×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Treating a Stream as a "Pond"

Treating a Stream as a "Pond"

Treating a Stream as a "Pond"

(OP)
For years, i have used Hec-Ras to produce flood elevations for streams including those that have culverts. I simply model the culvert in Hec-Ras.
I have just recently come across a project where a very renowned civil engineer received an approval from our state's DEP (NJ) by treating the stream and contours upstream of a culvert as a "Pond" and performed a pond routing.
He basically calculated the drainage area to the culvert and produced a peak flow (as one would have to do for a Hec-Ras analysis), and then modeled the pond using HydroCAD or similar to come up with a peak elevation.
The only thing i see wrong with this method is that it will not tell you a DEPTH of water at a point along the stream at say 1000 feet back from the culvert... but it will tell you a conservative number at close proximity to the culvert which is all that matters for this particular project.
The time of a Hec-Ras stream analysis would be say 80 hours.
The time to do this pond routing would be say 8 hours..... so there is a huge time savings.
Any thoughts? has anyone ever done this?
Replies continue below

Recommended for you

RE: Treating a Stream as a "Pond"

I've done it both ways. It really depends on how detailed an answer you need. If you're just trying to prove the ponding at the culvert isn't adversely impacted by upstream land development, then modeling it as a pond in both the predevelopment and postdevelopment conditions should be plenty good enough for your analysis, and the peak stage elevations at the culvert itself should be good enough to set your adjacent FFEs. As you say, they should be conservative.

If you're actually doing flood mapping, then obviously that analysis isn't enough. But then again, you're being paid a lot more for drawing a flood map than you are for checking a culvert near your land development project.

Hydrology, Drainage Analysis, Flood Studies, and Complex Stormwater Litigation for Atlanta and the South East - http://www.campbellcivil.com

RE: Treating a Stream as a "Pond"

How far up the stream do you cut the countours off and create the "pond" or are you chasing this all the way upstream?

RE: Treating a Stream as a "Pond"

a typical pond routing would attenuate the flow a little bit. a more conservative approach would be to just use the peak discharge as the design flow and then use culvertmaster or HY8 to calculate the ponding level at the culvert. really not sure why you would go to any trouble with a stage - storage - discharge pond routing unless this was a very small culvert / very high embankment (such as a dam)

RE: Treating a Stream as a "Pond"

When I've done streams as ponds, they're typically in fairly hilly watersheds, so it's no real problem to cut the contours off where they close naturally. I suspect that modeling a stream as a pond in very flat watersheds might produce more error.

Hydrology, Drainage Analysis, Flood Studies, and Complex Stormwater Litigation for Atlanta and the South East - http://www.campbellcivil.com

RE: Treating a Stream as a "Pond"

The only thing i see wrong with this method is that it will not tell you a DEPTH of water at a point along the stream at say 1000 feet back from the culvert...

Depth = your peak WSEL - Ground Elevation at point of interest

What am I missing?

RE: Treating a Stream as a "Pond"

1000 ft back from the culvert, you need to at least do a direct step method calculation (or something more robust like HEC-RAS's standard step method) to compute the equations of gradually varied flow. The pond approximation presumes no significant flow velocity upstream of the culvert.

Hydrology, Drainage Analysis, Flood Studies, and Complex Stormwater Litigation for Atlanta and the South East - http://www.campbellcivil.com

RE: Treating a Stream as a "Pond"

I thought the premise of this exercise was to ignore the use of HEC-RAS and simply use the headwater elevation computed from the culvert analysis.

We don't know his stream gradient and headwater elevation, so how do we know his headwater elevation does not reach back 1000' under this culvert analysis only premise?

RE: Treating a Stream as a "Pond"

who cares if the headwater goes back 1,00 feet. according to the OP, he doesn't care about what happens 1,000 feet away. if he did care, than this simplified culvert analysis only approach would not be appropriate and RAS would definitely be the way to go.

RE: Treating a Stream as a "Pond"

..If you're just trying to prove the ponding at the culvert isn't adversely impacted by upstream land development, then modeling it as a pond in both the predevelopment and postdevelopment conditions should be plenty good enough for your analysis..

We don't know this because the OP hasn't given any stream gradient or headwater information. For example, how far is upstream land developement?

What does the topo look like? Is it more channelized or does it look like an aerial of Lake Powell, with coves that can inundate at the headwater elevation?

RE: Treating a Stream as a "Pond"

the OP didn't mention anything about upstream development, so that is really not at issue.

RE: Treating a Stream as a "Pond"

Obviously both the experienced engineer and the State DEP saw merit in this analysis approach.

HY8 is approved by FEMA for floodplain modeling.

OP: What was the upstream length of ponding at the headwater elevation for the approved DEP study?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close