INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

MS Project Calculation for ACWP

MS Project Calculation for ACWP

MS Project Calculation for ACWP

(OP)
I have been attempting to use MS Project to track my hours spent on a job, remaining work, percent complete, etc. I was recently asked to start tracking the earned value data as well....So, I saved a baseline, loaded labor rates and got some good data.  The problem is, my ACWP does not agree with my actual hours spent on just some of the tasks. In other words, when I multiple labor rate times hours spent, most of the ACWP are correct but some are not.  Of course, this is throwing off the cost numbers for the entire job.  Any ideas?

RE: MS Project Calculation for ACWP

(OP)
I've spent the day trying to figure this out...one more piece of info.  It appears that MS Project is not calculating actual costs for any work performed ahead of schedule.  So, I have resources that have completed 50% of a task (and spent 50%) of the budget but my schedule shows they should only have spent 25% of time & budget.  MS Project stops calculating the actual costs after it hits the 25% mark.  So, it is still not showing accurate costs in the ACWP field.

RE: MS Project Calculation for ACWP

For EVA remember to use physical % comp. and configure msp to calculate eva using this value

RE: MS Project Calculation for ACWP

(OP)
That does change BCWP but it doesn't impact ACWP.  I need to track ACWP using spent hours that get reported to me weekly.  Project isn't calculating ACWP for anything that is completed ahead of schedule...even though we are completing work and incurring cost.

RE: MS Project Calculation for ACWP

You are right, I didn't read carefully your question.

Check the status date and if it is still not working properly check the field named AC (Actual Cost) and compare that one to the ACWP .
 

RE: MS Project Calculation for ACWP

i wonder if i can get any advise on free visual course for MS project ?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close