INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Total Overhaul of Schedule

Total Overhaul of Schedule

Total Overhaul of Schedule

(OP)
I inherited an MS Project 2003 .mpp that needs a total overhaul.  I have never done such extensive modifications.

Current:
5 days / week
M - F, 8 hrs /day (0800 - 1200, 1300 - 1700)
Single Shift
Non-Resourced

Needed Conversion:
6 days / week
M - F, 10 hrs / day (0700 - 1200, 1230 - 1730) & Sat, 8 hrs / day (0700 - 1200, 1230 - 1530)
Double Shift on part of the schedule
Fully Resourced

The effort was entered in as days for completion.  So, the conversion needs to not touch the duration.  It is understood that the Single Shift converted to the Double Shift should be one-half (or so, 8 hr day wrenches this) of the effort.

Man-hours and equipment-hours are to be extracted from this schedule.

Calendar setup and definition of working times as well as other details would be greatly appreciated.

Thank you all in advance.
Replies continue below

Recommended for you

RE: Total Overhaul of Schedule

(OP)
Thanks for the response and question, IRstuff.

The duration has already accounted for the double shift, i.e., the single shift duration represents the double shift production...Single Shift: 1 laborer / task = 8 hrs => Double Shift: 1 laborer / task = 4 hrs.

RE: Total Overhaul of Schedule

(OP)
IRstuff:  again, thank you for the reply and question.

Technically, the task duration is kept exactly constant, the double shift subtasks add up to the single shift subtasks.  The double shift subtasks are 1/2 (or so) of the single shift.

I believe that if I keep the duration the same and use 200% of a resource, I will arrive at the appropriate number of man-hours and I don't have to use a double shift schedule.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close