×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Credit for work not needed as a result of alternate means/methods

Credit for work not needed as a result of alternate means/methods

Credit for work not needed as a result of alternate means/methods

(OP)
We have a multi-million dollar sanitary sewer extension project that is currently under construction. The soil borings obtained during project design revealed extensive rock excavation would be required. Accordingly, language was incorporated into the specs to address a myriad of blasting concerns (e.g. blasting near watermains/services, gas mains/services, pre- and post blasting inspections of a nearby municipal well, etc.)

By using an excavator-mounted rotary grinder as well as drilling and jack-hammering techniques, the Contractor was able to avoid blasting, thus obviating the need for pre- or post-blasting inspections (and similar activities). While the Contract presupposed that blasting would be used, it also explicitly and exclusively obligates the Contractor to all means and methods. The Contract contains no provision for reimbursement of implicit work associated with an assumed means and methods when alternate means/methods are used. The means/methods chosen by the Contractor for rock excavation was still costly in terms of man hours required and wear and tear on equipment. The Contactor is well ahead of schedule in meeting the project completion date.

Recently, the Owner's Manager directed Staff to contact the Contractor and request a credit for the municipal well inspections NOT performed because of the fact that blasting wasn't used. Staff has no knowledge of what cost arrangements were made (if any) between the Contractor and the well inspection firm.

Question: Is it ethical for Management to demand reimbursement for work not needed as a result of a Contractor employing other means and methods?




Replies continue below

Recommended for you

RE: Credit for work not needed as a result of alternate means/methods

Was this is firm-fixed price contract?

RE: Credit for work not needed as a result of alternate means/methods

(OP)
03. Awarded Contract was $4 million and was comprised of 50 pay items with individual unit prices. The awarded unit price for rock excavation was $110/CY. All ancillary tasks needed to complete the rock excavation (monitoring, inspections, etc.) were made incidental this pay item.

RE: Credit for work not needed as a result of alternate means/methods

I'm not sure exactly what the owner wants. If it's just some unnecessary inspections thay want refunded, he seems to be missing a lot of costs. But I'd say the contractor got a windfall, and that's the way it goes. They're under no obligation to refund anything not spelled out in the unit costs and not done. If they want to be a good guy and refund something, that's up to them.

RE: Credit for work not needed as a result of alternate means/methods

It will depend on the wording of the contract, in firm fixed price type deals then the owner probably doesn't have a leg to stand on.

By going fixed price they put the risk management etc. on the contractor had things gone wrong. If the contractor finds a way to save on a few side items they get to keep that.

Posting guidelines FAQ731-376: Eng-Tips.com Forum Policies http://eng-tips.com/market.cfm? (probably not aimed specifically at you)
What is Engineering anyway: FAQ1088-1484: In layman terms, what is "engineering"?

RE: Credit for work not needed as a result of alternate means/methods

(OP)
The Owner is a unit of local government. It always looks good when a final cost can be presented to the Board that is less than the awarded project cost (which is the unmentioned underlying issue). But doing the right thing ought to trump how one appears to the Board. After all, the Board chose to award the project (and not to the lowest bidder, in this particular case, at that).

Thanks for the responses and validation.

RE: Credit for work not needed as a result of alternate means/methods

This does not appear to be an ethical issue, but a contractual one.

The credit issue should work both ways. If the contractor's chosen means and methods resulted in a higher cost than originally bid, would the owner be willing to pay extra? If the answer is "No", then the contractor should keep any savings he had.

I also disagree that pre-and post-inspections were not necessary. Even drilling in rock transmits vibrations than can damage adjacent structures. Should have been done either way.

RE: Credit for work not needed as a result of alternate means/methods

This would be the difference between firm-fixed price (FFP) and cost plus fee (CPF). An FFP contract places the risk on the contractor, so the profit or loss goes to the contractor, so long as the contractor terms have been met in full.

TTFN
I can do absolutely anything. I'm an expert!
homework forum: //www.engineering.com/AskForum/aff/32.aspx
FAQ731-376: Eng-Tips.com Forum Policies forum1529: Translation Assistance for Engineers

RE: Credit for work not needed as a result of alternate means/methods

If the contract bid item was for "Rock Excavation" and didn't specify the means and methods that the contractor was to use, the contractor can use whatever means and methods that get the job done that are allowed by the contract. The contractor probably planned on using the rotary grinder instead of drilling and blasting when he bid the job, thus potentially being able to lower his bid compared to other bidders. If as you say the bid item lumped all tasks associated with "Rock Excavation" into one bid item, then the contractor is not obligated to give the owner a credit for not doing the pre and post inspections that would have been required if blasting was used.

RE: Credit for work not needed as a result of alternate means/methods

Isn't there a "Law-Tips.com" site?
Oh wait, those guys don't do anything for free - even the free advise is credited for taxes.

RE: Credit for work not needed as a result of alternate means/methods

The contractor will not offer any savings. He will claim that the method he used cost just as much as blasting with supervision but was safer, quieter, had less vibrations, etc. Good luck getting a savings. If you ask for a savings, he will ask for an extra on another item.

www.PeirceEngineering.com

RE: Credit for work not needed as a result of alternate means/methods

If it's fixed price, he not only won't offer any savings- he shouldn't. He was clever enough to choose a superior method that met the spec without requiring the other controls. He also took the risk that it wouldn't work out and he'd have to do blasting after wasting money trying the other method. That extra money is his to keep for his cleverness and to compensate for his risk.

But we don't know the details of the contract. If there's some reimbursable component to it, there may be some room for negotiation.

Anyone paying attention should notice that if you want innovation, fixed price is more likely to give it to you than a reimbursable contract is. If you're making money on every dollar of material and labour expended, slow and painful wins the race.

RE: Credit for work not needed as a result of alternate means/methods

So the sum of it, the contractor was obligated to include costs in his bid for item that might possibly be required or might possibly not be required, and since those items are now not required, the owner wishes to get a refund?
That's like wanting a refund of your insurance premium since it turned out that you didn't need to collect on it.

RE: Credit for work not needed as a result of alternate means/methods

Right or wrong, if there is potential for repeat business from the buyer, it would be good marketing to refund the excess funds.

RE: Credit for work not needed as a result of alternate means/methods

This is the responsibility of the Contract writer. You can break your contract unit items down as fine as you want and include language to pay only for items actually used. We do this in tunneling contracts because of all the unknowns, but it makes for extensive Contract documents.

RE: Credit for work not needed as a result of alternate means/methods

If you break it out that way, that's great, but it moves the risk (with potential savings AND potential overruns) from the contractor to the owner.
In which case, that owner would balk at paying any of the extra items when they came up.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close