The Necessary of 5 Points Check
The Necessary of 5 Points Check
(OP)
In Centrifugal pump, between bearing type or others say center hung type, is it necessary to do 5 points check if only 1 side of mechanical seal is under replacement or installation..?





RE: The Necessary of 5 Points Check
It is a capital mistake to theorise before one has data. Insensibly one begins to twist facts to suit theories, instead of theories to suit facts. (Sherlock Holmes - A Scandal in Bohemia.)
RE: The Necessary of 5 Points Check
Johnny Pellin
RE: The Necessary of 5 Points Check
RE: The Necessary of 5 Points Check
Johnny Pellin
RE: The Necessary of 5 Points Check
My mind jumped to 5 data points to establish performance and/or check the pump to the curve - no flow (deadhead), min rated flow, design point or some mid-point/max eff., max rated or just shy, and runout off the end of the curve
RE: The Necessary of 5 Points Check
1.) Radial deflection (0.005mm)
2.) Axial play/ Shaft End (0.1mm)
3.) Shaft run-out (0.05mm)
4.) Concentricity of bore (0.125mm)
5.) Squareness of face(0.125mm)
All checks must below those numbers (for axial play, its depend on type of bearings)
Let say outboard(O/B) or NDE side of seal is fail. So, we take out the seal and replace with new one. But, before installation, we normally do these 5 checks. So, back to my question, is it compulsory to do these checks if only 1 side of seal being install??
RE: The Necessary of 5 Points Check