I keep getting mixed up when I read section 2.3.6. Earthquake in API RP 2A... Could some one help me with the following?
Is designing the primary joints for the full brace capacity a must when the strength level earthquake is higher than 0.1 g?
What if I use the ductility level acceleration and check the joint punching against the brace actual load (Based on the ductility level)do i still have to check the joints against the braces full capacity?
Is designing the primary joints for the full brace capacity a must when the strength level earthquake is higher than 0.1 g?
What if I use the ductility level acceleration and check the joint punching against the brace actual load (Based on the ductility level)do i still have to check the joints against the braces full capacity?
RE: API RP 2A Earthquake requirements
**********************
"Pumping accounts for 20% of the world's energy used by electric motors and 25-50% of the total electrical energy usage in certain industrial facilities."-DOE statistic (Note: Make that 99% for pipeline companies) http://virtualpipeline.spaces.live.com/
RE: API RP 2A Earthquake requirements
If you "heard" it on the internet, it's guilty until proven innocent. - DCS