wallerdf
Structural
- Aug 4, 2009
- 33
I am working on a design to transform an existing office building (60 psf) to an laboratory (120 psf by owner request). There are existing floor joists at 4 ft o.c. and the existing slab is good for about 300 psf @ 4' span. My solution was to come up between each joist with a new steel beam. It was more cost effective then stiffening the existing joists. I'm going to have them shim and weld the beam to the underside of the deck to ensure a tight fit.
In my design the joists have an I=171 in^4 and the new steel beams have an I=88.6 in^4. I distributed the floor load based on stiffness. 66% went to the joist and 34% went to the beams.
A fellow engineer disagreed with my approach. He said the slab was so stiff that essentially the entire load will be transfered to the joists and the beam would just be taken for a ride. His suggestion would be to make the beams moment of inertia as close to that of the joist. This would add approx. $30K to the job.
I feel the distibution of load is valid. For the beam to deflect it needs to take load, right. Any thoughts would be helpful.
In my design the joists have an I=171 in^4 and the new steel beams have an I=88.6 in^4. I distributed the floor load based on stiffness. 66% went to the joist and 34% went to the beams.
A fellow engineer disagreed with my approach. He said the slab was so stiff that essentially the entire load will be transfered to the joists and the beam would just be taken for a ride. His suggestion would be to make the beams moment of inertia as close to that of the joist. This would add approx. $30K to the job.
I feel the distibution of load is valid. For the beam to deflect it needs to take load, right. Any thoughts would be helpful.