INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Resource Management - 10 projects, 10 resources, 1 project manager

Resource Management - 10 projects, 10 resources, 1 project manager

Resource Management - 10 projects, 10 resources, 1 project manager

(OP)
Hi everyone,

I am a PM of a group that has about 10 projects annually, and about 10 resources to spread around these projects. I would like to evolve from Excel to MS Project for resource management and scheduling.

Once I create a resource pool project (with no tasks), do I need to open ALL 10 projects at the same time in order to see resource allocation across all projects? These MS project files will stored be stored on a Sharepoint in different folders, so opening all 10 everytime I want to see the assignments for 1 resource seems inefficient.

Thanks,
Drew

RE: Resource Management - 10 projects, 10 resources, 1 project manager

In principle you don't have to open all projects. However, when having updated a project and saving it you may be asked if you want to update other projects all well.

While setting-up your projects, however, it is essential that you have opened the pool first in order to use the external resources.

Why an easy solution if you can make it complicated?
Greetings from the Netherlands

RE: Resource Management - 10 projects, 10 resources, 1 project manager

I would highly recommend you prioritize said project tasks between these projects to prevent skewed resource planning. For example if you don't prioritize this relatively small resource pool you have for their project tasks, what can happen is you can very easily end up with a resource working on a different project every day which "usually" isn't the norm (key word "usually). I had one project whereby a resource changed tasks every other day, he finally shared with me that he works a project tasks at least for a solid week before moving to another project or project task on the same project. It made sense then that we prioritized all our project tasks.

Honestly after all that effort this particular group that works on console for NASA running live software for active missions (launch or station), they quit using the MS Project resource planning all-together because of the cumbersome administrative requirements. Personally I think it can be very helpful for very specific types of projects, but in my years of doing this have learned many PMs get excited about the "idea" of using resource mgmt, but stop when they first hand experience at least MS Projects software variation of resource mgmt. It's not too terrible to me, but many feel it's too labor intensive for at least smaller projects.

RE: Resource Management - 10 projects, 10 resources, 1 project manager

Hi Drew,

I understand that you are dealing with resource-constrained scheduling of multiple projects that share many common resources. When you want to move away from Excel for this kind of scheduling, do you consider MS Project as the best alternative? All popular project management tools are inefficient for resource leveling across multiple concurrent projects.

RE: Resource Management - 10 projects, 10 resources, 1 project manager

I can not agree that MS Project would not be capable of handling scheduling conflicts across several projects. When you want to apply levelling for over-allocated resources you can specify to do this minute by minute, hour by hour, day by day, week by week or month by month.
It is indeed possible to assign priorities to Projects. When levelling priority, standard the Project priority in first taken into account and only subsequently the priorities within projects for individual tasks. You can also level individual tasks manually.
I would anyhow always perform Levelling calculations Manual.
Realize that no levelling changes will be performed within the chosen time-frame. This as MS Project assumes that the resource would handle possible conflicts itself within the specified time-frame.
AS a general rule Task Duration should be in units of about the same length as your updates, including status dates settings, are apart. So, setting tasks as days, with many 1 or 2 days duration, is not realistic if you update only once a month.

Why an easy solution if you can make it complicated?
Greetings from the Netherlands

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close