INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

best practice to validate caesar II report

best practice to validate caesar II report

best practice to validate caesar II report

(OP)
Dear all piping stress engineers,

i hope we all in good condition. i want to ask, is there any best practice can we take to review displacement allowable range (not stress) that occur on piping system and the load on restraint of the piping system for caesar II report review activity?

thank you all
Replies continue below

Recommended for you

RE: best practice to validate caesar II report

What exactly are you asking? It's easier to review the stresses and forces by using Caesar since most models are too large to realistically review thru the Excel/Word reports.

If you're asking what to look for while reviewing; ensuring code stresses < 100% and restraint are adequate (steel/concrete/whatever is strong enough, not excessive movement, etc). Additionally you want to review any equipment connections and compare them with the equipment allowable loads or other criteria.

RE: best practice to validate caesar II report

(OP)
Thank you RVAmeche,

"restraint are adequate (steel/concrete/whatever is strong enough, not excessive movement, etc)", is there any best practice for reviewing the safest displacement distance for Dx,Dy,Dz,Rx,Ry,Rz so we can ensure that the value of displacement is safe?

thank you

RE: best practice to validate caesar II report

Dear Zul78289,

is there any best practice for reviewing the safest displacement distance for Dx,Dy,Dz,Rx,Ry,Rz so we can ensure that the value of displacement is safe?

It depends upon the project specs. Usually criteria is: sag (-DY) should be less than 12.5 mm, and Axial Displacement less than 75 mm, if it's more than this value, displacement should be marked on Stress Isometrics, so that the larger shoe (if applicable) could be employed.

Secondly, it's important to check that there is no clash with the adjacent lines.

RE: best practice to validate caesar II report

It also depends on the physical space available; ie, how big the gap is on your guided slides, or if there's any equipment/items located nearby that the pipe may hit depending on the magnitude of growth.

There's lots of guidelines for various scenarios; nothing is one size fits all.

RE: best practice to validate caesar II report

(OP)
Dear all,

Thank you so much for the answer. But if any cases that the project specification not stated any provisions about maximum displacement either on displacement report or restraint summary.

Is there any standard do you know that regulate this maximum displacement and load on restraint?

Thanks

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close