the drop Member 12 would be still caught up at top of the Northern pier because it still had 10.5" for sliding out. To me it was the dropping of the heavy deck that rip out the lower PT rod in Member 11 and assisted in further breaking out the 11/12 connection.
RE: Miami Pedestrian Bridge, Part XIV
At the beginning of the collapse the 11/12 support would move inwards due to 9/10 formed a hinge resulting the bridge deflected downards and shortened the span. This is indicated by the first sketch showing the diaphram started to lift off from the bearings. At some point the underside of diaphram would be able to lean against the southern edge of the northern pier. The motion from that point onward would be sliding.
When the bridge kept on deflecting there came a time when the diaphram could clear off the northern pier but the Member 12 couldn't because it has an extra 10.5" to go yet. At this moment the half span weight of the bridge would suddenly supported by the 21" wide Member 12 instead previously by the entire length of the diaphram which is 18'-2" long. The support length was abruptly reduced by a factor of 10. Thus Member 12 would split. The deck was able to drop freely down and rip out the lower PT rod in Member 11. I estimate the lower PT rod could have about 3" concrete from the external surface so it is easier to rip it out sideway than breaking in tension the 1.75" diameter PT rod.
RE: Miami Pedestrian Bridge, Part XIV
Refer to my "cut-and-paste mashup" in Part 12 - MikeW7 (Electrical) 22 Jul 19 03:24. It's crude, but the sequence of events seems to follow what was observed in the truck dash-cam video. Image 2 assumes the 11-12-canopy triangle remained relatively intact after the hinging began, in which case the canopy hinge combined with the rigid 12-canopy "L" section would have forced the 11-12 joint off the deck almost immediately and crushed the lower end of 11 in the pinch point where the lower end of 12 overhangs the deck end.
RE: Miami Pedestrian Bridge, Part XIV
Your "cut and paste" is pretty descriptive and definitely helpful. I think it needs a bit of scale, and removing M11 in pic 4 may be deceptive in the case of M12. Specifically, pic 4 shows M12 falling behind the pylon. That begs the question how did it climb back atop the pylon? I suggest M11 was still attached to the bottom of M12 and prevented M12 from dropping behind the pylon. There was 4 feet of the top of the pylon available to catch M12 before the deck started sliding south. This could explain some of the damage to M11 and the missing concrete from M11 and M12. It may also have contributed to the bend seen in the upper PT rod of M11. If the concrete near the base of M11 were damaged, either before initiation of collapse or during, and M12 were falling over the end of the deck or pylon with the lower anchor plate of the upper PT rod still embedded, the 35 kips or so DL in M12, supplemented by the force necessary to fail the canopy at Node 10/11, would bend the upper PT rod of M11, resulting in the bend seen in the upper PT rod in photos of M11 leaning on the pylon. There has been discussion of the upper PT rod being bent due to axial compression, but that seems unlikely to me because the upper end of the rod was free to move (it had just been tensioned for a second time) and the rod was not grouted so was not bonded.
The scale of pic 4 shows the structure having dropped maybe 20 feet (top of truss about level with top of pylon) at Node 9/10 while Diaphragm 2 is still on the pylon. The spreadsheet posted here
https://res.cloudinary.com/engineering-com/image/u...
shows the diaphragm likely slipped off the pylon when Node 9/10 dropped about 11 feet.
The comments of 22 Jul 19 20:46 seem to hold today.
The numbers show that as Node 10/11 passes what was the original elevation of the top of the deck , N10/11 has moved north about 1 foot and the geometry shows diagonal M11 to be about 5 feet longer than the length of the canopy from the top of M12 to Node 10/11. Thus the base of M12 can be pushed about 6 feet northward from its original position. Then as Node 10/11 continues to fall below the top of the pylon it is M11 that restrains M12 and/or drags the bottom of M12 to its final position. M11 experiences a bit of damage in doing so.
Thank you,
RE: Miami Pedestrian Bridge, Part XIV
- The truck dash-cam video clearly shows 12 starting to dropping behind the pier at about the 11 second mark when the deck hinge has fallen about 1/3 the way to the street.
- I can't surmise an exact description of what happened to the lower half of 11, but whatever remained of it was most likely crushed, in or before the deck-12 pinch point, as soon as member 12 slid off the deck.
- When the "falling man" is visible a couple of frames later the deck hinge has almost hit the street (maybe one foot of daylight is still visible) and the 12-canopy "L" has fallen so far the canopy hinge appears to be resting on the remains of 11. Also note at this time that the deck end appears to still be on the pier.
- As the north section collapses on impact with the street you can see the deck slide off the pier, the "elbow" of the "L" appears to rotate on top of the pier until 12 is level, then the canopy hinge drags the "L" to it's final resting position with the base of 12 on top of the pier.
- With the exception of the actual collapse of the north bridge section, these events are what I tried to show in my cut and paste diagrams. The diagrams aren't accurate to the millimeter, but they're "close enough" to understand the torturous journey of member 12 as shown in the dash-cam video.
NOTE: numerous small edits since I first posted this.RE: Miami Pedestrian Bridge, Part XIV
Your postulation assumed the hinge at 9/10 formed first, secondly the 11/12/canopy remained relatively intact and thirdly the rigid canopy “L” would have forced 11/12 joint off the deck.
The weakness in the model are :-
(1) The collapse was initiated by the hinge at 9/100.
(2) There was no joint blowout or a need of it.
(3) The deck finally rest against the northern pier and not flatly on the ground. If this wasn’t the intention the model has no explanation how the deck ended as it did.
(4) The canopy “L” was rigid and able to forced 11/12 out of the deck.
Answer to (1) The design of the bridge resembles to an “I” beam with the canopy as the top flange (in compression) and the deck as the bottom flange (in tension). The diagonal members are the equivalent web. In performing this structural duty the bridge’s neutral axis, where the stress is zero, would be somewhere in the middle of it 18’ height. If for whatever reason the web fails, say by the deck could not hold Member 11/12 in position, the support of the whole bridge would passes to the 2’ thick deck as it is the only bit left resting on the two piers. The second moment of area, which is proportional to the cube of structure height, would then be drastically reduced. The height reduction from 18’ to 2’ would be accompanied by a shockingly high stress increase in the order of 729 times. Clearly the deck had no such resisting ability but to buckle or hinge. Thus between the hinge of the deck and a functional loss of the web the former is less likely. Additionally the whole deck has been uniformly reinforced and post-tensioned by tendons without one part made stronger than the other. If the deck structure fails it should be at the point of maximum bending moment near the mid span and not at the end span.
Answer to (2) It was OSHA who used blow-out 10 times in its report. The importance of a blow-out is that it is sudden and most probably the starting point of a major structural collapse. This blow-out occurred when 11/12 was detaching from the diaphragm.
Answer to (3) I have already explained with sketches how the deck dropped flat onto the ground with my post on 19 Jun 20 12:14. This ties in well with geometry computation mentioned in Vance Wiley (Structural)’s post on 19 Jun 20 18:26.
Answer to (4) Member 12 and the canopy are structurally superfluous to this bridge as it will stand if you chop them off and install the canopy post-tension anchors at the next bay. In fact a standard Warren truss does not have them. The easiest way to appreciate their insignificance is at each node the member forces must hold each other in equilibrium. At the top of 12 there was no opposing member. Neither there was any member on the other side of the canopy to balance whatever axial force inside the canopy. Therefore these two members have no significant internal forces. Structurally top of 12 has to support a portion of the canopy’s dead weight while the canopy provides anchorage for the prestressing tendons, in additional to its function as a weather shield.
The canopy “L” was NOT rigid enough to be able to dislodge 11/12 out of the deck.
RE: Miami Pedestrian Bridge, Part XIV
The top of M12 was pushed north about 2 inches as Node 10/11 fell thru a straight line from the south bearing to the top of M12.
At the same time, as the deck failed in bending at Node 9/10 and dropped about the same amount, 3 feet, the top of the deck and diaphragm 2 rotated into the fall, translating the base of M12 south about (3' drop/40' bay*48" = ) 3.6 inches. So now M12 is leaning north 5.6 inches out of plumb while the deck is now sloping south and down 3 feet in 40 feet. That deck slope should indicate M12 would be moving south at the top 3/40 * 16 feet = 14.4 inches.
Rotations, strains, and moments in M12 at the top of the deck are now equivalent to the top of M12 being forced north 20 inches from its original relationship to the deck. The remains of M12 suggest a bending failure with tension on the south face at the bottom of M12. Until it failed, M12 was applying torque on the top corner of the "blow out" block. While M12 possessed stiffness due to its 34.5 inch dimension, it only lapped ontothe deck by 24".
What was the magnitude of that moment at the base of M12? I hope someone with access to some design aids or computer programs can tell us that. I suspect M12 failed early in the collapse, maybe before Node 10/11 dropped 3 feet. We can see some damage at the underside of the canopy and south face of
M11M12.Also, the damage to M11, in viewing the dash cam video of the collapse in the excellent frame by frame video work ( the creator of which I cannot identify now after 15 minutes of searching so I might give proper credit) posted , I see what appears to be Member 11 folding toward the canopy as the structure drops maybe 10 feet or so. Did M11 fail at Node 10/11 early in the collapse?
Regarding the initial movements of M12, the numbers support the post by SFCharlie (Computer)8 Jul 19 02:15
and his comments on 3 frames from the dash cam "(continues as 12 appears to remain vertical)", "(continues as 12 appears to remain vertical)", and "(Finally 12 tips)".
He also noted an angle change between M10 and M11 early in the sequence.
Thank you,
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Hard to watch him criticize FIGG for not checking their work while his work needs checking.
It is Member TWELVE.
Fortunately no one died from his work. And in this case he can make his own deadlines.
He does present it logically, as I see so far. Much more to read.
Edit: Thanks for the link.
RE: Miami Pedestrian Bridge, Part XIV
The Heywood presentation does succinctly tell part of the story of the fatal problems with this structure, and why the road should have been closed.
Edit: On further examination, I see that you were referring to the reference to "Member 2" in that one photo. I am yet to figure our the perspective of that photo. Taken 2 days prior to the collapse? Hard to believe.
RE: Miami Pedestrian Bridge, Part XIV
threetwo blue flex tubes appear into the left (ultimately north) of the two white pipes that weakened the diaphragm twelve joint allowing the blowout, (edit) so I think it is a close in wide angle shot.
RE: Miami Pedestrian Bridge, Part XIV
Can anyone provide a link to PART 1: BRADY HEYWOOD BLOG please?
I cannot find it in Part 2 nor their web page.
I would like to read it.
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
https://www.bradyheywood.com.au/miami-bridge-failu...
RE: Miami Pedestrian Bridge, Part XIV
https://www.bradyheywood.com.au/blogs/
RE: Miami Pedestrian Bridge, Part XIV
Well written and clearly presented.
I would have went directly to post tensioning here - I cannot think of one
piece of reinforcingmember in this structure that is primarily in direct tension as a working member and depends on normal reinforcing. As presented, this statement appears to describe the post tensioning as - "additional"?He starts counting time from the first indication of a problem - the blowout, and makes this statement after the picture of the bridge hitting the roadway.
Now if memory serves me from my elementary physics over 60 years ago "d=1/2at^2".
In 429 milliseconds a dropped bowling ball will drop less than 3 feet. Have I lost it? Has something changed that I did not notice?
The structure is about 18 feet above the street. The bowling ball will need about 1.05 seconds to hit the street. I would suspect a bit longer for the structure, because some progressive nature exists and at least minimal ductility. Rotating about the south bearing, the center of the bridge would drop 3 feet in 429 ms, ane the north end would drop only 6 feet.
Help me here.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
The north end of the bridge falls faster than 9.81m/s^2. It is not a free falling object. There is a rotational force added by the south pier which makes the north end accelerate faster. That is why the falling person is "slower" than the north end of the south segment. This is not intuitive at all that the north end is actually accelerating faster to the ground due to the south support. The CG of the south bridge segment is falling at a lower acceleration than 9.81 m/s^2. And obviously the south end of the south segment has zero vertical acceleration.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Kinetic energy = KE = 0
Potential energy = PE = 0
Instantaneously remove one of the supports. Beam begins to rotate downwards.
When it has rotated by an angle R it has rotational velocity Q and
PE = -mgRL2/2
KE = Integral of [m(Qx)2/2] wrt x, from x=0 to x=L.
These two must sum to zero, leading to
Q = sqrt(3gR/L)
If the falling end was accelerating downwards at g, the beam would have
Q = sqrt(2gR/L)
So the free end is accelerating at greater than g.
(Not that this ~20% difference explains the much larger difference that tweaked Vance W's interest.)
RE: Miami Pedestrian Bridge, Part XIV
The real reason that we all know is that the member in compression, as it should have been, member 11, just wasn't attached to the lower part of the truss - the deck - with sufficient strength / re-reinforcement. The joint area at the deck, 11 & 12 node was not provided with enough steel to be able to connect member 11 to the bottom deck. The drain pipe, those 4 white plastic tubes and a host of other small black tubes plus the PT rods and their plates made it virtually impossible for member 11 to be connected to the deck with enough strength. THAT is the key issue with this concrete truss.
Now it's a bit of what iffery here, but IF those temporary tendons in member 11 hadn't been there would there have been more room for some steel to connect member 11 to the deck? Who knows?, but it won't have helped. Normally you wouldn't need to have 2 PT rods and their plates in such a truss. A bit like why those white plastic tubes were moved from somewhere where they caused no problem right into a highly congested location which again prevented sufficient steel from being included in that high stress area.
One layer of hole in the swiss cheese gone.
Add in that concrete trusses on their own may have worked as you could pour them in one go on their side to avoid all these horrible cold joints is a major downside to concrete trusses built into a slab / deck. Add in the cold joint was at a shallow angle to the compressive load and there's your hole in the swiss cheese appearing again.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
As a quick check, I normally go to limit conditions - even more so than your rigid and uniform beam assumptions. In my check for the time of fall I used the parameters of a point mass at center of span, weightless and rigid structure, and removed the north support. It seems to me under those conditions the north end would fall at the rate of 2g and the nuances of the problem could only slow the fall. Under these "ideal" conditions the fall distance at the north end becomes just less than 6 feet in 429 milliseconds.
In the actual case at hand, previous calcs found the north end was on the pylon until Node 9/10 dropped about 10 feet. As the deck folded somewhere near Node 9/10 the yielding of the PT in the deck maintained its moment capacity, however inadequate, and effectively slowed the collapse to some extent. The canopy also provided some resistance.
So my takeaway is that this collapse took much longer than 429 milliseconds and even the experts can benefit from a review of their work.
I agree with Charlie's suggestion that an incorrect frame rate was likely used.
Thanks again,
RE: Miami Pedestrian Bridge, Part XIV
I still think this bridge got so much attention because of that dash cam footage being posted so soon after the collapse.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The times and the state of the bridge are from the NTSB report (pages 11,12) (sheets 30,31 of 152 in the pdf)
Link"Highway Accident Report
Pedestrian Bridge Collapse Over SW 8th Street
Miami, Florida
March 15, 2018" figures 9 and 11
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Member 12 ultimately hinged along the failure plane tracking the upper PT rod. The following image labelled "PHOTO 8: Truss 12, North view cracks" from NTSB's Bridge Factors Attachment 24 – Email from Mr. Rodrigo Isaza of MCM to Mr. Dwight Dempsey of FIGG dated March 12, 2018 is indicative of such failure.
I suspect this explanation will resonate with most.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
But - if the expert makes this mistake in front of a jury and is called out on it he loses credibility and likely his influence in the case.
Now SFCharlie tells me the time is from the NTSB Report? This just keeps getting better. Maybe someone should carefully review the NTSB report. Was the time stamp made by the camera taking the video or assigned during some viewing/editing process? At any rate (oops - no pun intended) the interpretation is easily misleading.
The math presented in the BLOG is correct as to differences in time presented by the NTSB and apologies become due to the BLOG.
I will trust that the author prepares in more detail before testimony than before blogging.
Thanks for the link, SFCharlie.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I just did a FBD with a rigid horizontal stick supported one end. Acceleration varies linearly from zero at one to max at the free end. I get an acceleration of 1.5g at the free end, 0.75g in the middle. The load at the support is 0.25wl. Hopefully I didn't make any mistakes.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
In reinforced concrete a blow-out is a loose term. Generally it means when a part of the reinforced concrete under a very stress suddenly fails the local concrete is crushed into small pieces and disintegrated after the collapse.
OSHA is an officially appointed and professionally qualified investigator in the FIU bridge collapse and the word blow-out has been used in the report text five times and in the description figures also five times. NTSB used the word blowout also four times in the text and one time in the figure description. Thus the word blow-out or blowout would be the opinion of an expert witness in court and one I would concur based on having worked all my life with reinforced conceret. Thus I am sure it isn't a fallacy.
Comparing your figure posted on 1 Jul 20 17:57 with OSHA Fig 64 below (or any of Fig 58 to 70) your ultimate failure plane is nowhere near to what had happened on the bridge.
The bottom of 12 failed because the weakest plane, where the stress is the highest when the cross ection is the smallest, is at the 8" PVC drain and not somehwere above it where Member 12 still has a full cross section. The OSHA Fig 58 to 70 inclusively show no concrete above the 8" drain after the collapse.
The elastic mudular ratio between concrete and PVC is about 15:1 so the 8" PVC pipe could take hardy any laod. If both deflect by the same amount the PVC takes only 1/16 of the load when both have the same area. However the overall 8.6" OD PVC drain caused a 41% reduction in the 21" thickness of Member 12. As the drain pipe situated at the middle so the reduced section is split into two 6.2" thick pieces on either side of the PVC drain. Do you still think the 21" thick concrete is easier to break than two 6.2" sections when under the same load?
Lastly I like to re-post NTSB's Fig 32 below as this is the official failure plane concluded by NTSB and it matches all the post collapse photos. Any attempt to re-write the history or the offical verdict should be supported with similar rigorous analysis and investigation. Merely a personal opinion on something else not backed by proof is not a contribution to our understanding of what has really happened.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
With reference to NTSB Fig 32
Along the South to North direction
The failure section has A-B-C and D-E-F in horizontall direction. A-B-C failed by shear but D-E-F was likely by bond failure as the none of the reinforcement (2x#11+8x#7 on East and then on West face) failed by shear. The vertical plane C-D failed by tension. In reinforced concrete design concrete is assumed no tensile resistance in design and a small amount in analysis.
Along the East to West direction (East being Fig 32 while West is the back side of 11/12)
The deck is physically attached to 11/12 via area C-D-E-H-C but the two 4" dia vertical pipe sleeves destroyed part of the bonding or shearing area. What was left has been indicated by the hatched area and there are two sides both of which failed by shear.
RE: Miami Pedestrian Bridge, Part XIV
Sounds interesting, but confusing. Any chance you can provide a plan view of the deck showing what you consider to be the vertical failure planes ? many thanks for your input.
RE: Miami Pedestrian Bridge, Part XIV
A plan view as requested
RE: Miami Pedestrian Bridge, Part XIV
Also a 3D cutout view (originally from NTSB Final Report Fig 16)
Please note area bounded by C-D-E-H is the East face of Member 12 bonding with the deck. It has an identical West face at the back of member 12.
The flaw of the design is that along the East/West direction the longitudinal tendon anchors, shown in purpose, prevent placement of rebar linking Member 12 with the either side of the deck. The two size 4 bars, shown green in BTSB 3D sketch, were the only reinforcement.
In the South/North direction it is also impossible to place large rebar to link Member 12 with the deck because the obstruction by the two PT rod anchor plates.
The devastating effect of the two 4" vertical sleeves, extending to the full depth of 4'-3.875" of the diaphragm, on either side of Member 12 should not be overlooked. Their presences and locations served as a partial isolation joint between the deck and Member 12.
The positions of the two PT rod anchors can also be significant when examining the NTSB Fig. 32. It could be seen while the re-tightening of the lower PT rod could progressively compress the deck against the 11/12. The similar re-tightening of the upper PT rod, on the other hand, could encourage the concrete to debond along interface D-E-F which at the thinest point is only 6.2" wide on either side of the 8" drain pipe.
RE: Miami Pedestrian Bridge, Part XIV
I do not see this failure as being significantly different had there been an intentional slip joint, perhaps in the form of teflon pads, at the surface of the deck with Members 11 and 12 sitting on it and no reinforcing passing thru the joint. There would not have been a vertical shear plane. There would have been failure due to a lack of resistance to the horizontal component of any axial load in Member 11, preventing the development of any axial load in Member 11 EDIT ADD and therefore preventing any vertical component to support the structure.
It would have happened long before transporting and likely during removal of falsework. Actual joint construction, reinforcing, and post tensioning simply prolonged the event until 1:46 PM, March 15, 2018.
RE: Miami Pedestrian Bridge, Part XIV
The same thing could be said of the upper PT rod until Member 11 and the joint to Member 12 began to split. Until that point both PT rods were adding shear more than clamping compression, and instead were contributing to the cracks in the deck around Node 11/12 and the pvc sleeves. After member 11 split and the joint began to disintegrate, the failure was underway.
It could seem that the EOR found advantage in the low angle of Member 11 and sought to restrain the failure evident in the deck using the horizontal component of that added/restored PT force. It could maybe have worked if the upper end of Member 11 were fixed to some immovable object, but instead Node 10/11 just reversed the force and pushed back on Node 11/12.
I have yet to distinguish in my mind between whether the splitting of Member 11 happened before or after or during the shear failure of the deck block beneath Members 11 and 12 and between the 4" vertical sleeves and above the 8" drain sleeve.
Thank you for your discussions.
RE: Miami Pedestrian Bridge, Part XIV
A trace of the crack in Member 12 from just above the lower slab rebar at the north face of 12 to just below the upper slab rebar at the north face of the deck reveals this possibility.
Edit: To clarify, Member 12 had to allow Member 11 room to move north. The shear plane in 12 was the weakness that was exploited but once enough northward movement had occurred, Member 11 failed just above the nodal block to start the cascade. The falling deck rotated the diaphragm off of the base of 12 while 11 hammered into the node. I believe that this sequence allows for the deformity in the upper PT rod in Member 11 to occur while the lower PT rod kinks at the slab.
RE: Miami Pedestrian Bridge, Part XIV
The above postulation does not appear to be supported by the collaspe photo shown below. It is clear that after collapse the end of 12 was resting on the top of the North pier. Had 12 been allowed 11 to move north by shearing off as claimed then 11 had be further north of 12 but it ended up below and on the south side of the pier.
The second weakness of the postulation of 12 shearing off is that the shearing plane can only take place when 11 was moving but 12 did not. This is impossible because during the collapse a hinge was seen at 10/11 connection with the canopy. Thus the triangle formed by 11, 12 and the canopy was initially rotating as one entity and there was an absence of force available to shear off 12 within itself. Remember once in motion the bridge was a mechanism.
RE: Miami Pedestrian Bridge, Part XIV
This can be confusing as I was initially thought it too. But I now believe the stressing inside 11 does not increase the horizontal shear in the system.
The easiest way to explain it is to imagine the 12 is prestressed similarly by a PT rod. While the compressive stress inside 12 is indeed increased the reaction will not be increased and the north pier would not feel anything. Thus by similar argument there should have no increase in the horizontal shear in the 11/12 joint by the PT rod re-stressing simlpy because 11 was inclined at 31 degree.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The force from internal PT in Member 12 which you describe would be perpendicular to the deck surface and therefore have no horizontal component. Member 11 is 58 degrees from perpendicular and has a serious horizontal component which must be resolved at the surface of the deck.
Of course the north pier would not feel anything - the reaction of the structure does not increase because the PT forces were internal to the truss and anchored in the deck which is a part of the truss. The PT forces were present in the truss while the truss was transported and erected in place. The pier is not a part of the truss.
l
RE: Miami Pedestrian Bridge, Part XIV
How about imagining just 12 on its own but with an arm sticking out at 31 degree. You can stressed this arm with PT rods as much as you want and it would not affect 12.
Another way is to imagine if you have a flat equilateral triangle on the ground each side is like Member 11. By post-tensioning one side internally with PT rod you will not get the remaining two sides stressed to the same level. The post-tensioned side will shorten axially in responding to the PT rod stress but the other two arms will simply bend slightly inward to accommodate the exial shortening of the first side. So the internal post-tensioning is not additive to the summation of forces at a nodal point in the equilibrium calculation. That would be my interpretation.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
FIGG couldn't Cast the lower PT rod any further into Member 12 as it would interfere with the 8" drain pipe. FIGG also can't change the drain pipe position as the drain connects to two spans and datum sensitive for gravity discharge.
On hind sight one should have fought the architect, who most probably would say the new arrangement looks ugly, and route the drain sideway, not penetrating into the diaphragm at all but attached to its external face and do the same for the short span. A few extra meters of PVC drians readily discharge to the river down below would have bought the FIU bridge a new lease of life by extending the low PT rod fully into Member 12.
RE: Miami Pedestrian Bridge, Part XIV
If the arm does not bear on the support below, the same problem exists at the face of the column. In this case the sliding force is vertical. On March 15 the sliding force from the PT was horizontal.
Here is a Member 12 with an arm and prestressing. If the acute angle between the arm and Member 12 is "A" it is my opinion the shear at the dotted "shear Plane" on the side of M12 is Clamp Force (PT) * cosine A.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The force of the lower PT rod was acting against the deck not against member 11.
The force exerted by the lower PT rod was trying to open the crack rather than pull it together.
The concrete had already sheered and shifted.
Only the re-bar was holding the joint together.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
I was responding to " imagining just 12 on its own but with an arm sticking out at 31 degree. You can stressed this arm with PT rods as much as you want and it would not affect 12."
My concern is there seems to be a thought that the PT force does not have anything to do with shear at the top of the deck.
Hopefully I am just misunderstanding the points being made.
Thank you for your comment. I will hand it off to you for further comments.
RE: Miami Pedestrian Bridge, Part XIV
Once the crack had opened up, the concrete had failed and the re-bar had started to deform.
Why did the crack stop there and not progress further?
The lower PT rod was acting as a restraint.
It had some freedom of movement inside the sleeve.
When the PT bar was tight against the bottom of the sleeve, the movement ceased.
The PT bar was acting as a restraint.
As the PT rod was tightened further, the force against the bottom of the sleeve in member 11 increased.
The concrete had already fractured and the rebar had deformed and was supplying minimum restraint.
At this point the structure was held together by the lower PT rod by reason of the downward pressure against the sleeve and the lower part of member 11.
I suggest that the first part of the final failure was the PT rod ripping out of the bottom of member 11.
So, the construction joint 11 fails and the 11/12 joint shifts until it is restrained by the lower PT rod and the compromised re-bars.
Then the tension on the lower PT is increased.
The lower PT rips out of the bottom of member 11.
No longer restrained by the lower PT rod, the 11/12 joint blows out away from the deck.
The damage to the ends of members 11 and 12 is subsequent to the failure of the bottom of member 11 and was a result of the failure of the bottom of member 11, not a cause of the failure.
I have not seen any mention of the restraining action of the lower PT rod once the concrete joint had failed.
Forgive me if I have missed something.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Regarding the shear plane in 12, it is not an epic saber slice from the heavens. It is the expression of the tensile stresses built up from the bending deformation and was to be expected but was never identified. There are many vids of beam shear failure on the net and its easy to see the amount of abuse a beam will take (include deflection) without an epic complete failure. Hence, I wager that 11 lost its ability to support its compressive load first.
In essence, the failure is a complex arrangement of simple, well understood failure mechanisms with a wicked feedback loop.
3DDave, I will gave you a star because I like the diagram.
I can"t compete with Vances artistic abilities. I swear if I drew mouse ears on one of my sketches, some people would never get over it, even if they know the bridge design was mickey mouse.
RE: Miami Pedestrian Bridge, Part XIV
I suppose you can create shear at the joint as your 6 Jul 20 01:42 post depicts.
I am think alone the line more like below.
RE: Miami Pedestrian Bridge, Part XIV
The bridge was still standing but with worrying cracks described by the workmen "crack like hell". At this point the two PT rods in 11/12 have been de-stressed as per design.
11/12 was holding and could possibly for able to do so for weeks and not days. I support this statement by pointing out the shift of 11/12 was still relatively small according to the crack measurements at that time. The rebar across the shearing plane, as one shown by NTSB Fig 32 based on the failed bridge evidence, has possibly yielded at a few locations but not broken or snapped.
Personally I think the 11/12 was held in position by the vertical reinforcement inside Member 12 as it is quite substantial with 2x#11 and 8x#7 which if you like were acting as dowels. It is noteworthy to point out none of these vertical reabr has failed in the end. They were just stripped of the concrete an clear indication of bond failure.
In my own opinion the re-stressing of the PT rods was the the last straw that broke the camel's back. First by attempting to pull the cracked 11/12 joint together the restressing woul grind smooth the shearing surface, reverse the bearing concrete stress from back to the front of the rebar, asymmetrically pull the 11/12 shearing face with the deck as only one PT rod was stressed at a time and lastly the upper PT rod could literally pull open the north part of the shearing face due to the eccentricity.
I am highly critical of the proximity of the two 4" vertical flexible sleeves on either side of Member 12 as they are ideal instruments for crack inducements. The substantial verical rebar inside Memeber 12 have the thinest concrete cover next to the vertical sleeves which are almost certainly the initiation location for a blowout. The bond between Member 12 vertical rebar and concrete was forcibly reversed by destressing/restressing at the two points of thinnest cover is a bomb waiting to go off. The bond between concrete and steel must be totally rigid if two were to have same strain so destressing/restressing movements are simply cannot be tolerated. Once the steel and concrete each has its own deflection the bond is gone!
Therefore it is possible a bond failure local to the 2 No. of 4" flexible on either side of Memeber 12 increased the flexibility of the 11/12 hinge with the deck sufficiently to initiate a blowout. The record shows the bridge collapsed "during" the last operation of restressing the bottom PT rod after the upper PT rod had been fully re-stressed.
RE: Miami Pedestrian Bridge, Part XIV
At that point all that was holding the joint together was the rebar.
Given the relative movement of the joint, the rebar must have been compromised.
Why did the joint not fail completely?
After moving over 1/2 inch, why did the movement stop?
The lower PT bar was restraining further movement.
The lower PT bar would have been forced against the bottom of the sleeve.
The lower PT bar was not tight in the sleeve and some movement relative to the sleeve was possible.
The lower PT bar did not act as a restraint until it had taken up all possible movement within the sleeve.
I submit that the initiating blowout was the failure of the bottom of member 11.
When the bottom of member 11 blew out downwards due to the increased force against the restraint of the lower PT bar the 11/12 node was relatively free to move away from the deck.
The rebar had been unable to prevent the original failure or separation and was no compromised.
Without the restraint of the lower PT bar, the rebar provided little restraint as the failure progressed.
Consider:
1. The lower PT bar never failed.
2. The lower PT bar was firmly anchored in the deck below the plane of separation.
3. The PT bar remained anchored in the deck.
4. The 11/12 node could not move away from the deck as long as the lower PT rod was in place.
The first blow out must have been the failure of the bottom part of member 11 as the PT rod started to rip out.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
You may not be familiar with the design. The two PT rods are what we normally call "temporary work". It is there temporary to assist the constrcution and could be removed when the bridge is in service.
The bridge in service will have Member 11 permanently in high compression so it makes no sense to stress the PT rods there. However when the bridge was moved from the casting yard to the piers it could only do so by supporting the two "next" inner bays during the transportation so that the two end bays can be launched onto the piers. In this arrangement the end bay is a cantilever and Member 11 will be in tension. For this reason alone FIGG had to stressed the Member 11 for the purpose of transferring the structure from the cast yard to its final position. Naturally once in the final position the PT rods could be de-dtressed as happened on site.
My point is the two PT rods were never a permanent design and can be ignored in the strength assessment of the bridge in performing its structural duties in service.
Also the PT rods are straight bars of 1.75" diameter and they would not have been forced against the bottom of the sleeve before the collapse.
The 11/12 joint at that time, in the permant position with PT rod stress removed, had probably shifted by 1/2". Such deflection would not necessarily cause a failure. The rebar could be bent or even yielded at some locations with some local concrete crushing confined only to the area around the shearing plane that has shifted.
In the above OSHA Fig 61 there are 2x1.375" plus 8x0.875" vertical reinforcementcast inside Member 12 now exposed between the two D1 tendon anchors. It is my belief that these 10 steel reinforcement were acting as dowels to hold 11/12 in position prior to the collapse.
In engineering we learn from mistakes. One of the most valuable lessons of the FIU bridge is that there was not a single failure from the above 10 vertical steel bars when Member 12 sheared across them completely. There is no better illustraion to show the FIGG's design deficiency in not able to make these bars to do what they were supposed to.
I do not have the dimension of the tube casing for the PT rod but my guess it would be around 4" so leaving at least 1" clearance all round the PT rod. In my experience it is highly probable when the concrete sheared by as much as 1" across the duct the Member 11 would have failed or broken already.
The 11/12 finally moved away from the deck. The lower PT rod anchor was still in its designed position with the deck. The upper PT rod was still inside Member 11. Member 11 was ripped open by pulling the lower PT rod against its bottom face where the concrete cover is at its thinnest. You can image between a 1.75" diameter high strength PT rod and a layer of say 3" concrete which one break first.
RE: Miami Pedestrian Bridge, Part XIV
You have obviously misunderstood my post.
When the joint failed, why did the 11/12 node move just one inch and then stop?
The tension was relieved from the lower PT rod.
The only function now provided by the lower PT rod was that of a pin, preventing further movement, until the tension was re-applied, generating enough force on the bottom part of member 11 to destroy the bottom part of member 11 and probably cause collateral damage to the upper part of member 11.
Please explain how the 11/12 node could move more than one inch without either breaking, pulling loose from the deck or breaking out of member 11.
The upper PT rod was completely contained within member 11 and played no part in the failure.
The lower PT rod had issues.
It was anchored at one end at the top of member 11.
It was anchored at the other end in the deck.
It crossed the plane of failure.
Tension in the lower PT rod would cause opposing forces between member 11 and the deck in the direction of the failure.
When the joint moved, the lower PT rod was forced against the bottom of the sleeve.
How could it not be so?
The rebars failed to remain embedded in the concrete, while the PT anchor did remain embedded.
Sounds like a failure of the reinforcing design to me.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
I suggest you have a read of WJE's sketches enclosed in FIGG report to see how the 11/12 developed the cracks and why it could remain in place until the day of collapse.
I suggest you take note of the reinfrcement, drawn to scale, along the failure surface.
The only thing you need to watch out in WJE's work, as it was used to fend FIGG, is the assumed cracked line marked in yellow. That we can agree or disagree. The rest is as per documented photos so should be credible.
RE: Miami Pedestrian Bridge, Part XIV
Thank you for the considerable time that you have expended relying to me.
Allow me to retract an ill advised sentence in my previous post.
Consider the following possible sequence.
The crack originated in the fab yard, either during or after the tensioning of the lower PT rod.
The joint was broken but substantially held in place by the rebars.
When the bridge was placed the crack opened up approximately 1 inch.
With one inch displacement through the lap joint of the rebars the integrity of the rebars was substantially lost.
Further movement was restrained by the lower PT rod acting as a pin.
I take issue with your estimate of the sleeves as 4 inches in diameter.
I cannot find a spec, but one picture seems to show the sleeve at about 150% of the rod diameter.
The sleeve may have floated upwards against the bottom of the PT rod in the wet concrete.
If the rebar lap joint could not prevent 1 inch of movement it could not have halted further movement.
It would have broken its bond with the concrete during the first movement.
When the crack opened it relieved the tension on the lower PT rod.
When the lower PT rod was retensioned, it forced the joint apart.
As the PT rod was acting as a restraint at that time, that restraint had to be relieved by the bottom of member 11 breaking out.
As far as the fall ripping the lower PT rod out, during the first part of the fall the angle between member 11 and the deck is diminishing, rather than increasing.
This would not have ripped the PT rod out of member 11.
The bottom of member 11 had to relieve the PT rod for the movement of the 11/12 joint to increase beyond the previous 1 inch.
1. Original failure in the fab yard, with movement restrained by the rebars.
2. Second failure when the crack opened up about 1 inch and destroyed the bond and integrity of the rebar lap joints.
3. Final failure when reapplied tension on the lower PT rod simultaneously broke out the bottom of member 11 and pushed out the 11/12 node.
Full length rebars would provide considerable restraint even after a 1 inch relative movement.
Similar movement on the lap joint would act to break the bond of the bars to the concrete and destroy the greater part of their effectiveness.
I believe that you are putting too much faith on the rebar lap joint and are not at all considering the action of the PT bar as a pin.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
The joint wasn't broken. It had some cracks. Every structure of this size and complexity will have cracks.
The bridge was placed on piers on 10 Mar. PT rod tensions in 11 was removed within a few hours on the same day. Photos were taken on 12 and 14 Mar. Earlier photos show smaller cracks. Only on 14 Mar the crack was measured 1" on the outside but the interior was about 1/2". I urge you not to treat the PT rod as a structural element beccause within 11 it has no structural duty after destressing
This is pure speculation. Do you have proof of such bad workmanship? Such accusation is very dangerous if unfounded.
You obviously lack the basic knowledge of reinforced concrete design. We are talking about a rebar perpendicular to a shear plane here. The bar has to be designed with a development length, approximatly 45 times its diameter, below and above the shearing face in order for the steel stress fully developed. A mear 0.5" lateral deflection of the bar inside a locally crushed concrete is not a big deal because rest of the bar can hold the structure if the situation deterioates no more. We are talking say about one diameter high of the steel and crushed concrete shifted by 0.5" but the rest of the length of 89 times the diameter is still soundly gripped by concrete. Here I urge you not to mention the PT rod because the 0.5" shift was the result of destressing. The 11/12 could have nearly negligible or not-measurable cracks prior to the destressing but nobody knows because the stress was removed from 11 within hours it was placed on pier.
That is pure speculation again and suggests FIGG didn't know about the bridge more than you. It is obvious to everyone that FIGG was tightening the PT rod to close the cracks and not to force the joint apart. I believe nobody knows whether the cracks were closed up or pulled further apart as the result of the restressing. We only know from OSHA report "They had re-tensioned the upper bar to the desired tension of 280 kips and were at the lower bar at their last cycle to complete 280 kips when the incident occurred."
Can i ask you to read my post on 19 Jun 20 12:14 in which I drew two CAD sketches to explain how the lower PT rod was ripped out?
For (1) Please understand that you cannot use the word "failure" here. As an engineer you should be prepared being on on a stand in the court of law when giving out such opinion. I have said it before contracturally no one could reject MCM's work at the casting yard. You can complain and MCM would just ask a labourer to brush-paint the crack areas with a cement slurry. You can inspect it later and wouldn't find anything. I am not suggesting it is OK for MCM to cheat but the cracks were just one grade above trivial because such cracks are fact of life in the industry especially if the work is stressed in one part and not the other.
For (2) There is no second failure. The 0.5" crack was recorded one day before the collapse. No more photos on it was taken. Like I said previously the bar has 45xdiameter above and below the shearing plane. Your destroyed bond can only about 1 to 2 diameter at the crack interface.
For (3) If you look at any of the OSHA photo on the lower PT rod you should find none of them show broke out the bottom of 11 but attched firmly to the deck. Also whenever bars were provided they were in fully length. The problem here is FIGG cannot insert them at the right places due to congestion. Please be advised suggesting the PT rod useful as a pin is irrelevant. Even if both PT rods could act as pins they were useless against the collapse because none of them broke.
RE: Miami Pedestrian Bridge, Part XIV
If we remove the parts of M12 beyond the projection of the Arm thru M12, your point becomes clear. I have attempted to show this in Fig 1.
But what happens if there is a severely sloping construction joint somewhere between the two PT anchors?
Or an identifiable plane which could simulate a joint. Perhaps this is a problem with concrete as a material and not something that can be applied universally to all materials.
Were M12 and the Arm cast while laying on their side and and monolithically, then forms stripped and allowed to cure and dry, it would likely crack at the interface with M12 due to shrinkage and drying stresses – concrete always seems to crack at reentrant corners.
Were the Arm cast alone and in one piece and then PT added, I see no reason for a diagonal crack to form so there is not a defined sloping plane for failure. Joining another and different section of concrete may create an opportunity for cracking and may define a plane for consideration. Casting M12 at a different time than casting the Arm clearly creates a joint and a defined plane.
So IF, and it is an “if”, the Arm develops a defined sloping plane, the plane must transfer a component which creates shear at the plane. I tried to show this in Fig 2.
And I tried to illustrate my concern for not having significant axial load across a sloping joint in a compression member using Fig 3.
No one would think of allowing a joint as shown in Fig 3.
Plus – if anyone had seen cracking in a pier at a sloping joint and that in anyway looked like the cracking seen on the deck at Node 11/12 they would have known it was coming down and soon. To see a 1'9” X 2 ft column (same size as M11) supporting one end of a 174 foot 950 ton concrete Albatruss (spelling intended) should have alerted someone. And M11 had much more load – about 1500 kips axial.
As I recall, the ACI code allowed or addressed Shear-Friction design where (paraphrasing here and not complete) different materials interface, where construction joints are used, and where a shear plane can be defined. I doubt that they ever envisioned a condition like M12 with a PT'd Arm.
OK, DDDDave – (note – my decoder ring is working again) now there are three sketches to admire. Better watch your six, Industrial Light and Magic.
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
12 merely has to bow sufficiently for 11 to fail.
At the same time that the weight of the bridge is
pushingmoving out with 11, the slab is weighing down and pulling the diaphragm in the opposite direction. Neither force vector passes through the connection at the bottom of the diaphragm.As waross suggests, the lower PT rod is likely the snag that prevented the bridge from meeting an earlier demise, an otherwise indeterminent structure bent on collapse.
The latest diagram that I posted, (and reposted by 3DDave) shows a movement by 11 of 1 inch, resulting in a rotation of 1.3 degrees. For ease of effort, the slab is held constant, and other fine detail of relative movements and deformations were omitted.
The point being that the movement is subtle but the damage to 11 at this point is already severe while the damage to 12 is not. It begs credulity that 12 would suddenly become the critical member.
Beyond this, at some point we just have to agree to disagree.
P.S. The various tears in the deck and spalls on the diaphragm are collateral damage and as such are distractions since these components are not critical elements.
RE: Miami Pedestrian Bridge, Part XIV
Thanks for your illustration. The sliding joint, as per 11/12 joint, will have shear across the CJ.
Can I have your thought on the action of 11 stressing and its structural duty? Both create comression inside the member and they are additive. I believe We all agree on that.
Would I be correct to say in prestressing Member 11 the 11/12 joint deflects to the South or towards the inner span?
When the bridge was droped on the piers by equilibrium the vertical compenent in Member 11 axial compression (plus self weight of Member 11) would be balanced by the vertical reaction from the pier while the horizontal comonent balanced by the tension in the deck. Member 11 had to act as almost like an arch but the 11/12 joint stoped it from kicking out so its deflection is to the North or away from the span.
Can Member 11 under two compressive cases deflect in opposite direction as I suggested above?
Also in the case of prestressing Member 11 do you expect the deck in compression, tension or no stress?
RE: Miami Pedestrian Bridge, Part XIV
Gibbs Rule #51: Sometimes You're Wrong.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
OSHA, NTSB and FIGG all offered reports on the FIU bridge collapse. The FIGG enclosed a report by WJE, a factual report by Turner Fiarbank Highway Resrach Centre and the NTSB Material Laboratory Study Report.
You can get a good idea how each describes the failure mechanism.
Like I said earlier WJE report was used to defend FIGG but the sketches, with the exception marked yellow lines stated as estimated cracks, were the crack mappings verifiable by the photos. WJE also show, via Exhibit 2.5.2 to 2.5.4 the broken out sections of 11/12 after the collpase. These are useful observed evidence, which are verifiable. to help our discussions here.
I would also point out the failure surfaces/planes between NTSB and WJE are substantially the same. In WJE case failure line between C-D-E is a striaght line instead of two sides of a right-angle triangle shown below.
I have intervened frequently because many discussions were not related to what had happen in the field.
RE: Miami Pedestrian Bridge, Part XIV
After both of you insisted on that the PT rods could have acted as "pins" or "snags" I take another look at the PT rods and rebars in Member 12.
The two PT rods are 1.75" diameter enclosed inside plastic ducts which I estimated to be either 3" or 4". By comparing with the exposed 4" verical sleeves in the phoros the duct is more likely to be 4" overall but it has ribs making the inside diameter smaller. In any case the point is there is free movement inside the duct for which I previously discounted its pining effect.
The vertical reinforcement inside Member 12 that pass through the CJ are 2x#11 (11/8" diameter) and 8x#7 (7/8" diameter). The combined steel area of these reinforcment is 1.6 times more than the 2 PT rod. These reinforcing bars were cast tight inside the concrete so would have to be in play immediately when 11/12 commenced shearing horizontally relative to the deck.
I don't know how much the PT rod play in resisting shear but it has a much yield strength of 120ksi against the rebar's 60 ksi so probaly a corresponding higher shear strength. The only problem is to realize the pin effect the 11/12 must deflect to take up the free slack isnide the duct.
Since the two PT rods, just like all the vertical rebar inside 12, did not sever so there exists the possibility their shearing capacity could have helped to restrain 11/12 joint from failure at least initially.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
upmostutmost respect. Second, it is my observation that WJE didn't include all the voids (conduits, etc.) that were in member 11. I think they decided what to look for and then created a test to find that (and nothing else). ...just my opinion, more based on my experience with human nature rather than structural engineering.SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
No. 1 is the condition before the collpase. No. 2 is the commencement of the collapse.
[Apology: I posted the unannotated sketches by mistake. The Editor does not permit me to change or replace the sketches so please read them in the order they appear]
Since the bridge became a "V" shape it had to pull the two extreme ends inward. Thus allowing the diaphragm to move over the edge of the pier as shown by No. 3 & 4.
The diagragm is 18'-2" long for the first 2'-0" width. Thereafter the length drops to 1'-9", which is the thickness of Member 12, for the remaining 10.5" width. Based on the post collapse evidence it is likely that the deck fell to the ground once it had clear the pier edge. The caught last 10.5" width was split and broken up as indicated by No 5 & 6. sketches.
OSHA Fig 62 shows the sepration of the 1'-9" by 10.5" section managed to remove part of the surface layer of the diaphragm exposing some of the horizontal rebar at the north face.
(by the way if you wonder what is the steel bar at the bottom of the diaphragm under the right D1 my guess is it could be a holding down bolt trapped inside the 4" vertical sleeve)
My interpretation may not the actual event but it is based on photographic evidence. If the part of Member 12 did split as suggested above the concrete would pulverize at the bottom anchor of the upper PT rod due a sudden to release of the high energy stored in the rod. The remain of Member 12 can be seen from the photo I posted in 5 Jul 20 11:52 post. Detail description of its interface plus off-site photos are also available in Exhibit B TFHRC Factual Report "Concrete Interface Under Member 11 and 12" of the FIGG Report.
RE: Miami Pedestrian Bridge, Part XIV
The secondary hinge locations as seen on the video are as expected for a shear friction failure of #11 (or any other failure that would relieve load on #11).
RE: Miami Pedestrian Bridge, Part XIV
There are several pre-existing design arrangements which weaken the connectivity of area CDEH. Amount them are :-
If you look at the area CDEH of NTSB Fig 32, available in 7 Jul 20 16:24 post, you will find the 4" vertical sleeves have taken up more than 50% of the available surface. The imposition of the sleeves displaces the concrete making locally insufficient amount to grip the reinforcement. The thin concrete layers between the sleeves and the rebar could break easily and trigger the bond failure of the whole bar.
The area around the vertical sleeves is congested with reinforcement too making even less concrete to bond the reinforcement. You can see from OSHA Fig, 70 for yourself.
The stress direction inside 11/12 is significantly different from the deck. The deck is uniformly post-tensioned by tendons both longitudinally and trasversely except the plan area of 11/12. Once the deck was post-tensioned the south portion of 11/12 could be influenced by the D1 tendons on both side of Member 12 but the rear of 11/12 was not stressed. Then when the PT rod stresses were applied the strain direction was about 31 degree to the horizontal. Thus area CDEH is the interface of two highly stressed zones each pulling it own direction. This explains why the concrete could pulverize and able to leave the flexible vertical sleeves almost undamaged. The deck section after collapse is also solid around the prestressing tendons zones because the stress is homogeneous there.
Due to the presence of deck's longitudinal tendon anchers, label D1 to D6, on either side of 11/12 it was impossible to place decent size reinforcing bars in the south to north direction through area CDEH to connect Member 12 with the deck.
Finally from the failure suface/plane established by NTSB and WJE it should be obvious that the lower PT rod was able to anchor into the deck and could be difficult to overtighten. The upper PT rod on the other hand seems to pull the 21" thick 11/12 joint mainly and with little participation from the deck. This could be a recipe of disaster because the rod stressing can also inadvertantly exert stress and help to break the CDEH connectivity with the deck.
RE: Miami Pedestrian Bridge, Part XIV
Your questions evoke issues requiring some thought. Thank you for asking my opinion.
Can I have your thought on the action of 11 stressing and its structural duty? Both create comression inside the member and they are additive. I believe We all agree on that.
Member 11 is highly loaded and in my opinion seriously under reinforced. Adding PT to support the cantilever condition under transport was a good idea. It provided the tension force for support of the cantilever plus kept the Member 11 in compression to prevent cracking. Under full span support conditions, more compression was not a good idea. The south end had sufficient capacity to tolerate the additional PT force without damage. The north end did not. As I recall, the added PT load was less than the design Live Load , and the failure may have created a loading during construction that was very indicative of performance under even more perilous circumstances.
While on the subject of transport conditions, Member 10 is also under a stress reversed condition during transport. Under full span Member 10 is a tension member with tension loads supported by PT rods. Under transport conditions Member 10 is a compression member with the added benefit of PT forces adding compression. As detailed on the construction drawings I think the compression reinforcing is less than the code prescribed minimum.
Would I be correct to say in prestressing Member 11 the 11/12 joint deflects to the South or towards the inner span?
“Deflects” is probably not the best word here – it may not deflect until something fails, and given the size of the deck I doubt the elastic shortening there was significant. The final load on any element with opposing loads will be the result of the resolution of vectors. Prestressing in Member 11 will attempt to move Node 11/12 to the south as long as the joint at the top of the deck is intact because the horizontal component of the PT force is to the south at Node 11/12. Initially both PT rods were anchored in the deck. When the joint at the deck surface failed I see Member 11 and the portion of Node 11/12 above the deck surface being allowed to slide north because of the overwhelming load from truss action. So in effect, the deck will remain in place because of its mass and section properties while the base of M11 at the deck surface wants to go north – both tendencies in response to the major forces in the respective members while the truss remaind intact. When Node 11/12 fails, about 1500 kips of PT in the deck is released (no longer loaded by Member 11), and some elastic shortening will develop in the deck. This will initiate movement of the north end of the deck, but I see this as being very small compared to the dimensional change as Node 9/10 falls.
When the bridge was droped on the piers by equilibrium the vertical compenent in Member 11 axial compression (plus self weight of Member 11) would be balanced by the vertical reaction from the pier while the horizontal comonent balanced by the tension in the deck. Member 11 had to act as almost like an arch but the 11/12 joint stoped it from kicking out so its deflection is to the North or away from the span.
I find that to be a good description of conditions under full span. Member 11 carried an axial load about 50% greater than the end reaction of the entire structure. Member 11 was pushing North at loads large enough to fail itself. When cable news aired this on the afternoon of March 15 and I could see it was a truss I suspected immediately that they had lost a heel joint. That became much more certain in the months after.
Can Member 11 under two compressive cases deflect in opposite direction as I suggested above?
Again the use of the term “deflect” causes uncertainty in my mind. If we focus on elastic shortening or elongation (because it is an axially loaded member) Member 11 was under tension during transport and under compression when placed on the pier. If the concern is that the PT rods placed Member in compression and by being anchored in the bottom of the deck added a horizontal component of force directed to the south, while the structure load in Member 11 attempted to force Node 11/12 northward, it is my opinion that the effect of the PT forces in Member 11 served only to create compressive stress in Member 11 and sliding loads across construction joints. The net effect on the truss was zero because the rods were anchored in the respective ends of Member 11 and had equal and opposing force components. This is like the equilateral triagle you previously postulated – in the case of pinned joints in the triangle, the PT forces change the dimension of one leg, and the angle opposite the PT changes, but the other members are not otherwise affected. While the PT forces in Member 11 were in place and the truss was on its bearing at the pylon, the compression stress was greater and some shortening was experienced for that period. In a true truss that would not cause a lot of issues providing capacities of members and joints were adequate, but in the case of a truss with some continuity/fixity in the joints, there can be resulting secondary stresses and potential damage. I view these as being of lesser significance compared to the disastrous performance of Member 11 and Node 11/12. They no doubt contributed, however.
Your mileage may vary. I appreciate the discussion.
RE: Miami Pedestrian Bridge, Part XIV
In sketch 5 the deck and diaphragm have slid south until the 2' wide sections of the diaphragm can just begin to fall. The 10.5" extension of Member 12 remains over the pylon. Member 12 and Member 11 are shown intact and in their original relationship to the deck.
At the point shown in sketch 5, Node 11/12 has slid 2 feet from its original location on the deck and has likely taken the 'blow out block' with it. The bottom of that block is defined by the top of the 8" sleeve, and the projection of the deck below the pipe sleeve was easily broken off the deck. But I think the important thing is Members 11 and 12 were severely damaged by their movement across the deck and the angle of Member 11 to the deck should have decreased as Node 10/11 dropped while the end of the deck had not yet cleared the pylon.
So I am of the opinion that Members 11 and 12 were damaged in their lower sections before the deck projection below the pipe sleeve was broken off.
Also the angle of the deck at the instant depicted in sketch 5 is likely a bit flatter than shown, because Node 9/10 is about 40 feet from the end of the structure, and the fall distance is roughly 18 feet. So the top of the deck at impact of Node 9/10 on the street should be less than 30 degrees below level.
Thank you,
RE: Miami Pedestrian Bridge, Part XIV
I must admit that my schetches 5 & 6 have not been corroborated with the estimated collpase trajectory worked out by others.
I also do not have information on the order of which part of 11/12 broke off first before the others.
The purpose of my sketches was to show during the diaphragm sliding off the pylon the falling dead weight could help to tear off the rear 10.5" of Member 12 from the diaphragm's body.
In agreement with you it is entirely probable that NTSB reported blowout, to the north of Member 12, took place at the level of the 8" horizontal drain pipe, due to high concentration of stresses, and so above this drain pipe level there was no concrete left to be split from the rear 10.5" of Member 12. Nevertheless the splitting of the rear 10.5" of Member 12, commencing from the bottom upward, would be able to rip out the Member 12 north face vertical reinforcement cast in the first lift of the concrete pour.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
My guess is the shearing was probably trying the direction you were suggesting but the progress might have been impeded when the shearing crack hit 7S03 & 11S03 bars. Therefater the shear changed to splitting.
On the possible extra damage to the pylon and the rear of the diaphragm my explaination is as follow:-
On the pylon we have no information of damage. Secondly the bearing area of the pylon has been designed to take half of everything the bridge got so it will not shear off a corner if that is what you expected. Beneath the bearing there should be heavily reinforced with additional anti-burst reinforcement similar to the end of the post-tension anchor.
OSHA Fig 61 & 62 show a triangular layer section of the north face of diaphragm peeling off to expose the reinforcement inside. The reason only a limit section of the surface layer came off with Member 12 is due to the proximity effect. The splitting force came from the 1'-9" wide Member 12 and the OSHA 61 below shows the influence extending about 2 to 3 times the Member 12 width, about the bottom of anchor D3/D4, on either side at the bottom gradully reducing to 1 x width at the top. This is the same agrument like when considering the second moment of area of this bridge in resisting load one cannot take the full 31'-8" width of the deck but only a short section on either side of the web as the effective width for the bottom flange. Different codes allow different effective lengths but between 2 to 3 times the web width seems to be borne out by the evidence of this bridge.
The peeling off commenced from the bottom and would have travelled upward at an angle about 45 degree. It was abruptly stop near the tendon anchor D1 because the surface layer there was in high comression resisting the splitting.
RE: Miami Pedestrian Bridge, Part XIV
Background sketches courtesy of saikee119 (Structural) . No copyright violation intended.
DDDDave - this is the closest thing to tracing I can get. Sorry I can't meet your standards.
A decoder ring may be needed to correlate my numbering with that of Saikee - my numbers are one less than the numbering on his sequence of sketches.
3DDave - it is the author's intent that the background sketches are detailed enough to provide sufficient relevancy to the subject of this forum.
The next 5 sketches show what I think is the probable failure sequence. Please consider the sketches as sections cut thru the center of M11 and M12 so the internal voids can be illustrated.
W01 is basically depicting my idea of conditions while re-tensioning the PT rods in Member 11. The Node 11/12 had slipped about a half inch before retensioning began. The lower PT rod is anchored in the deck, the upper PT rod is anchored in the block which is moving with the bottom of M11 and M12 and which is being pushed out of the deck at the north end. The different anchorage conditions cause cracking in M11.
Sketch W02. The angle change in the deck, M11, and M12 is shown greater than I think is correct for a sliding distance of maybe 6 inches by the deck. At 6" slide I find the angle to be about 16 degrees. Internal voids increase and cracking increases as Node 11/12 pushes farther out the end of the deck.
Sketch W03. Member 11 is just about to drop into the void left by the blowout of the block in the deck. Vertical load from M12 will likely break the end of M11, angles are changing quickly as Node 10/11 drops.
Sketch W04. Diaohragm just clears the edge of the pylon. The blow out block above the 8" pipe sleeve has cleared the end of the deck and is falling onto the top of the pylon. Member 11 is breaking up as it bends over the corner of the deck. The 10.5" projection of the deck under M12 and below the 8" sleeve is breaking off the deck.
Sketch W05. The Deck is falling beside the pylon while the bridge pancakes and Member 11 folds against the deck. The lower ends of M12 and M11 skid across the top of the pylon and stay there. The canopy dives onto the deck as the deck hits the roadway.
OOPS! Pay no attention to that screw in the upper corner - that is not the screw you were looking for.
Th - Th - Th - Thats all, Folks!!
Thank you,
RE: Miami Pedestrian Bridge, Part XIV
Totally wrong.
There are two triangles involved.
Triangle one is formed by member 11, member 12, and the canopy.
Triangle two is formed by member 11, member 10, and the deck.
When the collapse starts, the base of the second triangle starts to elongate.
Your sketch doesn't show this.
As the structure starts to fall, member 11 is pushed further out, hinging at the canopy.
Member 11 will continue to push out until the top of the canopy is at the level of the top of the foundation.
At that point, a little over 10% of member 11s length will be pushed out across the top of the foundation.
But don't forget the lower PT rod.
This is anchored in the deck.
As the collapse starts, the lower PT rod must break its way out of member 11.
There is no tension left on the rod but member 11 is moving north, as the structure falls the deck with the end of the PT rod is being pulled south.
In the first few inches the lower PT rod must break out of member 11.
As the structure falls the deck pivots at the lower end of member 10.
As the structure falls the deck is angled between the pivot point and the top of the foundation.
It doesn't take much fall of the structure for the deck to be pulled off of the foundation.
Member 11 is going north, the deck is going south.
This drawing is wrong.
The canopy and member 11 are shown too short.
At this stage of collapse geometry says that the 11,12 node will be pushed out past the north side of the foundation.
The deck is shown too long.
At this stage of collapse geometry says that it will have been pulled off of the foundation and be either sliding down the face of the foundation or have been pulled back enough to fall free.
I can do better than this but it will take a lot of time to first go back and find the bridge dimensions and then to set up the bridge as three pivoting triangles and show the relative positions as the structure falls.
It's grade ten geometry, but that doesn't mean that it won't take a lot of time.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I used 134 feet from sta 0 to Node 9/10 but can change that in a sec.
Max O/O length of deck EDIT ADD measured from bottom of diaphragms and lower outside corners is at 4 ft drop of Node 9/10. That is the point where Node 9/10 passes thru a line between the lower corners of the diaphragms.
I assumed no crushing of concrete at Node 9/10 - the compression block is only about 2 inches deep.
Comments welcome.
RE: Miami Pedestrian Bridge, Part XIV
The canopy is shorter from top of M11 to top of M12 than the deck from bottom of M10 to bottom of M12.
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
I cannot be sure. The frame rate is 0.2 seconds per frame. I can say canopy-11-10 falls farther, sooner than deck, 10,9.
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
What affects frame rate in dash cams? Scan speed? Record/transmit speed?
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Someday, when I have the time, I would like to read this thread in it's entirety. Thus far, I have only spent ~5 hours and most of that is just catching up on the past posts, while not fully comprehending the information that is in them or working through it in my head. My only request to the moderators is if there was a way to preserve all the embedded pictures within the posts for future learning, that would be great. In some of the old threads, the embedded pictures are unavailable, but maybe that has went away now?
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
So help me here - -
waross (Electrical)7 Jul 20 14:15
Gibbs Rule #39: There is No Such Thing as Coincidence.
Gibbs Rule #51: Sometimes You're Wrong.
Does Gibbs' Rule #51 apply to Gibbs' Rule #39?
(Love Gibbs Rules).
RE: Miami Pedestrian Bridge, Part XIV
Let's say before the collapse the full bridge has a second moment of area of 7824 ft4 and the centroid 6.756 ft from the bottom as computed by approximation using coordiate geometry.
One the 11/12 connection failed the web would be unable to hold member forces in the canopy in balance with those in the deck. The bridge was then supported by the deck only. The second moment of area and centroid would change to 18.69 ft4 and 1.3 ft respectively.
From fundamental principle of stress = (Momentxdistance to extreme fibre)/(second moment of area) the stress in the deck-only case is about 80 times of the full deck. This huge stress increases is reslistic estimate if the postensioning was intended to cause the deck in full compression when the bridge is in ist final position
Therefore once the 11/12 connection has gone the deck would be hugely overstressed and formed a hinge at 9/10/deck. The hinge at 10/11/canopy was never a driver in the collapse.
RE: Miami Pedestrian Bridge, Part XIV
We did spent a lot of time looking into what has happened.
Apart from formal education, on-site experience we can also learn from mistakes. Luckily for all of us the mistake is someone's else.
We have a wide range of disciplines in here and so far everyone is trying to accommodate each other's view and we all learn together.
There is an immense amount of record available. The project presentation is cunning. the design is unconventional. The construction sequence is extremely interesting. The photographic records are mind-boggling. The failure is intriguing and the manner of collapse is sublime to anyone who wish to learn. If that isn't enough the FOT reviewing engineer was able to mark up the drawings the failure risks of this bridge years before they happened.
OSHA, WJE, NTSB and FIGG reports were each prepared to serve a certain purpose and they were constrained by the insurance people. What we are doing here is for the academic interest of getting really into the very bottom.
As far as I know this forum had discovered the root cause long before any of the official reports came out.
RE: Miami Pedestrian Bridge, Part XIV
Could you point me to this information please? Sounds quite interesting!
Your post as a whole was spot on! Failures are unfortunately a great learning opportunity. Especially when they are on the edge or beyond what is considered “normal” design. As I said before, I haven’t spent as much time on this one, not for lack of interest, but more to time and the unlikelihood that I will ever design a bridge. The Hard Rock, Salesforce Transit Center, Millennium Tower, and Opal Tower issues are all more relevant to my day to day so I’ve spent significantly more time there.
RE: Miami Pedestrian Bridge, Part XIV
According to FDOT, the review performed on this project by the FDOT SDO—
was consistent with reviews performed on all projects; it consisted of a high-level
review only. We did not perform calculations or review EOR calculations
RE: Miami Pedestrian Bridge, Part XIV
Getting close.
A big part of the time will be to find the post with the dimensions of the bridge on a slow internet connection.
What I would look for is:
Distance between the piers.
Overall length of the deck.
Horizontal setback of the point at which the canopy hinges from the end of the deck.
The length of member 11 from the canopy "hinge" to the extreme north end.
Assuming that the deck and canopy hinge is centered on the PT bars, the height of the canopy PT bars above the deck PT bars (center to center).
I have read speculation that the rebars across the plane of failure were fully embedded in the concrete.
I have read speculation that the proximity of the 4" sleeves severely compromised the ability of the concrete to maintain a bond to the rebars.
(Was that the same poster?)
The 1/2 inch crack should have been measured horizontally.
That was the direction of displacement.
Say about 3/4 Inches.
Despite speculation to the contrary, once the 11/12 node had moved 3/4" horizontally, the rebar was now loose in fractured concrete.
The lower PT rod was all that was left holding it together.
At this point I speculate that the PT rod was crushing the corrugations in the sleeve.
High school physics: Flotation: The PT rods were rigid at the time of the concrete pour. Buoyancy in the wet concrete would have lifted the sleeves against the bottom of the PT rods.
Now, as the tension on the lower PT rod was increased, the PT rod commenced to crush its way out of member 11 in a horizontal direction.
What else?
The 11/12 node was moving north and the deck was moving south.
The PT rod was crossing the plane of separation and had to be crushing the bottom of member 11 horizontally.
As the movement continued, the top end of the PT bars would be extending out of the top of the blister.
This horizontal crushing continued until the deck cleared the foundation and started to fall.
At that point the the PT bars would be again pulled into the top of member 11
Once the slack in the PT bars was taken up, the horizontal crushing became a mostly vertical ripping.
There has been speculation that the PT sleeves were 4" in diameter.
There are some pictures of the rods and the sleeves prior to the concrete pour.
The sleeves appear to be about 150% of the PT diameter or 2.5" to 2.625".
This is moot however because buoyancy will have lifted the sleeves up into contact with the bottom of the PT rods.
The other thing that will take time is doing some auto-cad drawings of the various components as the structure fell.
My cad skills were never very good and I don't use it many times in a decade.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
The Interactive: The Path to the FIU Bridge disaster set up be NBC has recorded some basic information by FDOT Engineer Thomas Andres.
I believe FIU also have some records. There were some marked up drawings originally but later converted to typed text and replaced by computer CAD sketches.
Here are just two of the original mark-up drawings by FDOT engineer.
FDOT engineer was doing a high level review. The cracks were marked on areas whererever uneven stress areas were apparent. They were based on years of experience on postensioned concrete. As the bridge wasn't owned by FDOT so the peer review was given to a appointed party. Nevertheless FDOT offered a brief overview which proved highly relevant.
RE: Miami Pedestrian Bridge, Part XIV
A set of drawings in PDF here:
https://cdn2.fdot.gov/fiu/13-Denney-Pate-signed-an...
Dimensions are on Drawing B37.
The changing dimensions during fall are not real sensitive to exact location of Node 9/10.
If you check the spreadsheet the "top of deck" dimensions are measured along the deck surface.
At this point I am hesitant to advance an opinion as to just where the canopy hinged. At the north end of the blister? Intersection of PT rods? Hard to tell. Easy to change in spreadsheet. By the way, to check my spreadsheet, do the math on one drop point. The same formulas are used to find the output in each column.
Flotation - a 3" sleeve displaces 7.3 pounds of concrete per foot. A 1.75" steel rod weighs 9.17 pounds per foot.
This horizontal crushing of Member 11 ? continued until the deck cleared the foundation
It is my thought that at some point the remains of Node 11/12 have departed the deck and are simply being pushed wherever, and that may have happened before the deck fell off the pylon. I attempted to convey that idea in my sketch W04. When Node 11/12 clears the deck and has no connection to the deck depends mostly on dimensions and damage.
For the most part, we are tracking together pretty well.
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
It is not crazy because it is a concern and is in most cases the responsibility of the PT contractor. The PT is usually considered a design/construct sub who is responsible for doing it right. The contractor in this case has an excellent reputation. I have worked with their southern CA people.
The compressive stress under the anchor plate is quite high - as I recall something like 70% of specified concrete strength. To compare, working stresses (real) under the previous codes limited bending compression to 45% of specified concrete strength.
We would need access to shop drawings submitted for the PT to check the stresses.
RE: Miami Pedestrian Bridge, Part XIV
We should discount the fear of the PT rod overcompressing the concrete.
We know from the contract drawing the PT rod inside member 11 is 1.75" diameter, PT rod tension is 280kips, anchor plate size 12"x8" and the specified concrete strength is 6000psi.
The cross section of Member 11 is 24"x21".
If the entire 280kips bears on the concrete immediately behind the 12"x8" anchor plate the compressive stress is 2917psi. If the two 280kips PT rod tensions bear on the full cross section of Member 11 the average compressive strength is only 1111 psi.
ACI design codes, say 318, permits only 0.85x specified strength to be used in design in conjunction with other considerations. Thus below a stress of approximately 0.85x6000 = 5100 psi is a safe design.
If the concrete is about to fail the actual concrete compressive stress is of course allowed to reach to the specified strength but there is fat in the system that the actual strength is invariably higher than the specified strength. When NTSB cut cores from the collapsed bridge to test the concrete strength in a laboratory the lowest actual strength was 8,580psi while the remaining four samples registered strength all above 10,000psi.
Thus I don't think there is much mileage in proving the concrete could be overstressed by the PT rods in compression. To me the concrete in trouble is in the area outside the influence of the PT rods with not enough compression.
RE: Miami Pedestrian Bridge, Part XIV
That solves that. Thank you for your detailed post and data coverage.
I do see one thing on which I will comment - as I recall viewing photos of the PT rod anchor plates which had anchored the PT in Member 11 they appear square to me - not rectangular.
EDIT ADD: I think we should look for a specific allowable compressive stress under an anchor plate at the time of tensioning. The general usage of O.85f'c is for factored loads. Under PT installation the load is real and temporary until it relaxes or anchors set, and some increase is permitted but I am not sure it reaches 0.85f'c.
Had a reference but just lost power for a few minutes so will return in a bit. Hopefully with a reference.
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
Many photos, like OSHA Fig 64, 65 & 67, show the PT rod anchor enembedded exposing only one ful edge. Hence measuring the two sides is not possible and I agree it does appear to be square in shape. I attached OSHA Fig 64 for example.
The best photo I could come up with for checking the PT rod anchor is from NTSB "Materials Laboratory Factual Report (Report No. 18-082) depicted above.
In its lower section of Fig 15 enclosed above you can save the image, magnify it and measure the horizontal and vertical edge. When I did that I got a aspect ratio of 1.5 so the anchor is definitely rectangular to me. The specified dimension of it is 12" by 8" for 1.75" diameter PT rod used in Member 11.
RE: Miami Pedestrian Bridge, Part XIV
In my experience the 0.85f'c used in ACI code is to encompass a safety factor for the concrete as a material. When you do ultimate limit state design the ultimate tensile strain is 0.003 at collpase. You also have a strength reduction factor 0.9 making the net usable strength in concrete 0.9x0.85 = 0.765f'c for a ACI compliant design.
The Euro code ultimate tensile strain in concrete is 0.0035. The ultimate maximum concrete stress is equal to the specified concrete cube strength fcu divided by the material safety factor which is 1.5 for concrete. So the corresponding net usable ultimate concrete stress is 0.6fcu.
However concrete strength crushed by a cube is higher than that crushed by a cylinder. The universal conversion factor is f'c = 0.8fcu. Therefore EURO or Bristish designer would effectively use 0.6/0.8 = 0.75f'c which is close to the ACI code's 0.765f'c.
What you permitted in the design, by lowering f'c to 0.85f'c and then further reduced with a strength reduction factor, is just good engineering practice adopted universally but in slightly different formulae for different countries.
In the field the specified 6,000psi strength concrete actually has the insitu strength at least 8.580psi verified by the core samples. The acutal collapse analysis should based on the actual strength and actual stress.
RE: Miami Pedestrian Bridge, Part XIV
saikee's surface is indicated in chevrons and as I've explained before, I give it zero strength to hold 12 in the slab socket.
12 bows north under load from the horizontal component of 11, held in place at the top by the canopy and at the bottom by the diaphragm. The slab carries the downward component of 11 and passes the load around 12 to the diaphragm. Interestingly, when I rotated the upper PT rod to follow 12, I noticed that it would have to increase in length. This can't happen unless, say, the tension is released in the rod, a plausible explanation for the "cracked all to ..." upon detensioning.
I speculated earlier that the lower PT rod was a snag that prevented the structure from fully collapsing however, upon closer inspection of the PT rod duct spec and allowing for the 32 degree inclination, that allows over two inches of freedom for the horizontal movement. I now tend to believe that the structure held together with the few rebar threaded through 12 and the slab, as well as the rebar in the nodal block.
The strain from the retensioning eventually overcame the last vestige of connectivity allowing enough extra horizontal movement to cripple 11 which likely failed just above the nodal block (given all of the visible damage before the retensioning). As 11 pancaked and hammered into the nodal area, the primary rotation came from the slab which started its downward descent. Interestingly, the lower bound of the vacated socket area becomes a tension break. I believe until this time, 12 was able to absorb the strain.
Edit: Eventually 12 skips off the north end but that part is rather anticlimactic. Edit 2: I redrew the PT rod anchor plates to 8" in profile and relocated that lower PT rod closer to its as built condition. The orange line represents what I believe is the 45 degree bending shear plane in 12. It appears early in the gif but I got tired of editing.
RE: Miami Pedestrian Bridge, Part XIV
Your animation starts to illustrate the point that I have been trying to make.
There are some adjustments that you may consider.
Your animation shows the lower PT rod kinking. There is no photographic evidence of a kink.
It would instead have been breaking out of the lower part of member 11 in the area to the right of where the kink is shown.
You show the 11/12 node pivoting at the bottom. On reconsideration, you may agree that the pivot point was the canopy above member 10.
The 11/12 node would be rotating CW, not CCW and there would be separation between the deck and the 11/12 node.
The animation shows rotation. In fact there would have been little rotation initially but there would have been horizontal separation.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
You presentation with the changing static images is novel so is your postulation. The idea that Member 12 was pushed out, hinged somehow at the bottom and split at the deck level with Member 11 sounds exquisite and not without merit. The holding down bolt on either side of Member 12 could have provided the rotation point have indicated with the pink circle.
However there are some weakness in the postulaion of which among them are:-
(a) The separation of Member 11 from 12 at deck level, as confirmed by you couldn’t happen unless the tension of the PT rod is released. Therefore the photos available on 15 Mar, prior to re-tensioning, should show signs of the separation. FIGG has submitted seven photos dated 15 Mar to NTSB and I enclosed two of them here. The bridge was re-stressed from midday of 15 Mar and then collapsed.
The is no sign of any crack showing a separation of Member 11 from 12 on the west face.
On the east face a small crack is visible but it seems to trace back to the PT rods which have caused rather alarming surface cracking on both east and west faces of Member 11.
(b) If there has been a separation crack of Member 11 from 12 at the deck level then we can expect the Member 12 joint with the canopy to be pushed outwards and suffered some permanent damages. The actual joint, between the canopy and Member 12, appears remarkably intact after the collapse and remains substantially at 90 degree when I measured it for any permanent deformation.
(c) The ability of Member 12, which is only 1’-9” thick, could cause a rigid body rotation of the 18’ long diaphragm is stretching the imagination a bit, bearing in mind in the postulation Member 12 would have already partially separated from the deck and Member 11. I attach the end elevation of the diaphragm to show its relative size to the Member 12.
(d) If the evidence in the field is inadequate to support your postulation after the 11/12 has been de-stressed and the bridge was resting between piers then the subsequent re-stressing would make any separation crack between Member 12 with 11 even more difficult to occur because the upper PT rod would instantly clamp the two together. It was stated in NTSB report that the upper PT rod was first fully re-stressed, the 280 kips re-stress of the lower PT rod was just completed and the bridge fell.
I think the actual failure mechanism could remain a mystery for some time to come.
RE: Miami Pedestrian Bridge, Part XIV
Triangle #1. Member 11, member 12 and the canopy.
Triangle #2. The deck, member 11 and member 10.
Triangle #1 pivots at the member 11/canopy joint and slides across the foundation to the north.
Triangle #2 pivts mainly on the foundation but triangle #2 is distorting. The base is elongating and is the sum of the last section of the deck and the gap created as the 11/12 node moves north. This continues until the base falls free of the foundation.
The length of member 11 is approximately 30 feet.
The horizontal component component of member 11 is approximately 26 feet.
As the bridge falls the 11/12node will move approximately 4 feet north until member 11 is close to horizontal.
To do so, the lower PT rod must be breaking its way out of the bottom of member 11.
By the way, the lower PT rod is anchored in the deck which moves very little.
The lower PT rod will be extending out of the top blister until the deck falls free.
Once the deck falls free, the slack in the lower PT rod will be taken up and then continue to break out of the bottom of member 11.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Member 11 pushed the 11/12 node about 4 feet north.
When the bottom of member 12 cleared the foundation, it would have dropped until the bottom of member 11 contacted the foundation.
At this point member 11 would have been already severely damaged by the lower PT rod.
I can't find an exact dimension for the height of the deck above the foundation. I estimate from 2 to 3 feet.
That drop would be enough to finish the damage to member 11.
The lower PT rod as a pin.
Much has been made of the clearance between the sleeve and the PT rod.
The position has been taken that there was too much clearance for the PT rod to act as a pin.
Back to high school science.
Buoyancy.
The bigger you estimate the diameter of the sleeve, the more buoyancy it will have in the wet concrete to float up against the bottom of the PT rod.
It is possible that as the joint started to fail the first 1/2 inch or so, the PT rod had enough clearance in the sleeve to both crush a little of the concrete and to curve upwards in the sleeve.
That 1/2 inch gap would have relieved the tension on the PT rod.
When the rod was retensioned, that would create a force on the top of member 11 to push it northward and may have added a further crushing force to the concrete as the tension tended to straighten any curve in the rod.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
The above show that the diaphragm dropped to the ground while the other end was resting on precast concrete barriers.
Barrier to ASTM C825 seems to have 32" height so your height estimate is spot on.
NTSB material laboratory factual report lower section of Fig 14 shows the end of PT rod with a sleeve. My measurement is the internal diameter of the sleeve is under 3" making its overall diameter, including the ribs, about 3". You can download the image, enlarge it and scale it yourself.
RE: Miami Pedestrian Bridge, Part XIV
So top of 8" pipe sleeve was a little more than 2 feet above the top of the pylon.
RE: Miami Pedestrian Bridge, Part XIV
When the 11/12 node went off the back of the pier it would have dropped 48.5 inches until the bottom of member 11 contacted the top of the pier.
Note, the 11/12 node went off the back of the pier, not the front as has been suggested in several drawings.
It would have moved about 4 feet north and the lower PT rod would have broken away 4 feet of the bottom of member 11.
Following that, the continued fall of the structure would have pulled the 11/12 node back across the top of the pier, explaining the damage to the bottom of member 12.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
MIAMI BRIDGE FAILURE – PART 3: THE PEER REVIEW
Why did gross errors in the bridge’s design go unidentified, despite the design being subject to peer review by an independent engineering firm.
"If this were a movie you’d say it was unrealistic, you’d say engineers would never behave so nonchalantly in the face of significant structural cracking."
RE: Miami Pedestrian Bridge, Part XIV
https://www.bradyheywood.com.au/miami-bridge-failu... part 2
RE: Miami Pedestrian Bridge, Part XIV
The foundation or pier is 6 feet wide, not 4 feet wide.
Although the 11/12 node was pushed northward over 4 feet, it did not drop off the back side of the pier.
This picture is taken at the moment that member 11 is substantially horizontal and the 11/12 node is at its farthest travel northward.
At the time that this was taken the deck has fallen about the height of the canopy.
As a result, the distance between the south end of the deck and the north end of the deck is less than the sum of the two portions of the now broken deck.
This will increase the separation of the plane of fracture.
The lower PT rod is anchored in the deck and the 11/12 node has now moved over 4 feet 9 inches north of the end of the deck.
At the moment that this picture was taken the lower PT rod has already crushed its way out of about 5 feet of the bottom of member 11.
Members 11, 12 and the canopy will have continued to rotate until member 11 contacted the top south corner of the north pier.
The damage to members 11 and 12
is consistent with that contact.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Thus in Louis Berger review the 11/12 would be bolted tight with the short span which can conveniently used as a restraint to stop 11/12 any idea of moving to the north. If 11/12 has serious cracks previously FIGG/MCM has to made good to it and the bridge would not failed afterwards.
However the bridge without the short span is also a valid load condition and so without its inclusion the certification of the bridge adequacy is not complete.
Therefore the peer review contract between FIGG and Louis Berger although legal, does not materially deliver a true verdict on the adequacy of the FIU bridge in substance.
RE: Miami Pedestrian Bridge, Part XIV
This suggestion has been dismissed.
I suggest that this is a reaction to not considering this possibility in the first place.
Assumptions have been made to dismiss this suggestion.
On the other hand is evidence and probability.
Consider the sequence of the failure of the construction joint:
Such a failure is most often progressive.
The first displacement weakens the joint and leads to further failure.
When the failure does not progress the two most common reasons are that the displacement caused by the failure has lessened the forces across the plane of failure or some other factor or object has acted as a mechanical blockage.
The first cracking did not compromise the rebar but did lessen the force of the PT rod, hence the failure stopped with visible cracking when the PT force was relieved. At this point the rebar was holding the joint. together.
The second displacement of the plane of failure was 1/2 to 3/4 inches. Why did this stop separating?
The geometry was such that the force due to the weight of the structure was not decreasing.
The tension of the PT rod was removed with the first fraction of an inch of displacement.
If the rebar was unable to prevent the displacement it is unlikely that the rebar would be able to stop the movement abruptly.
If the rebar was full length it may have had a restraining effect but this was a lap joint.
A rule of thumb is that a rebar embedded to 40 times its diameter will break before being pulled out.
The rebar did not break.
The most reasonable explanation is that the loose pin formed by the lower PT bar became tight and stopped the movement.
When the rebar was retensioned, the pin failed by way of the destruction of the lower part of member 11.
Do not discount the buoyancy of the sleeves. The larger that you assume the sleeves to discount my suggestion, the more buoyancy they will have to support my suggestion.
Then gravity.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Apparently it also didn't include analysis of the "nodes" or joints, only the main structural elements ( deck, canopy and struts ).
Unbelievable.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
In a real world you can always try to engage somebody to do a peer review of a Rolls Royce standard by a watertight specification. For just $61,000 the offer would still be a Toyota Yaris and the offer would be written in into the contract the exact scope of work and every deliverable.
To do a reasonable peer review you need a PE, attendance to formal meeting half a dozen times, months of work by a couple of junior engineers to do number crunching, modelling and calculations, report writing and expenses to go with the job. That is just one iteration assuming no change is needed in the design.
Every drawing for construction in this project, which forms the input to any peer review, has four signatures of
(1) Prepared by - possible by a technician/draftsman/CAD operator
(2) checked by - detail check against calculation by a junior/assistant engineer not yet qualified.
(3) Designed by - checked by the designer himself to ensure his idea correctly implemented
(4) Approved by - signed by senior PE who owns the project, selected the scheme and created the initial general arrangement.
Had the design been properly executed the in-house peer review should have picked up any anomaly too.
RE: Miami Pedestrian Bridge, Part XIV
The whole tensioning / de tensioning of member 11 was an after thought and when they laid the end on the pier and took the transport away, the compressive load was very high from dead load plus the tensioned member 11. Sure it only apparently lasted an few hours before they de tensioned the rods, but that was still a high load going into inadequate re-inforcement.
Then of course re-tensioning it ( mainly the lower bar) was almost certainly what broke the thing as the additional load forced member 11 off the deck along the crack / failure plane. Once one or two bars snapped or lost their ability to hold member 11 then the rest went in a cascade.
Any sort of overview of the design only looking at the final layout wouldn't pick up any issues with that node because it would seem clear that any forces would be balanced by opposite ones from the second span.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
I haven't seen anything about the design yet that would support the back span being capable of properly supporting that node. Would you butt something against the end of a steel truss to stop the welds on a diagonal from ripping off the bottom stringer?
RE: Miami Pedestrian Bridge, Part XIV
The base of M11 and M12 may not have fallen 4 feet - at least in an abrupt manner. There is considerable material missing from the end of the deck which was initially directly below M11 and M12 - principally in the zone between the top of the deck surface and to the top of the 8" pipe sleeve, which basically defined the bottom of the "blow out block".
This would not ivalidate your interpretation of the failure but only lessen the drop at that step where M11 and M12 were no longer atop the deck.
RE: Miami Pedestrian Bridge, Part XIV
This is Canopy PT C1 and C4 noted to be "MAIN SPAN BACK SPAN CANOPY and 270+ feet long on drawing B-69.
I would have achieved that part differently but there are more ways than one to skin a cat. The cat does not appreciate any of them.
RE: Miami Pedestrian Bridge, Part XIV
I don't believe it was designed to work that way, should have been expected to work that way or would have properly worked that way. I believe the comments about the rest of the structure stopping the node from coming apart once it was built would have led to yet another blunder in the design and construction if the structure had survived long enough to get that far.
RE: Miami Pedestrian Bridge, Part XIV
Actually I did mean to say that but I was in error and posted a retraction.
The total displacement of the 11/12 node was about 4'9". The top of the pier was about 6 feet.
The 11/12 node never left the top of the pier.
The damage to the 11/12node was most likely done when member 11 contacted the top south corner of the pier as everything continued falling.
I can't accept the repeated sketches of the 11/12 node rotating off of the south side of the pier.
In the initial collapse that node was moving north, not south.
If the 11/12 node was damaged then by what act of God was member 12 lifted up into its final position on top of the pier.
Thank you for your comments LittleInch.
I suggest that the postulations that ignore the movement to the north of the 11/12 node, and which ignore the PT bar completely are more simplistic.
I don't suggest that the PT bar prevented movement.
I suggest that as the rebars were progressively failing, The PT bar arrested further movement after the original crack of 1/2" to 3/4".
How could member 11 move north in relation to the deck without the Pt bar ripping out.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
As a side note - I just placed a 30/60 triangle on my screen with the photo you posted - the angle between the Canopy and Member 11 is -30 degrees - if the angle of M11 to the canopy changed early in the collapse it went back to almost original angle.
RE: Miami Pedestrian Bridge, Part XIV
The entire triangle pivoted at the break in the canopy as the 11/12 node went west.
Yes, by the plane of fracture I mean where the 11.12 node left the deck behind on the journey north.
Member 11 would have contacted the south top corner of the north pier or the top of the deck as the structure continued to fall.
The bottom of member 11 would have been damaged already by the PT rod.
The contact with the deck and/or the pier is the most likely cause of the damage to both members 11 and 12.
The impact may have fractured the connection between the canopy and member 11.
Either it is still in position or it has become hinged at the canopy and has fallen back to close to the original angle.
Referring to your spread sheet, when the lower end of member 10 has fallen 4 feet, the north end of the deck has moved 0.26 feet north (a little more than 3 inches).
Vance, will you be so kind as to add a column to your spreadsheet showing the northward travel of the 11/12 node?
Thank you.
It will be interesting to see if you can calculate the interference between member 11 and the corner of the deck.
The point of contact will be almost 4 feet back from the end of member 11 and will have lots of mechanical advantage to do the damage to 11 and 12.
Thanks in advance.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
The calc considers rotation about the bottom corner of the south diaphragm and may fudge a bit because it projects drop at 10/11 as a ratio of horizontal distances relative to the drop at 9/10. I do not think that causes a variation that can be disproved by dash cam evidence.
It seems the base of M12 at the top of the deck is forced about 6 feet north before being pulled back.
If there is a need, I can change input lengths easily.
EDIT OOPS!! Column N is final horizontal distance from south corner of Diaphragm 1 to the point on M12 where the top of the deck and the end of the deck coincide. That dimension was used as the distance to Node 11/12. To find the over all length add the 10.5" that M12 extends beyond the end of the deck. The heading on that column incorrectly notes :deck". The deck has literally "gone south".
RE: Miami Pedestrian Bridge, Part XIV
Drawing B-37 has dimensions of concrete at Node 11/12. Overall 6-4 1/2. The fillet is left behind - about 13" gone there. I am going to deduct the 10.5" projection of M11. That leaves about 4'-4" of construction joint (without the 10.5").
From the spreadsheet the deck is ready to depart the pylon when 9/10 has dropped about 16 feet. At that point the bottom of Node 11/12 has moved north about 6 feet, the separation is about 8 feet. The point where Node 11/12 joint clears the end of the M11 projection (Put the 10.5" back) is about 5'-2". That coincides with a drop of 9 feet at Node 9/10, where the deck likely 'folded'. That assumes the deck extension of 10.5" for M12 is still attached to the deck. So if I did it right M11 clears the deck while the deck is still on the pylon.
I think the deck area under M11 and M12 was sheared free and went north with M11 and M12. And that left a void for M11 to fall into, beginning where the "blowout" started. With M11 at 31 degrees, the 24" dimension becomes about 4 feet measured horizontally, and half the member is 2 feet. So if the break out developed at the mid line of M11 the 5'-6" slide required to clear the deck is reduced by 2' and becomes 3'-6" slide required to fall into the void in the deck. That corresponds to a drop of about 5 feet at Node 9/10 on the deck surface.
I expect there will be questions.
RE: Miami Pedestrian Bridge, Part XIV
Am I reading your spread sheet correctly?
Does the 11/12 node move far enough north to drop off the north end of the pier?
Is it possible that there were two drops, one onto the top of the deck, and shortly after a second drop onto the top of the pier as the deck falls away?
Two consecutive drops followed by being dragged back onto the pier after hooking over the end of the pier would explain the damage to the lower ends of member 11 and member 12.
In regards to the action of the lower PT rod.
Has this been explored before I brought it up?
I can't remember seeing it in previous posts.
I see the lower PT rod acting as more than a simple pin.
It was at about a thirty degree angle.
It may have been acting as a wedge and exerting considerable downward force on the lower part of member 11.
Given the angle, the downward force would have been greater than the horizontal force.
This would have provided considerable clamping force to increase the resistance to sliding of the fractured concrete.
There is always a reluctance to examine new suggestions when your mind is made up. (Speaking generally, not to you personally Vance. I feel the same reluctance myself at times.)
The PT rod did not fail either in tension or in shear.
There has been speculation that due to the diameter of the sleeve, the PT rod did not make any contribution to holding the joint together.
I suggest that there is no evidence that the PT rod was centered in the sleeve.
I suggest that the position of the PT rod in the sleeve can be estimated by the 1/2"to 3/4" opening of the original crack.
The rod was there.
The rod was strong enough to make a difference, both in the horizontal plane, acting as a pin in shear and in the vertical plane, increasing the clamping pressure.
It was there, it must be accounted for.
Well, maybe not. There are a lot of things that FIGG didn't consider.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I do not see two drops - it all began with Node 11/12 on and in contact with the surface of the deck.
Member 12 and the canopy it supports total about 50 kips. Member 11 is split and damaged in the last photo taken. It would seem that the weight of M12 would have to be supported by the lower face of M11 as it slid over the edge of the blowout zone. How much moment could M11 resist in the damaged lower section at Node 11/12? Post collapse photos show maybe 4 feet of the bottom end of M11 is gone. Answer - not enough,
apparently.
But - There could have been two drops - or a two step single drop. IF the bottom of the blowout block provided a surface for support - at the top of the 8" pipe sleeve. I have no good dimensions for the remaining surface on which the Node and blowout block could have been supported. Then there would be about a 24" drop to the top of the pylon as a second drop.
I suspect the bending caused by the lower face of M11 going over an edge coupled with the drop to the top of the pylon explains most of the damage to M11 during the collapse.
It may have been acting as a wedge and exerting considerable downward force on the lower part of member 11.
Early on, perhaps. But at some point it began ripping out the bottom. If it created a normal force because of the wedging it also created an opposite force against the deck surface from below and may have contributed to the cracking experienced as the blowout block failed. But as I recall the deck is not ruptured and remains in place just north of where the PT rod enters the deck.
I concur with your comments about the PT rod in the sleeve and the cracking in the deck. The possible contribution to failure or resistance/support provided is quite difficult to really determine. All told, there was apparently enough capacity at the deck surface to transmit a force sufficient to tear out the "blowout" block of the deck.
EDIT ADD A comment - the geometry and results are sensitive to the location of the break in the canopy and M11 at the top = was the hinge at the Node? Edge of blister? I cannot answer that.
RE: Miami Pedestrian Bridge, Part XIV
Did anyone report any cracking at Node 10/11? If I had a rattlesnake at my foot I would not be looking up either. In this case the rattlesnake would be the cracks in the deck.
We have so little if any information on the top of Member 11. The photo that I recently saw for the first time shows the lower end of M11, - I think.
The question arises - if Member 11 failed at the top how was it able to deliver enough load to the deck to cause the blowout?
As far as forces go, Member 11 pushes south at the top just as much as it pushes north at the bottom. But it is near the end of the deck at the bottom. The Nodal shear at 10/11 is greater because Member 10 is also pulling to the south at the same time and those components are additive. The canopy is only 12" thick but the blister is a reinforcing element to lower the stresses of the transfer of the force. BUT - there is a FIGG/MCM construction joint there also.
At this point Node 11/12 seems easier to explain and has more evidence to support it as the initial failure. But that is no reason to stop looking. Thanks, Charlie.
RE: Miami Pedestrian Bridge, Part XIV
I am going to think about this for awhile.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The blister is probably another instance of good concrete and a lousy construction joint.
The blister looks as if it parted company with the canopy and is probably not in the original position relative to the canopy.
We can't discount the action of the PT bars in member 10 that may have pushed the blister to the north.
For discussion rather than argument, the canopy may have broken in two places.
I am wondering about the length relative to the height of the pier.
Intuitively, the weakest spot and the spot with the most bending would be under the blister where the PT rods from members 10 and 11 cross.
This is also a corner of the triangle.
Breaking of the canopy away from the 10/11 joint would destroy the geometry of the triangle.
It is hard to imagine that the obvious break in the canopy is the original break, given that the canopy to member 12 joint is intact.
Please consider this sequence as a possibility.
1. The bridge starts to fall as we have discussed and the canopy hinges at the 10/11 node. That would tend to lift the blister off of the canopy, intact.
2. As the bridge falls, the lower ends of members 11 and 12 are destroyed.
3. When the broken end of the canopy hits the ground, the canopy breaks again, and also breaks member 11.
Looking at the last picture posted; The first break would be the south side of the section of canopy labeled 'CANOPY" and the second break would be the north end of the section labeled "CANOPY".
Part of member 11 would be broken and beneath the broken canopy.
Consider the length of the PT bar compared to the intact length of member 11.
That argues strongly for a section of member 11 to be broken and lying beneath the rubble of the canopy.
I find it difficult to accept the damage to the lower end of member 11 to crushing damage. This is a triangle and crushing of member 11 would change the geometry and change the angle of the canopy to member 12 joint.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Full frame, highest res, full length:
Link
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I have now looked at that several times and stepped through it several times.
It is not as clear as one would desire.
There is a utility pole in front of member 12 and a tree behind member 12.
Member 12 is being shaded by the canopy and is difficult to make out.
What at first looks like member 12 may be the unshaded utility pole.
Add to that the moving viewpoint.
There are several frames per second.
In the last frame in the 23 second interval, it is unclear to me which is the tree behind, which is the utility pole in front or which is member 12.
In the next frame, the 1st frame in the 24 second interval, it arrears that member 12 is still attached to the canopy at right angles.
Looking at the photograph of the canopy and member 12 in their final resting positions, it is hard to accept that gravity would allow them to remain in that position if the connection between the canopy and member 12 was broken.
Member 11 seems to be broken at both ends and does not seem to be providing any support.
I may be wrong.
Please take another close look at the video with consideration of the utility pole, the tree in the background, the movement of the camera and the shadows.
Thanks.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Yes! It is very hard to sort out all the pieces. I was able to get advice from the great gentlemen of this thread, to dump out the individual frames of this video. I used an old windows seven computer to enhance them. I drew lines around each member in each frame of the collapse and copied them to the next frame so I could detect motion and rotation. I believe you are right, that M11 broke at both ends. I also believe that M12 remained upright until it started to follow the canopy in falling south.
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I can't tell if M11 failed and shortened or how much it may have shortened. But if the triangle "canopy/M11/M12" was lost, for whatever reason, the location of the top of M12 is influenced by the deck rotation as Node 9/10 drops and by the rotation of the canopy as Node 10/11 drops.
Added column "Q" shows the eepected difference in position due to the mistracking of the geometry - in feet. That difference is accommodated by 1) strength of joints and M12 or 2) cracking in M12 or 3) failing of joint to canopy or deck or both.
RE: Miami Pedestrian Bridge, Part XIV
The canopy broke in several places but the PT rods did not.
As the canopy fell, the end to end distance shortened.
There is no way that member 12 could have remained vertical as the canopy fell.
As for the lower PT bar restraining the movement, Consider the amount of concrete that would have to be crushed for member 11 to fail in compression with the amount of concrete that would have to be crushed to relieve the restraint of the PT rod.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
The canopy broke in several places but the PT rods did not. I do not see evidence of the canopy breaking in several places until the deck hit the roadway and the collapse was basically complete.
As the canopy fell, the end to end distance shortened. I agree. But until Node 10/11 (or wherever the break in the canopy developed) fell thru a straight line from the bottom of the diaphragm 1 to the top of M12, it actually got a little bit longer. Then it began to shorten.
There is no way that member 12 could have remained vertical as the canopy fell. Agree.
As for the lower PT bar restraining the movement, Consider the amount of concrete that would have to be crushed for member 11 to fail in compression with the amount of concrete that would have to be crushed to relieve the restraint of the PT rod.
If I read this correctly, your point is the PT rod would have failed to resist the slide before a compression failure developed in M11. Am I correct?
The lower PT rod gave it up early as it tore from the bottom of M11. The upper PT rod went with the bottom of M11, lost all concrete around the anchor plate, and lays bare on the top of the pylon. So I see the lower PT rod as being the only one providing resistance. And as compared to the axial capacity of an undamaged M11 your point (as I read it) is correct.
As I view some videos it seems the canopy may have failed first - does anyone else see this? I welcome dissenting observations.
EDIT ADD Looking back to March 18 of 2018, the view from the south shows the unbroken length of the canopy as 4" on my monitor and 3.25" wide - with actual width being 16 feet the unbroken piece is about 20 feet long - about the distance to the north edge of the blister. The deck may have failed at the north face of the blister. Or my monitor is screwed up.
RE: Miami Pedestrian Bridge, Part XIV
I rotated the yellow outline to stay aligned with M11. Please note that it does not remain aligned with M12 or M10.
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I am going to suggest that had you chosen to release the joint between M11 and M10 and fixed the yellow outline of M10 to the image of M10 the yellow lines would have illustrated what happened to Member 11 more clearly.
By the third frame, as you see, the outline of Member 10 is shown trying to punch thru the deck.
The discussion of triangles should probably be expanded to include the canopy/M10/M9 triangle which I think was not damaged at the time the third image was captured. Outlines on M9 would illustrate any change in relationships by M9.
I am now thinking the canopy first failed at the north end of the blister. In the third frame, M11 was broken at Node 10/11 because Node 10/11 had dropped and Node 11/12 was still on top of the deck.
Is there any evidence that the canopy also failed at the south end of blister 10/11?
RE: Miami Pedestrian Bridge, Part XIV
If we consider the vertical distance of Node 10/11 above the deck, at the point where Node 9/10 has dropped one foot and Node 10/11 has dropped 1.12 feet, the point directly below Node 10/11 has dropped 24'/40' X the one foot drop at Node 9/10 or 0.6 feet. The vertical distance between Node 10/11 above the deck has shortened by 1.12'minus 0.6 feet or 0.62 feet. The 'pancake' of Member 11 has begun.
RE: Miami Pedestrian Bridge, Part XIV
I did look at a lot of pictures trying to answer than question and saw some suggestion that the first break was at the 10/11 joint.
With all the PT in the canopy, I doubt that they blister was strong enough to act as a fulcrum for a break.
The spot with the greatest force to strength ratio was the point at which the member 10 PT rods crossed the member 11 PT rods.
I may be wrong.
But, no matter where the canopy broke, member 11 would still be pushed to the north.
Revisiting another issue:
I have spent a lot of time scrolling through this and previous threads.
I can not see any photographs showing any damage to the canopy to member 12 joint.
I appreciate the work that you spent isolating frames but I find them inconclusive.
The view is obstructed by a power pole and by a manlift boom.
Member 12 is obscured by shadows and blends in with the tree in the background.
Inconclusive.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
At first mention I had that sinking feeling, oops, I missed something important.
Then I looked further.
Construct-ability.
It appears that the pin is shown passing through the deck into the pier.
Tough to do when the pier is on site and the deck is being cast in the fab yard.
The pin would have to pass through the drain pipe.
There is no photographic evidence that there was a pin through the drain pipe.
And it is not shown on this rebar detail.
Conclusion: That vertical pin did not exist.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Something went wrong here?
(photo)
Miami Pedestrian Bridge, Part IV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Drawing B-23 shows the vert PT rods as 1-3/8" dia, plate on bottom, 4 feet into pylon, with a coupler at the surface of the pylon.
There are 2 vert PT rods in the pylon, each 1'-1" from center of structure. That is 2+1/2" from the face of M12. So one of the sleeves on each side was there to access the coupling nut and install the rods post-erection. Note 4 of Stage 3 notes calls for the
installation andstressing of the PT rods after grouting below the diaphragm.I wonder if the PT tensioning equipment will fit that close to M12.
Previously, regarding damage to the canopy at M12, there is cracking and chipping of concrete below the surface of the deck at M12. I first thought there was no damage also. There is at least 2 feet of translation discontinuity of Member 12 - so bending, shears, and moments are created. Clearly the damage is far greater at the deck end of M12, but the top to deck is not undamaged. Whether that damage happened at the beginning of the collapse or near the end, is another matter and difficult to determine. EDIT ADD Sorry - did not intend to jump onto this - I had not seen SFCharlie's post of the picture when I sent this. Maybe the comments will have some value.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Any help suggesting a better presentation will be appreciated!
I also ran into difficulties due to the dashcam "dollying". I need some sort of 3D model, but I don't know how to even start...
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Nice work.
The slides suggest that the first break in the canopy may have been at the north end of the blister.
Suggestive but inconclusive.
If the canopy first broke at the north end of the blister it is likely that the upper end of member 11 also broke.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
After looking at the images I have a comment. Or two.
As I study Frame 3 I think the top edge of M11 is a place to focus. Even though the crane is in the way, we can see the top edge of M11 that is visible will project to intersect the bottom of the canopy some distance - maybe 5 feet - north of where M10 intersects the canopy. Drawing B-37 has the overall contact distance as 4'-2" but that includes small fillets at each side. And we may not be seeing exactly where the bottom of the canopy really is.
Now to Frame 4 - notice the projection of the top of M11 almost touches the deck at the same place as the top of M10? Drop of the canopy looks like about 4 feet.
Frame 5 - more of the same - not a lot of difference from Frame 4. Top of M11 projects to almost same point as top of M10 at bottom of canopy. Drop estimate is 6 feet. Important point - top of canopy and M12 have dropped maybe two feet. Deck is still on top of pylon.
Frame 6 - Top of M11 is projected to two feet or more down M10 below the canopy. This suggests M11 has separated from Node 10/11 at this point. In fact, it appears the top of M11 projects to intersect the deck maybe 80 feet to the south. The top of the canopy at M12 is now dropped maybe 4 feet or more. Total drop is maybe 8 feet or more. Deck appears to be on top of pylon. This frame and Frame 7 have two intersecting lines at the left end which, in Frame 6, appear to be a projection of the canopy and M11 - are these construction lines and not something popping out of the construction?
Frame 7 - The canopy looks to be folded about at the left side of the white crane boom. Node 9/10 has about hit the roadway. Is the deck still on top of pylon?
Thanks for the great work.
RE: Miami Pedestrian Bridge, Part XIV
You are flogging a dead horse now.
Upper end of member 11 may have been damaged but did not break. The photo below shows upper end of member 11 was able to act as a fixed support of a cantileve after the collapse. The free end of the cantilever (member 11) has rebar resting on on the pier but they were not bent suggesting member 11 was able not to relying the pier as a support. You can search videos of NTSB engineers milling around underneath member 11 never feeling any safety issue.
Any engineer with the basic understanding of statics can tell us that if the member 11 were unable to hold its position at the bottom with the deck but move to the north then the whole bridge will collapse.
Equally if the upper end of member 11 move vertically above the canopy the bridge will also drop.
The evidence in the field is member 11's upper end has not moved upward but was still solidly connected to the canopy as shown from the above photo. In the collapsed bridge the canopy folded or hinged at the point member 11 meets member 10. The blister simply came off from the canopy with possibly some rebar attached.
The important feature of the bridge is member 11 is a strut. As long as member 11 does not crush or buckle in compression and the two ends are structurally connected it will be able to "prop" up the bridge.
All the evidence in the field and the official reports from MCM, FIGG, OSHA and NTSB indicate the bridge failed because of 11/12/deck connection.
Yet the discussions that something fishy happening at the canopy joint amount to nothing but video footages confirming the canopy hinge deflection being more pronounced than that of the hinge at the deck. This has been pointed out that top of member 11 might have separated from member 10 at the canopy during the fall. I post a similar shot taken by another vehicle (I believe) showing the separation.
All post-collapse photos show the canopy has been broken up at this location. Only the breakage took place during the collapse could explain why Member 11 was able to attached to the canopy and ended up as cantilever on the ground.
RE: Miami Pedestrian Bridge, Part XIV
Saikee's first photo above, The upper PT rod appears to be supporting member 11.
Saikee's third photo above, Member 12 is shown still at right angles to the canopy.
It appears that member 11 has broken at the upper end.
We can agree to disagree.
Blame parallax and poor quality frames.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Good point. It sure looks that way to me.
RE: Miami Pedestrian Bridge, Part XIV
This photo suggests that M11 may not have remained attached to the Canopy unbroken.
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
I'd say the upper end steel that bridged between the canopy and member 11 was largely intact. But is 11 still attached? I guess it depends on whether the rebar in 11 is considered part of 11. It's clear that all the rebar in 11 joining it to the deck was either severed or torn loose and the concrete at that joint was pulverized, so that joint clearly no longer exists.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
From a post by Ingenuity on 16 Mar 18 07:04 in the first part.
Things are really going in circles....
RE: Miami Pedestrian Bridge, Part XIV
Is that a PT ROD I see?
Maybe from M11?
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Thank you.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Justice is done finally to a designer refusing to admit own mistakes even up to now.
I have said earlier that my respect of Figg dropped into the gutter when Figg was claiming the FIU bridge was still safe in the morning on the day when the bridge collapsed in the afternoon. Most qualified bridge engineers and RC designers would have known the bridge has gone just by looking at the photos of the extensive cracks right at the most vital locations.
It is also increasingly clear the re-stressing of the two PT rods on a badly cracked 11/12 node has accelerated the demise of the structure.
RE: Miami Pedestrian Bridge, Part XIV
Two firms that were involved in the investigation are giving a short talk at the SEAOI (Illinois SE) bridge symposium:
https://www.pathlms.com/ncsea/courses/20483/webina...
The talks seem pretty short so I doubt they will get into anything we'd really be interested in. But WJE is one of the speakers.
EIT
www.HowToEngineer.com
RE: Miami Pedestrian Bridge, Part XIV
Good luck with developing a conceptual repair/retrofit...did the carrier not see the extent of the collapse before setting the tasks?
RE: Miami Pedestrian Bridge, Part XIV
"I have said earlier that my respect of Figg dropped into the gutter when Figg was claiming the FIU bridge was still safe in the morning on the day when the bridge collapsed in the afternoon.:"
Yes, but it is also clear that FIGG did not have anybody on site to assess the crack. The telephone message by Denny Pate does not state that he had seen the cracks. Then, he had to destroy his telephone in the laundry, because it no doubt showed that he had seen nothing, but gave his assurance that it was all OK.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
"Hey Tom, this is Denney Pate with FIGG bridge engineers. Calling to, uh, share with you some information about the FIU pedestrian bridge and some cracking that's been observed on the north end of the span, the pylon end of that span we moved this weekend. Um, so, uh, we've taken a look at it and, uh, obviously some repairs or whatever will have to be done but from a safety perspective we don’t see that there’s any issue there so we're not concerned about it from that perspective although obviously the cracking is not good and something's going to have to be, ya know, done to repair that. At any rate, I wanted to chat with you about that because I suspect at some point that’s gonna get to your desk. So, uh, at any rate, call me back when you can. Thank you. Bye."
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
https://www.nbcmiami.com/news/local/engineers-dism...
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Very sad that FIGG (EoR with significant past-experience as a senior bridge design engineer) personally witnessed that degree of cracking/distress then attend a meeting stating:
RE: Miami Pedestrian Bridge, Part XIV
Allegedly responsible experts examined the cracks.
The alleged experts then dismissed the cracks as unimportant and gave orders that resulted in the destruction of the bridge and multiple deaths.
The contractor may have made an expensive mistake but he was not responsible the death and destruction.
That is on the alleged experts.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Certainly not to defend anybody but you have to remember that while he was a well-qualified senior bridge design engineer he nor anyone else had any experience with a breach of this type. As a matter fact since most of their experience was with steel construction for bridges there overall view of what was a problem was probably somewhat distorted.
RE: Miami Pedestrian Bridge, Part XIV
Either you have prior experience, you have a solid grasp of the fundamentals to assess new situations, or you don't perform the work. Basic engineering ethics.
I agree that FIGG and Pate's reputations only get more soiled the more we learn.
----
just call me Lo.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
"Figg left the site to return to Tallahassee to develop a way to enhance the north end truss member connection at this stage of construction."
Why? If all was well and good and no one had any concerns, why?
IC
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Thanks.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
"Miami Pedestrian Bridge Collapse - A Bridge Too Frail"
June 23, 2020
https://nsc.nasa.gov/resources/case-studies/detail...
Lessons Learned
http://julianh72.blogspot.com
RE: Miami Pedestrian Bridge, Part XIV
Sorry for straying outside the subject of this discussion.
Brad Waybright
The more you know, the more you know you don't know.
RE: Miami Pedestrian Bridge, Part XIV
Brad Waybright
The more you know, the more you know you don't know.
RE: Miami Pedestrian Bridge, Part XIV
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
One of my colleagues sent me the graphic from an article in New Civil Engineer.
Link
RE: Miami Pedestrian Bridge, Part XIV
The issue about "designing outside the area of engineering principles" is more appropriate to a bridge structure than to a very risky space exploration project. There was no need to experiment with this bridge without understanding its behavior beforehand. The issues with the design were that the form of the bridge as a concrete truss/frame of that shape and magnitude had never been done before, and then they relied on unproven shear friction theory in a critical joint. The design could have been proven or otherwise by load testing before erection, while the bridge frame was still in the casting yard.
RE: Miami Pedestrian Bridge, Part XIV
your comment "The issues with the design were that the form of the bridge as a concrete truss/frame of that shape and magnitude had never been done before, . . . " is not correct. The record is full of instances where concrete trusses were successfully used in bridges and other structures. However, I agree that in none of these instances was shear friction theory applied. Whoever came up with that theory should face a court martial.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
I 100% agree that there are few examples of RC or PRC trusses used as bridges, and definitely none with deck and canopy used as top and bottom chords. So, the bridge was definitely a novel structure, designed using wrong code, with the initial S.F. close to 1.3-1.35 at construction stage, a horrible detailing of the joints - the node in between the deck and #11 diagonal being classical example (positioning of the anchorage of post tensioning rods in the middle of the bottom joint causing likely delamination below the anchorage - and the sliding plane). The shear friction theory was discussed at length, so I will not comment on it. The simple approach is that the cracked concrete cannot carry any stresses, so the theory works only with uncracked concrete, and most likely in the lab condition.
The reports by OSHA and NTSB are both missing the crucial point - C/D ratios were computed using demand computed with load factor 1.3 for DL and for the bridge with DL/LL=9 this was suicidal. All RC trusses existing or proposed have overall SF of 2.5/3, and these are mostly redundant structures.
RE: Miami Pedestrian Bridge, Part XIV
I suspect strongly that the failure would have occurred in the finished product, too...
Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?
-Dik
RE: Miami Pedestrian Bridge, Part XIV
Maybe there is a better explanation out there of why they chose the lower demand model, but I have not seen it.
What happened after the cracking started to occur is a different story.
EIT
www.HowToEngineer.com
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I have not worked with polarized light but it would seem it could reveal distortions from a true plane, but the model used would require great precision to start with. If the PL could show changes in density which could represent stresses the model would need to be loaded appropriately.
The problem developed at the joint of the truss diagonal to a 32 foot wide deck, so three dimensions would be required.
Perhaps the light of a setting sun (career) would have been most helpful.
So tragic.
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
The issue with FEA is that even with my exposure to it which encompassed Dos to windows to integrated into pro engineer and autocad (I actually used to work for strucom who did the initial port to autocad) is that generating a FEA model became way to easy. Everyone just blasted it through and had no conception what they were doing with the mesh or the element types. It was pretty grim in the late 90's i would hate to think what its like now with colossal computing power and getting away with murder. We had to be tight and know what we were doing with 18 hours static load runs on a 486. I was mainly doing none linear which had its issues. But even with company's that should have know what they were doing you were presented with the issue of explaining that it was a nonlin geom problem and worse than that tet mesh was completely the wrong element type to use.
I suspect the model they were using was a static linear model which would give utter nonsense results especially if all they looked at was the von misses and didn't roll back to none linear geom and displacements.
RE: Miami Pedestrian Bridge, Part XIV
I'm not sure...
Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?
-Dik
RE: Miami Pedestrian Bridge, Part XIV
Maybe load factors should be adjusted upwards with every automated analysis option used in a design. Of course on the other side the gross simplifications sometimes made in hand calculations can also lead to problems.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
The over reliance on software solutions is a problem in all fields of engineering. I had the opportunity to introduce a newly minted engineer to the psychrometric chart today, just as good today as it was 50 years ago. For some tasks just as fast at the computer calculation.
Fred
RE: Miami Pedestrian Bridge, Part XIV
An asymmetric concrete truss with different width flanges, made to look like a cable stayed bridge hence more forces concentrated at one end, The flanges themselves were not evenly tensioned.
Then the real killers - late extension to the length forces the two ends to become cantilevered during the rather fraught installation forcing extra tension tendons only for the transportation phase in members 2 and 11. Throw in the fact that at least some parties never analysed the part completed bridge, the joint area at 11/12 was changed to incorporate lots of ducts and tubes and the bridge really should have collapsed as soon as they removed the transport supports. IMHO.
Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?
-Dik
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?
-Dik
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Here is a link to an interesting POD cast to watch.
I personally think too many people are making too much of the bridge being a truss when the real issues were a design flaw in the joint (which could have been designed properly) and more importantly an ethical issue. When the design issue was discovered (very large cracks), the public was not properly protected.
There are some real benefits to a PC concrete truss. The asymmetric flanges are not an issue. The diagonal layout is not that hard to deal with. There are more difficult issues to resolve than these issues. In fact, that is what may have distracted the designers. They couldn't see the forest from the trees.
RE: Miami Pedestrian Bridge, Part XIV
This seems like an incredibly badly designed and badly constructed connection.
I don't believe that the constructors were made aware that this area was much more critical than the other similar poured joints on the bridge.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
A number of the other joints were critical (overstressed by code). The south was theoretical even worse. If the construction information is on the drawings and specs, there is no need for the contractor to know how stressed the joints were. However, in similar situations, I think it is a good idea to have a conversation to let the contractor know about areas that are highly stressed and critical to the design. In essence, the contactor should assume all the structural elements are critical until confirmed otherwise.
RE: Miami Pedestrian Bridge, Part XIV
nd on one side of the bridge.RE: Miami Pedestrian Bridge, Part XIV
The problem is how do you get the horizontal end reactions of the canopy resisted - only one column at each end is 'fixed" to a support, so the reaction is maybe 67 kips and moment at 16 feet is 1070 ft-kips. Have not checked the reinforcing but member 1 and 12 are not heavily loaded. Plus 12 is encased in lots of concrete before the live load should be present. But my takeaway is a lot more steel would be needed than is required on the drawings.
Of course torsion in the large deck section could begin to provide lateral resistance through some diagonals near the end, and the stiffness of the deck could relieve the forces transmitted to the roof near the ends. A bit difficult to evaluate on an envelope back.
The designers submitted 3 or 4 thousand sheets of calcs - maybe it is in there somewhere.?
But I had the same thought.
And with all the talent on this forum, I wish someone would investigate the 16" pipe "fake stays" for vortex shedding. At 130 feet long, it just looks like they could really hum. Key of E for rock - maybe G for bluegrass ?
Thanks,
RE: Miami Pedestrian Bridge, Part XIV
The structure was designed anticipating a negative camber, even with the post tensioning system. The natural forces pull the base of the columns at either end toward the middle of the span while the stiffness of the end columns and the outward force of the diagonal members resist. Much effort has been invested in analyzing the structure through the frame of reference of the outward/downward force transmitted by the diagonal even in the face of obvious complications such as the portion of deck directly beneath Member 11 suffering minimal damage through the collapse. A much easier analysis can be done by examining the system through the frame of reference of the tension force exerted at the node by the deck, the question becoming "Is the deck adequately tied to the node"?
The obvious answer is no. The explanation quickly moves to the portion of slab beneath Member 12 which is isolated from the larger slab by a number of inclusions including four white ducts for future tie downs, six blue electrical conduits (three on either side), perhaps a grout line or two, and also the PT anchor plate for the lower PT rod. The deck rebar passing through the portion of slab beneath Member 12 is minimal. This isolation sets up the failure. If the slab is not a cohesive unit passing beneath Member 12, the only connection it has to the node is through the footprint of Member 11. The rebar, largely oriented as dowels are not optimized to resist the horizontal force. Even 300 percent more steel would not resist the destructive force of the tension in the deck. In fact, since the system ceased functioning as a cohesive unit, these very rebar are now serving to tear Member 11 apart with the base of 11 being pulled down and south with the deck. As the lower PT rod is retensioned, it cannot restore the structure but instead becomes the leveraging force pushing the remaining 11/12 node north while pulling the end of the deck south and further displacing the mid span downwards. This vicious cycle exasperates the tearing at the base of Member 11 while at the same time distorting it across the longitudinal axis.
I'll throw this in here because there is no eloquent way to include it. Surface roughening is not an issue. The base of 11 was doing its damndest to resist moving with the slab but it had no choice. Although a slight gap opened up beneath 11, this is not evidence of the "sliding" that it's made out to be. More surface roughness would only improve the efficiency of the tearing mechanism.
As I've posted earlier, it seems that Member 11 was pushing hard against Member 12 when it finally gave out, causing the kink in the upper PT rod. It did not take more than a few inches of relative displacement between the deck and 11/12 to destroy 11 at the deck interface. As 11 fails and the structure starts to collapse, the pancaking 11 hammers at the node while the deck rotates the diaphragm causing 12 to skip off to the north. The rotational component is evidenced by the CW/CCW diagonal fracture pattern seen in the diaphragm (it is not the cause of the failure, it is the result of the failure).
OSHA got this much right, "There is no viable mechanism to capture the horizontal tensile forces from the diagonal 11 to the deck." This failure is not at all mystical and it certainly does not give rise to the loose and sensational blanket statement of a concrete "blow-out". The largest identifiable concrete remnant landed immediately adjacent the base of the north end of the supporting pier. The structure succumbed to deliberate ill conceived actions of irresponsible parties and fell straight down.
Two things I would have expected to hear from the NTSB study, mention of management techniques pertaining to the meeting on the morning of the collapse (akin to aviation cockpit management where a plurality of experience and ability is used as an advantage), and footprint stress analysis of the awkwardly loaded Member 11.
In closing, I'd like to say that ego is not the best face of the NTSB. Colombia is spelled, "C-O-L-O-M-B-I-A"!
Edit: Three things -> also discussion of the camber and its progression since the work crew was using it as a measure of caution.
edit: Four things -> a measure of how much extension was pulled on the upper and lower PT rods with the retensioning. It would not have been a straight forward exercise if the structure was reacting to the load while the crew was working on it. The upper PT rod may not have required as much pull if it was stretching while the lower was pulled and the lower may have gone slack while the upper was pulled.
RE: Miami Pedestrian Bridge, Part XIV
Or maybe the top surface of the base of Member 11 failed first? Clearly the cracking exhibited on the east and west sides of Member 11 can be seen as the side longitudinal column rebar pushing out the skewed stirrup. All that space at the lower end of 11 was a problem. Once the rebar reaches the nodal block, it is once again safely tucked inside the nodal block stirrups. I think we are finally getting to the real answer.Added:
I notice now that there was a problem with the column rebar lap right at the skewed stirrup. The devil is in the details and the details are getting chewed up.
I'm struggling to make sense of the rebar a the bottom end of 11. Does anyone with rebar experience have any comments on the workmanship visible in the photo's?RE: Miami Pedestrian Bridge, Part XIV
My comment about reinforcing at node 11/12 is simply there is too much happening in too little space.
As I see the construction drawings, the reinforcing requirements for Member 11 could have been easily interpreted two ways due to the presence of the PT rods. One interpretation would result in less than code minimum reinforcing for a compression member.
In either interpretation the member appears to be lightly reinforced, particularly considering its importance to the success of the structure.
RE: Miami Pedestrian Bridge, Part XIV
In the near future I will likely break down the rebar visible in this photo and check for any indications of improvements made prior to casting that other photos cover.
RE: Miami Pedestrian Bridge, Part XIV
I don't seem to be able to find your top photo of the crushed member 11, do you have a reference handy?
Thanks,
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I was going through the Bridge Factors report from the NTSB database when I found the formwork photo, though that one is marked up. I see waross has included it earlier in this thread.
RE: Miami Pedestrian Bridge, Part XIV
This is excellent work! Thank you so much
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The blue sky photo is from the OSHA report, the formwork photo is from the FIGG report (right click on the photo and copy gives a copy without the overlaying annotations), and the arm measuring is from the Bridge Factors Photo evidence. As I stated earlier, the OSHA image is flipped around, it is a view from the east overlaying a view from the west.
Now to explain the following, one image is from the NTSB B-roll video (the darker sky) and the other is from Materials Laboratory Factual Report - FHWA TFHRC Steel and Concrete Materials Testing. They are scaled and rotated slightly.
To borrow from Figure 57 in my above post, the two medial longitudinal rebar along the east face of Member 11 (that I have coloured yellow above, red-orange and hot pink below) seem to have escaped the collapse unscathed.
The J-hooks extending the member through the nodal block and slab along the east and skyward face (red above, green and yellow below) have assumed the displaced shape of the upper PT rod.
From the NTSB presentation, the following overhead image credited to the Florida Highway Patrol, indicates member 12 in its final position in alignment with the longitudinal axis of the deck. Member 11 however, has kicked out to the east. The exposed rebar on the west face of member 11 is significantly mangled. Together with my above post, it suggests to me that Member 11 buckled or sheared just above the nodal block with the upper portion moving east.
To me there is no question that Member 12 held fast to the diaphragm while Member 11 pressed hard against it and failed. As these types of failure are know to be sudden, there was no indication, to even a seasoned observer, as Member 11 was overloaded with compression that morning. A clear hole blowout in Member 12, as suggested by OSHA, or any translational shear of Member 12, as is the unambiguous theme of many others, would not have allowed this damage to Member 11.
I estimate that there was a three foot length of Member 11 along its skyward face (see my above post) that was inadequately reinforced (missing hoops). It seems to have been an assembly difficulty that begged for a solution that was never found. In the end, this disaster should be seen as a colossal reinforcement design failure, though not for the dowelling issue cited by the NTSB.
From the MCM Party Submission,
RE: Miami Pedestrian Bridge, Part XIV
Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?
-Dik
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?
-Dik
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
On day one, when the shoring was removed, the deck detached from 12 as per the following sketches (which are exaggerated for illustration). The situation became more obvious with time as the cracks became more pronounced. The structure managed to stay together until 11 buckled/sheared and the span started to go down. As the structure begins to go down, the top of twelve has to move north several inches to accommodate the geometry of the rotating long end of the bridge. 12 is somewhat held in its vertical orientation (though it bows considerably) while the deck rotates the diaphragm off of 12.
These sketches are not perfect but they serve to illustrate the bigger idea of what I'm trying to get across.
EDIT: The east/west arrows on the compass are backwards. It's rather karmic that I took this sketch, and compass, from the NTSB report
EDIT 2: Problem solved!
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The 11/12 connection to the deck failed in shear.
The concrete was broken and the joint was held together by some rebar.
The lower PT was anchored at one end to member 11 and at the other end by the deck.
The lower PT rod crossed the existing failure in such a way that increased tension tended to open the existing crack.
When the lower PT rod ripped out of the bottom of member 11 and the rebar crossing the crack failed, the 11/12 connection left the deck.
The concrete had already failed days before.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
Thank you very much!
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
I also feel that the cracks running up member 11, traveled deeper into member 11 that just delamination of the cover concrete and were a sign of eventual compression failure in 11, just in advance-of/above the 11/12 node.
I had been trying to work out, if the compression failure in member 11 & the shear failure, at the back of node 12/diaphragm occurred independently or simultaneously, as a result of de-tensioning the PT bars. And if the detetensioning of one bar created a load differential in member 11, resulting in shearing forces and cracking, inside of member 11 between the two PT bars.
The following photo from NTSB file 628553 , page 11 (Bridge Factors Photographs - FIGG Bridge Engineers, Inc. Photo Submission) - oddly out of dating sequence, demonstrates that failure took place at the back of the diaphragm, in conjunction with the cold joint failure/shearing, while the bridge was still in the casting yard. It is where the energy was relived from the minute sliding of 11 at the cold joint.
While examination of the engineering has determined that the bridge was doomed before it was even built,
Sym P. le is correct that the failure was initiated upon removal of the shoring.
RE: Miami Pedestrian Bridge, Part XIV
Suppose, for the sake of argument, the 1.75" lower PT rod was encased in a 3" plastic tube. At a 31 deg incidence angle, there would be 2.4" of play. In other words, the relative horizontal movement between the deck and the bottom of Member 11 would have to be at least 2.4" before binding would occur. That is not a likely scenario.
My apologies, I chased that seductive theory myself for a long time and struggled to move away from it even after I first did the calculation months ago.
RE: Miami Pedestrian Bridge, Part XIV
A 3" plastic tube will have significant buoyancy in wet concrete.
It will have been tight against the bottom of the PT rod.
The PT rod was anchored to the deck, not to the end of member 11.
It is possible and even probable that the pressure of the plastic tube against the bottom of the PT rod helped the rebar to restrain the 11/12 node when the concrete sheared and the cracks opened up.
I suggest that the failure of the rebars crossing the fracture and the failure of the bottom of member 11 when the PT rod started to rip out happened simultaneously or almost simultaneously.
I suggest that the triangle formed by members 11 and 12 and the canopy remained intact during the initial collapse.
The canopy cracked and deflected at the 10-11 node.
As the structure fell, the bottom ends of 11 and 12 were dragged across the top of the pier with much of the weight of the canopy adding to the forces.
Member 11 had already be severely compromised by the damage done when the lower PT rod ripped out.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
The 11,12 node may well have been pulled down on the top of the pier by the weight of one end the entire canopy and the weight of most of the bridge.
That explains the damage to the 11,12 node.
Look at the pictures of the upper PT rod and the recently posted aerial photo which shows member 11 displaced sideways.
Member 11 was definitely broken at both ends.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
A: It deflects the energy to baffle the NTSB!
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
"The only thing more laughable than the reinforcement detail at the bottom end of Member 11 is that it wasn't the weakest link in the structure."
This statement is correct because member 11 was loaded in compression. Concrete has considerable strength in compression. The portion of the design that was weaker than member 11 itself was the connection of member 11 to the concrete deck.
That is because:
(a) this point of connection witnessed very high tension forces generated in the concrete deck;
(b) concrete has practically zero strength in tension; and
(c) there was no steel designed or introduced into the concrete deck to deal with this tension force;
(d) the foregoing is evidenced by the fact that the failure mode was apparent just before failure: the photographs show large tensile cracks appearing in the deck and not appearing in member 11. True, some spalling was seen on the corners of member 11 as the deck/11 node rotated, but the deck was the element that formed tensile cracks one inch wide and into which a tape measure could be inserted up to seven inches deep.
RE: Miami Pedestrian Bridge, Part XIV
Member 11 doesn't shrink, it passes behind the obstructions.
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Miami Pedestrian Bridge, Part XIV
The release of the upper PT rod after the move is what allowed member 12 to move north, thus the "cracked all to hell." An implication of this is that further travel north required further release of the upper pt rod, as such, an unlikely scenario. The upper PT rod is the key to this puzzle, not the lower one.
Member 11 displays all classic signs of compression failure both before and after the collapse. Retensioning both upper and lower PT rods caused the collapse. Edit: by overloading Member 11.
RE: Miami Pedestrian Bridge, Part XIV
I have drawn the triangle of C,11,12 on each frame and compared the frames and 11 shortens. Please go to any one of the many posts on this subject,
Thank you.
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
At 3:00PM VSL - Kevin Hanson informs SAMUEL NUNEZ, Project Manager Structural Technologies VSL, that they don't have hydraulic oil for the equipment and asks for the grade required.
At 3:09PM SAMUEL NUNEZ, Project Manager Structural Technologies VSL, responds that the grade required is AW32.
RE: Miami Pedestrian Bridge, Part XIV
That is an excellent and important detail. It points to how deficient the reinforcement was, both by design and installation.
I don't believe this is a sophisticated failure. The bottom three column hoops were omitted (by the designer) and though some of the longitudinal bar was intended to be meshed inside the node rebar, the adequacy of this let alone the execution is hardly a substitute.
The collapse was temporal to the retensioning of the PT rods and thus the activity played a role but this structure was distressed and likely to fail short of immediate intervention, namely shoring.
RE: Miami Pedestrian Bridge, Part XIV
This is quite the revelation given that we have been led to believe that destressing was the problem.
Page 15
Page 39
Page 40
RE: Miami Pedestrian Bridge, Part XIV
RE: Miami Pedestrian Bridge, Part XIV
That is not to say that re-stressing number 11 made any sense to begin with. It never the less remains that if he didn't understand that the bridge was, in fact, failing under its own weight prior-to destressing; that had he been informed of such, his decision making might have taken a different course of action.
Wasn't his lead on the project on vacation for a week or two, immediately after the bridge was set into position? It also doesn't appear that MCM recognized or made a point to convey a clear timeline of cracking, not realizing it could be significant to Figg's review.
Sym P. le - Congratulations on making it through the Alexis Molena transcript.
RE: Miami Pedestrian Bridge, Part XIV
SF Charlie
Eng-Tips.com Forum Policies
RE: Miami Pedestrian Bridge, Part XIV
Why he couldn't see & understand that the north end of the bridge was blown out is another matter.
RE: Miami Pedestrian Bridge, Part XIV