Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

All welded beam connection – are erection bolts needed?

Status
Not open for further replies.

StructureMan44

Structural
Joined
Dec 10, 2014
Messages
201
Location
US
We recently designed all bolted connections for some new steel inside a power plant. We did this to limit field-welding, eliminate the need for a “hot work permit”, and because we don’t have a way to check the quality of field welds. The erection Contractor has come back and stated they prefer fully welded connections; they don’t want to perform any field drilling. If I understand this correctly; OSHA 29 CFR 1926 states that the two bolts per end are still necessary to secure the beam before completing the connection:


My question is, can the Contractor get around this requirement by keeping the beam hoisted while they perform the welds on both sides (hopefully they keep the beam web vertical while it's hoisted)?
 
"During the final placing of solid web structural members, the load shall not be released from the hoisting line until the members are secured with at least two bolts per connection, of the same size and strength as shown in the erection drawings, drawn up wrench-tight or the equivalent as specified by the project structural engineer of record, except as specified in paragraph (b) of this section."
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top