INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

API 653 Hop Tap for 8" nozzle

API 653 Hop Tap for 8" nozzle

API 653 Hop Tap for 8" nozzle

(OP)
Dear Sir.

Does anyone coult tell me if, for a tank of dia x H = 27.625' (liquid hight 20.8'), we can performance a hop tap of 8" nozzle having a shell average meassured thickness of 0.208". I know that API 653 require a minimum thickness of 1/4" but the shell plate required by calculation, using A283C plates and E = 0.7, is 0.1472".

In case that we can not performance the hot tap procedure I would apprciate any alternative to place in the tank a 8" nozzles without empty the thank

Thank for your help

RE: API 653 Hop Tap for 8" nozzle

As you note, API 653 calls for a minimum shell thickness greater than yours.
Possible options:
Don't comply with API 653
Hot tap two 6" nozzles and pipe them together
Hot tap a shell manway cover plate with an 8" nozzle, if the cover plate is 1/4" or more

RE: API 653 Hop Tap for 8" nozzle

Sometimes you must empty the tank ....

No spare empty tank available ? ...... Discuss this with the plant manager and the process engineer, perhaps this could be a future enhancement.

Suggest that you consider the modified shell manway cover plate fix. You can have a replacement made in the shop and ready to swap out during a brief shutdown

MJCronin
Sr. Process Engineer

RE: API 653 Hop Tap for 8" nozzle

Is the required minimum thickness the concern of the burn through during the hot tap?
Check with your plant Material Engineer to see if it helps to add a butter weld layer on the pipe for the hot tap connection.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

White Paper - PLM and ERP: Their Respective Roles in Modern Manufacturing
Leading manufacturers are aligning their people, processes, and tools from initial product ideation through to field service. They do so by providing access to product and enterprise data in the context of each person’s domain expertise. However, it can be complicated and costly to unite engineering with the factory and supply chain. Download Now
White Paper - Medical Device Design Control
Medical device product development is a highly integrated and regulated process. Implementation of a requirements tracking solution requires attention to a variety of nuanced topics. When presented with the task of tracking the many concept relationships in a project of this type, the initial software solution of choice tends to be a two-dimensional text systems. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close