Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

long term people schedule

long term people schedule

long term people schedule

(OP)
Our office (structural engineers) is in desperate need of a platform to look at our long term project outlook with regards to our staff allocation. We want to be able to see how much time a single project will consume one engineer or group of engineers, and be able to assign projects to project managers based on their availability in the future. Can anyone chime in with their experience on software that can do this? Microsoft Project is one avenue that we are looking at, but I want to see if there is anything else out there we should be looking at. thanks for your help.
Replies continue below

Recommended for you

RE: long term people schedule

Former employer we had an admin (forget her title, something like engineering accountant or something) one of whose tasks was to do this using Excel & Project.

It's nice to be able to see you're scheduled to work 109 hours a week to keep projects on track rather than just feeling like it.

Posting guidelines FAQ731-376: Eng-Tips.com Forum Policies http://eng-tips.com/market.cfm? (probably not aimed specifically at you)
What is Engineering anyway: FAQ1088-1484: In layman terms, what is "engineering"?

RE: long term people schedule

Our office (full service A/S/M/E/C) does this with a spreadsheet that is updated monthly. In a nutshell the process we use is as follows:

Each project manager reviews their projects indicating the anticipated revenue and effort by each department that every project will require for each of the next 6 months.
These are compiled to determine the total anticipated revenue and required labor effort for each department for each of the next six months.
From this you can evaluate each department to determine if the current level of staffing is adequate or if there is too much work or too little work.
This also gives you a good idea of the overall workload and the trends (up or down) as the months go by.

The month to month effort is only 1 or 2 hours per PM plus another 2-4 for the individual compiling all the information.

I would imagine that in a structural only office you could do something similar but considering the position rather than the department.

Keep in mind that the information for something like this is only as good as the one providing it. This process was done for years before I started at our firm 9 years ago, so most of the bugs have been worked out and people understand how to read the information.

Regarding other software I've been told that Deltek has a module that does a lot of this. We have Deltek, but don't have this module so I can't speak to it's effectiveness or complexity.

RE: long term people schedule

I use MS Project and identify teams/people and project assignments with project end dates as the only milestone. Typically I take the project schedules and assigned team, roll it up and put it on an office wide schedule. This really helped us identify the weeks and months that were really slow for the office. one can get as detailed as one wants.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close