INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Vacuum Distillation Tower - Condenser

Vacuum Distillation Tower - Condenser

Vacuum Distillation Tower - Condenser

(OP)
Hi all

I am currently working on the project of a vacuum distillation unit and I'm facing some trouble with the vacuum system condenser of the vacuum tower. There will be a lot of fouling and accentuated corrosion.

Due to the necessity of little pressure drop on the system, the condensers (3 in total) will have to be located at much higher position than usual (100 ft instead of the usual 10-30 ft)

I am concerned mainly with three aspects:
- Maintenance;
- Installation of the ring test;
- Removal of the tube bundle;

The details are as follow:
- Condensers located at 31,5 m elevation (aprox. 100 ft)
- Condensers characteristics (total of 3 condensers):
- Area: 1 402,54 m² of exchange area (aprox. 15 000 sqft);
- Type : ASME Code Section VIII, Division 1;
- AXS type, dimensions: 1 829 mm x 6 096 mm ( 72" x 240"), tube bundle 3/4" BWG 14, ASTM A179
- Number of tubes: 3960 tubes per shell, pass = 23,8 mm (0.937"),
- Estimated weight of each tube bundle = 23.5 ton




Have any of you seen a similar situation: big dimension and weight AXS condenser installed at an altitude of 100 ft above ground level?

What is the frequency of repairs / maintenance / inspection activities in similar condensers?

How are maintenance activities handled (what kind of prevention is needed to protect the equipment from damage during maintenance)?

Are there any special tools / equipments used for maintenance in this kind of situation?

How is the 1st test made (ring test)?

How can the ring test (72" and 300 kg) be installed on the condenser at such height (100 ft)?
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close