INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Steam Turbine Oscillating Working
2

Steam Turbine Oscillating Working

Steam Turbine Oscillating Working

(OP)

I have a question regarding the above subject as below:
There is a single stage steam turbine that is connected to a gear box and a pump.The rated BHP of turbine is equal to 1200 hp.But when we need lower BHP (near to 950 hp),we try to reduce the turbine RPM.But we face to big oscillation in throttle valve opening and consequently in turbine RPM and therefore in pump discharge pressure.
Would you please send me your answer to the followings:
1)What is the criteria for oscillating working of a steam turbine?
2)Is the above subject(oscillation in low bhp at a steam turbine)usual or not?
3)Are there any margin (in percent of rated bhp)for preventing the oscillation working of a steam turbine?
4)What are your suggestions and comments for eliminating of the mentioned oscillation?

RE: Steam Turbine Oscillating Working

2
The situation that you have described is not "USUAL", by which I mean "expectable" or "acceptable".  The situation that you have described is rather common, especially when commissioning a turbine driven equipment string, but should be solvable.  

The turn-down that you have described - from 1200hp to 950hp is not severe.  The turbine and controls should be able to handle this.  

There are too many variables that you have not described for anyone to be absolutely certain of the problem based only on your post, but it is a good guess that the control system is not properly functioning at the part-load condition.  This is sometimes called "hunting" - the control system is "hunting for the set point".  It might be necessary to change the control system settings (proportional range, sensitivity, reset) to try to improve the behavior.  

Certain mechanical conditions can also contribute to the problem: loose valve and/or control system linkage, or the governing valve settings are two examples.  If the position of one of the governing valves is near to its seat at the part-load, the sensitivity of the entire "turbine system" might be higher at part load than at full load, and thereby make the equipment string more vulnerable to "hunting".  Loose linkage is something that, by itself, will not cause hunting, but might contribute to it when it begins.  There is likely to be some hysteresis - asymmetry of the oscillations if the linkage is loose.

Control system settings should be reviewed - preferrably with the OEM.
At the part-load point you could try to slightly throttle the steam upstream of the turbine; either at the trip&throttle valve, or farther upstream.  DO NOT DISABLE ANY OF THE SAFETY SYSTEMS IN ORDER TO DO THIS.  If the steam pressure to the turbine is changed (reduced), the governing valve(s) must move to try to hold the load.  If the oscillation is reduced by throttling the inlet steam, the governing valve is "bouncing" around on its seat at unthrottled part-load.  Governor valve settings might be modified so as to improve the part-load response.


It is also possible - very unlikely, but possible - that there is some sort of flow oscillation in the process side, and the pump load is actually oscillating.  Rule out the turbine control system first.  Check turbine mechanical systems next, then look at the process flow.


RE: Steam Turbine Oscillating Working

Sir Poetix is absolutely right.  99% it is a control system problem.  

His suggestion to throttle the steam flow upstream of the throttle valve at partial load operation is the best (if possible).  This would shift the throttle valve operation away from unstable region and it should be again able of handling the whole system automatically.

Folks, Merry Christmas and Happy New Year to all of you.  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now