msquared48 - Is this your doing?
msquared48 - Is this your doing?
(OP)
Bridge burns down in LA, now this in Seattle. Interesting week.
http://www.foxnews.com/politics/2014/05/08/massive...
http://www.foxnews.com/politics/2014/05/08/massive...
RE: msquared48 - Is this your doing?
Hard to believe this thing will not start again, if at all, for at least a year.
So far, it's just a big cork.
Mike McCann
MMC Engineering
RE: msquared48 - Is this your doing?
RE: msquared48 - Is this your doing?
A 150' deep pit is needed to access the front of the tunneling machine to make the repairs.
A quick schedule from WSDOT at http://www.wsdot.wa.gov/Projects/Viaduct/Contents/...
• Late May: Begin building the access pit’s underground walls.
• Late July through September: Excavate the pit.
• October: Remove the machine’s cutterhead and begin repairing damage to the seal system and main bearing.
• February 2015: Test machine to ensure it is ready to tunnel beneath downtown.
• Late March 2015: Resume tunneling.
More information about the project at http://www.wsdot.wa.gov/Projects/Viaduct/
RE: msquared48 - Is this your doing?
It is better to have enough ideas for some of them to be wrong, than to be always right by having no ideas at all.
RE: msquared48 - Is this your doing?
The thing did not find any gators, but was stopped by a Gooeyduck.
Mike McCann
MMC Engineering
RE: msquared48 - Is this your doing?
The cost of repair is not simply the cost of the labor and materials for the repair itself. In order to get access to the machine a rather sizable hole has to dug, which requires reinforcements, etc., etc.; the hole to be dug is about 80 ft in diameter and 80 ft deep, but pilings have to be driven down to keep the hole from collapsing, and retaining walls need to constructed to keep water out. Additionally, the delay of the project itself incurs cost; people get laid off and rehired, plus critical personnel are put on retainer, plus cost of money for a extra year. It's likely that there is no spare seal, and a new one has to be made. That, in itself, is probably not particularly expensive, but the dismantling of the machine to get to the seal, installation of the seal, re-assembly of the machine, testing, etc., are probably the cost driver for the machine repair itself.
The machine itself is unique, building a new one probably incurs a 1 year delay all on its own, and probably will cost more than the original machine. Even if a new is built, the old one will need to be removed from the tunnel, which presumably incurs a large cost of its own; if that part were easy, that would probably have been the approach for the repair itself. I would guess the cost of the actual repair to be on the order of $10M to $30M, and the rest to be attributed to the stuff mentioned above. Note also, that the assembly of the machine when received took about 3-5 months, and while the repair of the machine doesn't require a complete assembly, it's a disassembly/assembly, so possibly 4 months just for that and the testing afterwards.
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers
RE: msquared48 - Is this your doing?
I have been following this fiasco for over three years now, and besides the political and ecological football of the existing viaduct which the tunnel is supposed to replace, I have found the boring machine issue to be very boring.
Personally, I think they should just purchase a few anti-gravity machines, strategically place them around the viaduct supports, and sell tickets to tourists to view the boring machine from the 150 foot shaft. Tourists will buy tickets to see anything. If enough tourists enter the tunnel, we could just pull up the ladder, fill it up with concrete, and create a national monument to political fiascos.
Mike McCann
MMC Engineering
RE: msquared48 - Is this your doing?
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers
RE: msquared48 - Is this your doing?
The pipe did cause it to stop, and someone did forget to remove it, who I can't remember, but the overheating of the bearings is another issue here, possibly connected, possibly not to the pipe issue, and that is why it is shut down now pending any repairs.
Mike McCann
MMC Engineering
RE: msquared48 - Is this your doing?
RE: msquared48 - Is this your doing?
RE: msquared48 - Is this your doing?
I wonder if it would be safe to back up the TBM while deconstructing the ~1000 feet of tunnel liner behind it, and servicing the cutter head at the original entry face. It sounds cheaper than excavating a cutter head sized well for access.
Mike Halloran
Pembroke Pines, FL, USA
RE: msquared48 - Is this your doing?
Mike McCann
MMC Engineering
RE: msquared48 - Is this your doing?
The obvious analysis of alternatives should have included:
> back the dang thing up, fix it, and run it back in
> presumably building a new one would require the previous alternative, and if that could have been done, a new borer would be superfluous
> dig a hole down to the borer head and repair in situ.
Which raises a question. What I read implies that the cutters themselves had been damaged by the pipe and replaced. So, how was that done? I assume that there was some method of doing that without a major effort, since that must be a probable thing to happen during a 4-yr dig. A bearing/seal, on the other hand, was apparently not expected to have be replaced.
As for the cutting heads, cutting what is likely to be sedimentary rock, which is essentially sandstone or limestone, is a different thing than going against hardened steel piping. That's probably more like immovable object versus unstoppable force. The pipe won, which I don't think should be that surprising.
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers
RE: msquared48 - Is this your doing?
RE: msquared48 - Is this your doing?
Sorry about that, my "sarcasm" key has been sticky lately, I'll have to have IT look at that.
It is better to have enough ideas for some of them to be wrong, than to be always right by having no ideas at all.
RE: msquared48 - Is this your doing?
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers
RE: msquared48 - Is this your doing?
These machines take years to build, get on site and operating. Also, they do not have a reverse. They only can move forward. Great foresite, huh?
Mike McCann
MMC Engineering
RE: msquared48 - Is this your doing?
http://www.thestranger.com/seattle/what-could-poss...
RE: msquared48 - Is this your doing?
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers
RE: msquared48 - Is this your doing?
RE: msquared48 - Is this your doing?
Also, because it's the largest such machine ever built, they can't just buy a used one, or parts of one, from somewhere else.
I wonder if they could leave it where it is, buy two (used?) TBMs of ~half the size, and drive two smaller tunnels instead of one big one?
Doesn't matter, really. It smells like the dispute over cost overruns, from estimates based entirely on fantasy, with local and state politicians trying so hard to screw each other, will spend decades in court.
Mike Halloran
Pembroke Pines, FL, USA
RE: msquared48 - Is this your doing?
Mike McCann
MMC Engineering
RE: msquared48 - Is this your doing?
"Any chance of starting another boring machine at the other end of the tunnel and working back toward the broken one, then removing both when old one repaired?"
Great, now we have two machines stuck... the tunnel isn't really needed... matter of filling the void with CLSM or something and forgetting about it...
Dik
RE: msquared48 - Is this your doing?
Can't disagree, Mike, but the point is/was that the bore path was known to intersect a number of these casings (18 or so if I remember right), the casings were left by borehole wells made by the state DOT for soil/rock sampling. Point being, if you knew the casings were in the way, would you not have designed/programmed the cutter head to manage them?
The surrounding earth being drilled is mostly compacted mud/clay and glacia "till" (mixed gravel and mud). Oh, and below sea level in a wet climate, so really wet too. Pretty much guaranteed to collapse unless you seal it. So, whent the seal failed...well, now we have a driller head buried up to its figurative armpits in mud.
RE: msquared48 - Is this your doing?
Mike McCann
MMC Engineering
RE: msquared48 - Is this your doing?
RE: msquared48 - Is this your doing?
Nevertheless, whatever the problems there, they pale in comparison to the southbound 80 to Bay Bridge transition, which, on, say, Friday nights, can take a couple of hours or more to get through to the city. I once decided to head down to the San Mateo bridge to cross the Bay, just to avoid the Bay Bridge. The Bay Bridge seems to do little relieve the congestion on the approaches.
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers