Revising Drawings for Construction
Revising Drawings for Construction
(OP)
I am currently working for the CM on a massive project in which many RFI's have come from the Contractor and many RFC's have come from the CM team. We have had some problems coordinating revised drawings that are issued to the Contractor. We are trying to push the Designer to revise and re-issue drawings that have several revisions made by RFI/RFC, but there is quite a bit of argument as to what constitutes a revision. Does any one know if there is a published "best practice" when it comes to how to deal with this? I am hoping it will settle the differences in opinion.
Thanks.
Thanks.
RE: Revising Drawings for Construction
In the mechanical world this is more or less defined between ASME Y14.100 & ASME Y14.35M.
However, I don't know about in your field, maybe there's a similar standard(s).
KENAT,
Have you reminded yourself of FAQ731-376: Eng-Tips.com Forum Policies recently, or taken a look at http://eng-tips.com/market.cfm?
RE: Revising Drawings for Construction
Unfortunately these issues should have been addressed in the contract. The fact they were not does leave a gap. It soundsl ike you have a system in place for capturing and processing the RFI's and RFC's. You will probably want to negotiate a procedure with them that covers the implementation of the agreed changes covering all aspects of processing the RFI's, changes, deviations, etc.
It does not make sense for every change to generate a revised drawing - that is one extreme. Nor does it make sense that none do - the other extreme. Somewhere in the middle is where you need to get to. For example, some changes will be captured by the contractor as as-builts. But that is something you will need to work out with your design contractor.
Greg Lamberson, BS, MBA
Consultant - Upstream Energy
Website: www.oil-gas-consulting.com
RE: Revising Drawings for Construction
Been there done that don't need to go back.
RE: Revising Drawings for Construction
You may have already tried this, or maybe I might be WAY off track about your problem. Sounds like a typical concern though.
RE: Revising Drawings for Construction
The contractor Jestergold is dealing with is not interested in what it says on the DOT website or anywhere else other than the contract they signed. If it's not in it, they don't have to do it or they will get paid extra for doing it.
Greg Lamberson, BS, MBA
Consultant - Upstream Energy
Website: www.oil-gas-consulting.com
RE: Revising Drawings for Construction
In any case, in the past few days, a new player has been introduced to the team. He is very responsive to my requests for new drawings, or at least a new way to transmit them to the Contractor. I'm keeping my fingers crossed that he is more pro-active than who I was battling before.
RE: Revising Drawings for Construction
RE: Revising Drawings for Construction
When we respond to an RFI, we generally include any sketches that may be necessary to clarify the direction. These are archived and the master CADD files are updated as we go.
If the design team involved in your project failed to include sufficient fees to cover decent Construction Administration efforts, this will be a long project. The Contractor is not responsible for the design, you don't want him to alter the Construction Documents that have your stamp on them.
Completing a construction project these days truly takes a team effort, while we've been involved in many "partnering" construction projects that turned out to be more confrontational than even traditional Design-Bid-Build projects, with a GC, we have had success with many of the larger Contractors in our ares.
Best of Luck,
EEJaime