Thank you all for your input so far. I am trying to make my way through the NSBA document mentioned above. Hoepfully the answer becomes clear on what analysis will be required. I think I know what the answer is already but the people who write check around here will need a solid answer in order to invest in new software.
To answer the questions that have been asked, I'll do my best.
The bridge is actually a set of twin structure separated by a 2" gap between the decks. One deck will be poured all in one phase, the other bridge will be poured in 2 phases, well three considering the closure pour. The bridge aren't true twins since the overhang radii are different so separate analyses will take place. We want to simply the fabrication of the girders, so we hope to provide only one girder design.
Our research has show that the contractor should be able to pour the deck along the skew and load all of the girders concurrently thus eliminating some (most?) of the differential deflections. The length along the skew of the deck will be around 106'.
The DOT requested that we only look at straight beams with the curved deck. Not sure why they requested this. Good question though. Sounds like a slight curve in the beams would eliminate some issues like forming the variable deck edge.
We will definitely be looking into erection process.
We performed a superstructure type study in the 1st phase of this project. We went in thinking that prestressed concrete I's (Wide flange beames) would win hands down from a cost standpoint. With this amount of skew, our DOT requires the semi-integral diaphragm to be 5.8' wide. For the steel option, since we can clip the top flange back to the web, the semi-integral diaphragm only needs to be a little over 3' wide. The wider diaphragm also causes the span to increase by about 5' when compared to the steel option. The prestressed beam required about 360 CY more of concrete in the diaphragm alone. The bridge is also in a sag vertical curve. We checked the haunch thickness and it exceeded 7" in a lot of locations. Anything over 5", our DOT requires the haunch to be reinforced, more cost. When considering life cycle costs, the girders will be galvanized thus eliminating a lot of costly painting in the future. With the wider heavier diaphragm, longer span, and added weight of the prestrssed I's vs. the plate girders, the foundation system cost increased also. So combining all of these, we concluded that the steel option was best fit for this location. It worked out to be about $700,000 cheaper. Though the DOT could still come back and decide to use the prestressed option. Doubt they will though.
Thanks again! All suggestions and comments are welcome.