INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Partial landfill mining

Partial landfill mining

Partial landfill mining

(OP)
Hello everybody,
the discussion topic that I would like to introduce is that of a partial landfill mining, related to a road that has to cross part of a former urban waste landfill area (the site was closed several years ago). Of course, the area interested by the road must be emptied, since waste does not sustain the loads safely. It is impossibble to change the road path, as well as to build a bridge. Therefore, the issue is to separate more efficiently as possible the part of the landfill to be excavated from the one still remaining as it is. The initial idea was that of doing a slurry wall made of concrete inside the landfill body and then digging out waste in the foreseen road side: some problems with this option are bound to the difficulties to excavate for such a wall in the middle of the landfill body, also because the bentonite would escape from the waste voids, and this would create problems also in the subsequent mined waste classification. Another option could be relying on a reinforced earth slope to be recreated, in order to separate the two parts after waste excavation: anyway, this would probably require to excavate and dispose away a major amount of waste (i.e. more costs). Do you know of some similar cases in which an efficient solution was opted for? Any suggestion would be of great help.

Ps: the waste is not dangerous and well-stabilized.

RE: Partial landfill mining

how long is the road across the landfill? what is the thickness of landfill?

You really want to avoid excavating the existing landfill, can you support the road on a piled slab? Likely expensive but mitigates the cost of disposing of landfill material and the additional environmental warrants required.

You have a tricky problem.

RE: Partial landfill mining

(OP)
EireChch,
thanks for you reply.

The landfill thickness ranges from 2 to 11 m as strictly concerns the waste layer (quite irregular in spacing, but it's an old landfill), plus about 1 m of covering material. The constraints ask for the road to cross the landfill for a lenght of about 150 m. Total excavation foreseen to create a proper road basement would be almost 90 000 cubic meters: half is waste.
Do you know of reference cases of piled slab in situations like this one? Thank you.

ps: under the landfill there is a thick layer of well-graded gravel (at least 10-15 m from the surveys).

RE: Partial landfill mining

Can you use geotextiles to reinforce the top surface? Can the road be inexpensive with the intent of a limited life?

Dik

RE: Partial landfill mining

Dynamic compaction has been used several times for such a case. You can expect the compaction process to lower the Platform about 25% of the waste thickness.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

White Paper - The Criticality of the E/E Architecture
Modern vehicles are highly sophisticated systems incorporating electrical, electronic, software and mechanical components. Mechanical systems are giving way to advanced software and electronic devices, driving automakers to innovate and differentiate their vehicles via the electric and electronic (E/E) architecture. As the pace of change accelerates, automotive companies need to evolve their development processes to deliver and maximize the value of these architectures. Download Now
White Paper - Model Based Engineering for Wire Harness Manufacturing
Modern cars, trucks, and other vehicles feature an ever-increasing number of sophisticated electrical and electronic features, placing a larger burden on the wiring harness that enables these new features. As complexity rises, current harness manufacturing methods are struggling to keep pace due to manual data exchanges and the inability to capture tribal knowledge. A model-based wire harness manufacturing engineering flow automates data exchange and captures tribal knowledge through design rules to help harness manufacturers improve harness quality and boost efficiency. Download Now
White Paper - Modeling and Optimizing Wire Harness Costs for Variation Complexity
This paper will focus on the quantification of the complexity related costs in harness variations in order to model them, allowing automated algorithms to optimize for these costs. A number of real world examples will be provided as well. Since no two businesses are alike, it is the aim of this paper to provide the foundational knowledge and methodology so the reader can assess their own business to model how variation complexity costs affect their business. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close