INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Graphical Indicators at sub-project / project level???

Graphical Indicators at sub-project / project level???

Graphical Indicators at sub-project / project level???

(OP)
Can someone tell me how to get graphical indicators to work at a rolled-up level?  I get can them to show up only at a task level but not at a sub-project or project level (rolled up tasks).  

Look at this link.  The yellow cells show the location where I would like indicators to show up.

http://files.engineering.com/getfile.aspx?folder=9a4d7f7e-0646-4911-a4e0-edb1a0b1bcc8&file=Project_Indicators.JPG






 

RE: Graphical Indicators at sub-project / project level???

Well, where are you getting the values that generate the graphical indicators?  Usually, you would set graphical indicator column's values to be equal to some other column that does rollup calculations.

TTFN

FAQ731-376: Eng-Tips.com Forum Policies

RE: Graphical Indicators at sub-project / project level???

(OP)
I'm doing various columns and calculations.  But for this particular example one of the column is a customized for completeness.  It takes the % complete values and breaks them into 0-33% (white circle), 34-66% (half circle), 67-100% (full circle).  

But still same problem.  The overall projects (A & B) have no associated indicator at all!

 

RE: Graphical Indicators at sub-project / project level???

(OP)
Yes, I figured it out.  There is an option within the customize fields, under Graphical Indicators.   I few boxes above that you can check: Nonsummary, Summary or Project Summary.   

RE: Graphical Indicators at sub-project / project level???

Normally, the default is to for the summaries to inherit the behavior of the lower level tasks.

TTFN

FAQ731-376: Eng-Tips.com Forum Policies

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close