INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Assigning multiple resources to a task

Assigning multiple resources to a task

Assigning multiple resources to a task

(OP)

Lets say I have a task that has two different people working on the task with each person having a different hourly rate.  For instance lets say that for Task A John worked 8 hours at a certain rate, and Frank worked 8 hours at another rate.  How do I account for both the individuals at different rates working a a task for a given day?
Replies continue below

Recommended for you

RE: Assigning multiple resources to a task

Why is that a problem?  If you entered their rates as different numbers, and you entered the total work hours, the total cost sums up correctly.

TTFN

FAQ731-376: Eng-Tips.com Forum Policies

RE: Assigning multiple resources to a task

(OP)
Thanks IRstuff

But what if I am in the Resource usage view and I have a particular task I want to assign multiple resources too.

For example, what if one of the tasks I have is to install pipe.  If both person A and person B installed this pipe, how do I assign both of these persons time to this task?  Do I do this in the resource view, or some other view?

Thanks for the help.

 

RE: Assigning multiple resources to a task

(OP)
If you double click on the task and add the resources directly it only lets you input a certain % of the time worked on the entire task.

I want to track the actual hours that each resource spends on each task on a daily basis throughout the duration of the task.

 

RE: Assigning multiple resources to a task

So, what's preventing you from inputting the hours directly in the Task Usage view after you've entered the resources?

TTFN

FAQ731-376: Eng-Tips.com Forum Policies

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login



News


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close